Professional Documents
Culture Documents
a. logical relationships
b. the critical path
c. resource trade-offs
d. progress or status
2. A dependency that requires that an automobile be designed before the automobile can
be manufactured is an example of a(n) :
a. discretionary dependency
b. external dependency
c. mandatory dependency
d. scope dependency.
a. developing workarounds for problems that have led to project failures in the past
b. meeting schedule objectives by doing the job right the first time
c. reducing delays through better allocation of scarce resources
d. an increase in project risk
4. Your most recent project status report contains the following information: BCWP = 3,000,
ACWP = 3,500, and BCWS = 4,000. The schedule variance is :
a. +1,000
b. + 500
c. - 500
d. –1,000.
5. The delivery of a new computer system, a non-critical path activity, will be delayed. This
delay will not affect the overall outcome of the project. Because of the computer delay,
one should:
1
Mauro Sotille – Questões de Tempo
6. Which of the following best characterizes the scheduling technique called fast tracking?
a. meeting schedule objectives by doing the job right the first time
b. meeting schedule objectives by getting more cooperation from the stakeholders
c. reducing project duration by doing more work in parallel
d. motivating the team to work harder by setting aggressive target dates.
a. avoiding rework
b. link the communication controls
c. reduce the project duration
d. reduce project risks
10. A recent status report on a project reveals the ACWP=$1000.00, the CV=$100.000, and
the SV=$100.00. The BCWS=
a. $ 900.00.
b. $1100.00.
c. $1000.00.
d. $1300.00.
11. The is a network analysis approach developed to improve the scheduling of
projects whose activity durations could not be estimated accurately.
2
Mauro Sotille – Questões de Tempo
12. If an activity lies on the critical path, its total float will be :
a. the project manager may use float as a guide in making resource assignments
b. the project manager should generally use available float as early in the project as
possible
c. negative float is not of concern if enough activities have positive float
d. negative float can often be reduced by slowing the project expenditure rate
16. If the end date of an initial plan is later than the desired date, which of the following
should generally be tried first?
3
Mauro Sotille – Questões de Tempo
a. earliest start
b. latest start
c. latest allowable start
d. slack.
19. The is a technique used to predict project duration by analyzing which
sequence of activities has the least amount of scheduling flexibility.
20. The tool that provides a basis to identify the work that must be scheduled is the
a. Master schedule
b. Budget
c. WBS
d. Gantt Chart