3) The change control board, of which you are a member approves a significant scope change.
The first document that the project manager should updated would be the
Select one:
a. Schedule
b. Budget
c. Scope baseline
d. Work break down structure
4) The Bottom-up Approach for time and cost estimating is used when
Select one:
a. High uncertainty in project
b. Unstable Scope
c. Fixed price contract
d. Strategic and decision-making
7) The length of time required to recover the initial cash outlay on the project taking into
account time value of money is called
Select one:
a. Payback period
b. Internal rate of return
c. Discounted payback period
d. Return of Investment
8) When work packages have significant uncertainty associated with the time or cost to
complete, we use
Select one:
a. Bottom-up approach
b. Top-down approach
c. Range estimating
d. Phase Estimating
10) When the project size and scope are small, we prefer
Select one:
a. Responsibility Matrix
b. Work breakdown structure
c. Process break down structure
d. Organization break down structure
11) Which of the following generally cannot be validated using a work breakdown structure
Select one:
a. Quality control
b. Schedule control
c. Risk Management
d. Cost control
15) One of the most condition reasons why projects undergo scope change is
Select one:
a. Lack of Funding
b. Poor Work breakdown structure
c. Poorly defined statement of work
d. Lack of resources
16) Time - Constrain and Cost - Acceptable means
Select one:
a. Time is fixed, cost is fixed
b. Time is fixed , cost can be optimized
c. Time is fixed, cost overrun/under run is acceptable
d. Time is optimized, cost overrun/under run is not acceptable
17) The work breakdown structure "control points" for the management of a project are the
Select one:
a. Milestones
b. Work Packages
c. Activities
d. Constraints
18) Top - down approach is used for time and cost estimating when
Select one:
a. Fixed - price contract
b. Unstable scope
c. Cost and time are important
d. Customer wants details
22) Which of the following cannot be identified after performing a forward pass and backward
pass
Select one:
a. How much overtime is planned
b. Slack time
c. Dummy activities
d. Critical path activities
23) The amount of time a job can be delayed without affecting the early start time of any other
job is called
Select one:
a. Total Slack
b. Interfering Slack
c. Free Slack
d. Independent Slack