Professional Documents
Culture Documents
SECTION 13112:
KINGDOM
OFSAUDIARABIA
~~~1 4I,}JJ!
~I
forJubail&Yanbu
RoyalCommission cw.1~~1~1
SECTION 13112
SACRIFICIAL ANODE CATHODIC PROTECTION OF SUBMERGED AND BURIED UNDERGROUND
STRUCTURES
TABLE OF CONTENTS
PART 1 GENERAL............................................................................................................ 1
1.04 REFERENCES..................................................................................................... 2
1.05 DEFINITIONS....................................................................................................... 3
1.06 SUBMITTALS....................................................................................................... 6
1.11 INTERFACES..................................................................................................... 12
3.02 INSTALLATION.................................................................................................. 17
PART 1 GENERAL
A. The Contractor shall design, install, commission and document a sacrificial anode
cathodic protection (CP) system of submerged and buried underground metallic
structures. The purpose of the CP system is to prevent external corrosion of
submerged and buried underground metallic structures, such as piping and sheet
piles, by passing a low voltage (direct current) from a galvanic anode to the metallic
underground structure.
B. The Contractor shall furnish all labor, materials, tools and equipment required to
complete the Work.
A. This Section establishes the general criteria for the design, installation and
commissioning of cathodic protection (CP) of submerged and buried underground
metallic structures as required for corrosion control. The cathodic protection system
is of the sacrificial anode type, providing sufficient current to the structure to be
protected with the current sufficiently distributed so that the selected criteria for CP
system operation are effectively achieved.
1.04 REFERENCES
A. The referred codes and standards are intended to provide an acceptable level of
quality for materials and products. In case of conflict between these References and
the text of this Specification, the Specification text shall govern.
B. The latest revision of the referred codes and standards shall be used wherever
applicable. In case of conflict between codes and standards, the Contractor shall
conform to BS EN standards.
1.05 DEFINITIONS
D. bond: Metal conductor, usually copper, connecting two metallic points on the same
or on different structures usually with the intention of making the points equipotential.
E. buried structure: Any metal construction built or laid beneath ground level or built
on ground level and covered with earth.
corrosion by installing a sacrificial anode or impressed current system that makes the
protected object cathodic and thus resistant to corrosion.
S. electrolyte resistivity: The specific resistance of the electrolyte assuming that the
electrolyte is homogenous. Note: Usually expressed in ohm.meter (Ω·m).
T. galvanic anode: Electrode that provides current for cathodic protection by means of
galvanic action.
U. galvanic anode station: Station which comprises the equipment and materials
required to provide cathodic protection by the use of galvanic anodes. Such materials
and equipment will include galvanic (sacrificial) anodes, cables, and test facilities.
water.
X. insulated flange: Flanged joint between adjacent length of pipe in which the nuts
and bolts are electrically insulated from the flange(s) and the gasket is non-
conducting, so that there is an electrical discontinuity in the pipeline at that point.
AA. IR free potential: Structure to electrolyte potential measured without the voltage
error caused by the IR drop due to the protection current or any other current.
BB. isolating joint: Electrically discontinuous connection between two lengths of pipe,
inserted in order to provide electrical discontinuity between them, e.g. monobloc
isolating joint, insulated flange.
CC. measuring point: The point of which the actual measurement takes place. Note: In
the case of structure to electrolyte potentials this refers to the location of the
reference electrode.
EE. ON potential: Structure to electrolyte potential measured with the cathodic protection
current flowing.
GG. polarization: Change in the potential of an electrode (e.g. structure) as the result of
current flow to or from that electrode.
JJ. protective current: Current made to flow to a metallic structure from its electrolytic
environment in order to effect cathodic protection of the structure.
KK. protection potential: Structure to electrolyte potential for which the metal corrosion
rate is acceptable.
OO. service life: The time until safety, serviceability and acceptable appearance of the
structure or its main components falls below a defined minimum level or requires
unduly high costs for maintenance and repair.
PP. stray current corrosion: Corrosion caused by electric current from a source
external to the intended electrical circuit, for example, extraneous current in the
earth.
QQ. structure: Metallic construction, whether coated or not, which is in contact with an
electrolyte (e.g. soil, water). Note: The structure may represent a construction of
great length, such as a pipeline, pipe networks, underground electric cables, or well
casings as well as constructions on a smaller scale such as piles, sheet pilings, tanks
or other underground constructions.
SS. test station: Installation that provides measuring and test facilities for the buried
structure. Note: Such installations will include cabling and structure connections.
TT. zinc electrode: Measuring electrode made from sufficiently pure zinc.
1.06 SUBMITTALS
A. The Contractor shall submit to the Royal Commission, under the provisions of
SECTION 01330, the following items for review and approval before commencing
Work:
1. Manufacturer's Data
2. Shop Drawings
3. Calculations
c) The detailed calculations to support the design shall include but not be
limited to the following:
1) Cathode Current Requirement
(a) Calculation of surface area and current demand including
initial/final and average current and current drain in the
actual environment. If the structure is coated, the coating
break down factor shall be included.
2) Anode System Requirement
(a) Calculation of anode mass, number, type, dimensions,
resistance and current capacity including initial and final
current.
3) Circuit resistance of each component.
4. Method Statements
6. As-Built Drawings
A. The Contractor shall be responsible for the quality of work and shall develop and
propose programs and methods of construction and testing to achieve the specified
quality to the approval of the Royal Commission in accordance with
SECTION 01450.
B. The design, installation and commissioning of the CP system shall meet the Royal
Commission’s Quality Control standards. In addition, the CP system component
manufacturer’s own recommended installation procedure, material standards and
procedures shall be recognized as part of this Specification. No deviations to the
present specification or the manufacturer’s recommendations shall be permitted
without prior written agreement by the Royal Commission. The Contractor and
Subcontractor shall review and remain cognizant of all other specifications related to
this scope of work.
1. The Contractor shall be responsible for the coordination of all works relating to
the cathodic protection systems. It shall be the responsibility of the Contractor
to ensure that all work and equipment to be furnished under the Contract
results in a complete and satisfactory installation.
2. All work shall be carried out under the supervision of an experienced Cathodic
Protection Engineer. The Cathodic Protection Specialist/Engineer shall have a
Degree in Electrical or Electrochemical Engineering or Science Degree in
Physics or Chemistry from a recognized Institution, a minimum of 10 years
practical experience in cathodic protection design, installation and
commissioning. A professionally qualified NACE Certified Cathodic Protection
Specialist or a professional member of the Institute of Corrosion with a
bachelor degree in physical science or engineering is preferable.
3. All Contractor’s engineers and supervisory staff involved with the installation of
the cathodic protection (CP) system shall have had at least 3 years experience
in this type of work and the Contractor shall provide Resumes to the Royal
Commission for review and approval.
5. Supervision shall be carried out to a high standard throughout the works. All
equipment shall be inspected upon delivery and again prior to installation.
Inspection hold points shall be introduced for items or works which will be
buried so that assurance and responsibility is recorded for all items or works
prior to backfilling.
6. Any defects shall be reported to the Royal Commission and shall be recorded
in a retrievable data system. Corrective actions, which must be approved by
the Royal Commission, shall also be recorded.
7. The Contractor shall submit a quality plan, detailing his proposed procedure for
Quality Control, for review and approval by the Royal Commission.
8. All testing and commissioning work shall be carried out by the above Cathodic
Protection Specialist. Staff those are deemed to have insufficient experience
shall be prohibited from carrying out critical work tasks as described in the
relevant parts of the Specification. In such cases, replacement manpower and
any delays incurred shall be borne by the Contractor.
3. Contractor
B. In the absence of any of the above, best accepted industry practice shall be
employed throughout.
A. System Description
a) Anode System
1) Consisting of the sacrificial anodes, associated cables, and all
b) Cathode System
1) Consisting of the metallic structure to be protected as well as
structure continuity ties.
c) Monitoring System
1) Consisting of reference electrodes and test stations, test
connections to the structure and data acquisition system.
2) Remote monitoring, automatic control and data acquisition system
shall be as specified in the approved Contract Drawings/
Documents. For remote monitoring and control system refer to
SECTION 13450.
a) The acceptance criteria are given for the IR free potential measured with
respect to a copper/saturated copper sulphate reference electrode or a
silver/silver chloride reference electrode.
A. Examine conditions of the Project site and the underground or submerged structures
for which the CP is to be installed. Inspect for interfering structures, other current
inducing systems and other installed CP systems in proximity, which may affect
operation. Field surveys shall be performed to evaluate the applicability of using the
sacrificial anode system. The installation shall not proceed until all unsatisfactory
conditions have been corrected.
B. Verify that all submerged and buried underground metallic structures and other
nearby metallic structures, including reinforced concrete structures, are electrically
continuous if necessary (see par. 1.09 B.1.d). Verify that the appropriate
methodology of producing continuity is in place (see par. 3.01 B). Verify that bonding
cables are present for those metallic components not yet placed, but to be installed.
Continuity shall be verified utilizing the approved method statement. If discontinuity
exists, document such conditions and verify that corrections are made.
1. Document continuity test results, which will include test location and resistance
reading. All resistance readings shall be recorded on a plan sheet designating
each location to be tested.
2. Any affected discontinuous steel must be bonded, (see par. 3.02 B), to the CP
circuit using external cabling materials and procedures, which duplicate those
for test connections.
3. Following bonding, the new continuity test results shall be documented on the
plan sheet. An original plan sheet shall be provided to the Royal Commission
for review and approval following continuity tests.
1.11 INTERFACES
A. The Contractor shall identify and define all interfaces between his works and other
parties’ work, including other plant and systems under the responsibility of the Royal
Commission, Industry, other Contractors' plant and systems and third parties' plant
and systems. The Contractor shall keep updated records of all interface agreements
made with other parties.
1. Integration with the Royal Commission remote monitoring system. For each
test station, the physical interface, the communication protocol, and the data
format and content shall be defined and agreed with the Royal Commission.
A. The Contractor shall deliver, handle and store equipment and material in accordance
with SECTIONS 01650 and 01660, as well as fulfill the following requirements:
1. Deliver all CP components to the Project site in such quantities and at such
time as to ensure the continuity of installation. Each component shall be
securely wrapped, packaged, labeled and marked for safe handling.
Components shall be stored in a secure and dry storage facility to prevent
damage, distortion or deterioration. Components shall be handled in such a
way as to ensure against damage and that identification markings remain
clearly visible.
PART 2 PRODUCTS
2.01 GENERAL
A. All goods and products covered by these Specifications shall be procured, when
available, from an in-Kingdom manufacturer. Procurement of all goods and products
manufactured out-of-Kingdom must be approved by the Royal Commission.
2.02 ANODES
A. The sacrificial anode CP system shall comprise anodes as specified in the approved
Contract Drawings/Documents. The proposed anodes shall be manufactured by a
standard manufacturer company in accordance with NACE RP0387 and RP0492.
B. The sacrificial anodes shall have a minimum operational design life of 15 years in
which individual anode elements shall be capable of providing current continuously at
the selected design rating.
A. The Contractor shall furnish reference electrodes as per the approved Contract
Drawings/Documents, not limited to following:
1. The reference electrodes shall be appropriate for the environment that the
metallic structure to be protected are exposed to, whether it is sea water,
brackish water, fresh water, soil, etc. The reference electrodes commonly used
in sea water are silver/silver chloride (Ag/AgCl) or zinc (Zn) while
copper/copper sulphate (Cu/CuSO4) is most suitable for use in non-chloride
contaminated soil and fresh water (only for a short exposure time), but other
reference electrodes may apply. Zinc reference electrode shall be supplied
with bleeder to avoid contamination of the electrode surface.
5. The reference electrodes shall be provided with test certificates showing the
reference electrode type, theoretical potential and test potential against an
approved standard reference electrode.
A. Test stations shall be of corrosion resistant materials and fitted with a permanent
engraved label as per SECTION 16075 with a location reference. Each test station
shall contain terminals for monitoring the potentials of the structure with respect to
the reference electrodes. Each terminal shall be fitted with an engraved traffolyte
label with a reference number, which shall be proposed by the Contractor and
approved by the Royal Commission.
A. Insulation kits shall be used to electrically isolate the sections of pipelines, if required
in order to avoid leakage of cathodic protection current and to enable control of the
CP system. The insulation shall comprise gaskets with insulating sleeves and
washers. The details of the insulation kits and installation procedures shall be
submitted to the Royal Commission for review and approval.
B. Two insulation kits shall be installed, one at each flange of a valve in existing valve
chambers. In absence of valve chambers, buried insulation kits may be installed
subject to approval by the Royal Commission.
C. The insulation kits shall be made of a material which has the following properties:
A. The cables shall be capable of direct burial in salt-laden moist soil environments.
Cross sectional area of the anode cables shall be a minimum of 10 mm2 for power
carrying cables and a minimum of 4 mm2 for monitoring cables. Insulation for the
cables shall be high molecular weight polyethylene (HMWPE). Alternate materials,
which may be considered for approval, include XLPE and KYNAR.
3. Reference electrode cabling from the junction box to test stations shall run in
conduit and may be screened multi-core, multi-strand type.
D. All cables shall be terminated by crimped connectors suitable for the terminals
provided in the junction boxes. All cables and wiring shall be appropriately identified
within 25 mm of each end using permanent wire markers intended for the purpose.
Where cable identifications have been given in the Contract Drawings, these shall be
used. For termination of wires and cables, refer to SECTION 16150. Adhesive type
markers are not acceptable.
PART 3 EXECUTION
3.01 PREPARATION
1. The resistivity measurements shall be carried out for the environment of the
metallic structure using an AC resistance instrument or a conductivity meter.
B. Electrical Continuity
2. Unless alternative test procedures and criteria have been selected in the
design, the electrical continuity between the metallic structures shall be tested
by DC reverse polarity resistance measurement technique. This technique
measures and compares the resistance using a DC resistance instrument and
then reversing the polarity of the test leads.
C. Potential Survey
3.02 INSTALLATION
A. Anode Installation
a) Prior to installation, all the anodes shall be inspected for any damage.
Anodes that do not conform to the Specification shall be rejected.
d) All wire insulation shall be compatible with the high chloride, high
temperature environment.
B. Test Connection
C. Reference Electrodes
A. General
1. The testing and commissioning of the system shall be carried out under the
direct supervision of the Contractor’s Specialist Cathodic Protection Engineer.
A minimum notice of 1 week shall be given to the Royal Commission before
commissioning takes place to enable scheduling the presence of Royal
Commission’s CP Specialist, if so required by the Royal Commission.
2. The results of the testing and commissioning report shall be submitted to the
Royal Commission within 1 week of completion.
3. If the results from the testing and commissioning do not meet the performance
requirements, the Royal Commission at their discretion may instruct that the
commissioning exercise be repeated in part or in its entirety.
B. Pre-Commissioning Survey
C. Visual Inspection
D. Preliminary Checking
1. The potentials of the metallic structures and anodes shall be measured with
respect to the permanent reference electrodes at all test stations and
supplemented by portable reference electrodes.
1. The potentials of the metallic structures and anodes shall be measured with
respect to the permanent reference electrodes at all test stations and
supplemented by portable reference electrodes, in order to signify an adequate
level of protection for all the facilities.
a) Anodes shall be connected to the metallic structure via the test stations
where relevant (to be approved by the Royal Commission). 2 weeks
after connection (energizing) the IR free potentials of the metallic
structures shall be measured and recorded at all the test stations.
Where the anodes and metallic structure are connected via the test
station, the potentials shall be measured 'ON' and 'INSTANT OFF,' while
in all other situations the 'ON' potential is considered similar to the IR
free potential.
c) If the potentials recorded do not meet the design criteria, further action
shall be taken, e.g., the system shall be left for a longer period of
polarization or additional anodes shall be installed. The requirement for
remedial measures shall be agreed upon by the Royal Commission.
F. Operation
1. The Contractor shall operate the CP system for the period until the Royal
Commission’s initial acceptance of the CP system. After acceptance, the
Contractor shall operate the system for 1 year. The operation shall as a
minimum include performance monitoring and system review after 1, 3, 6 and
12 month.
A. General
B. Test Procedures
1. The ‘as found’ potentials of the metallic structure and other facilities located in
close vicinity shall be measured before the commissioning of the CP system.
4. The Contractor shall submit full details for carrying out interference testing for
review and approval by the Royal Commission.
2. The test report shall include all data obtained, details and location of all tests
and report the level (if any) of interference observed. Recommendations for
rectification shall be included. Three copies of the test report shall be
submitted to the Royal Commission.
A. An Operation and Maintenance Manual shall be provided by the Contractor and shall
be a complete and comprehensive reference manual with all relevant information
within one document. The Operation and Maintenance manual shall be provided in
accordance with SECTION 01830.
B. The Contractor shall submit a procedure, as part of the Operation and Maintenance
Manual, detailing how the CP system should be managed. This management shall
include criteria, fault finding, system malfunction checks and details of presentation of
data.
C. The Contractor shall prepare a monitoring program for the CP system. The program
shall as minimum include the following measurements to be carried out every
12 month:
3. Steel structure potentials (IR free) for all reference electrodes at test stations.
6. Interference testing.
A. Description
1. As part of the works, the Contractor shall provide training to nominated Royal
Commission staff in the operation and maintenance of the CP system,
including the system monitoring.
2. Each person trained shall be provided a full set of the course material. All
training material shall be supplied by the Contractor for training purposes.
4. The minimum requirements for these are outlined below. Instruction may take
place in any order and at various times within the Contract period.
B. Routine Operation
1. The data collected from the manual monitoring system and that from periodic
surveys shall be reviewed by an experienced Cathodic Protection Engineer.
Instruction shall be provided on the trend analysis of data and the type of data
required and changes in its recorded level which may signify that the CP
system requires adjustment or some form of remedial action.
END OF SECTION