Professional Documents
Culture Documents
1 INTRODUCTION ..................................................................................................................... 3
1.1 BRIEF DESCRIPTION ................................................................................................... 3
1.2 PURPOSE OF VERIFICATION ...................................................................................... 3
1.3 ABBREVIATIONS ........................................................................................................ 3
2 BASIC DESIGN PARAMETERS .............................................................................................. 4
3 DESIGN ASSUMPTIONS ........................................................................................................ 5
4 DIMENSIONS & LOADINGS ................................................................................................. 6
4.1 WEIGTH & DIMENSIONS OF ELECTRICAL PANEL ...................................................... 6
4.2 BASIC LOAD CASE .................................................................................................... 6
4.3 COMBINED LOAD CASE ........................................................................................... 6
5 COMPUTATION OF DESIGN MOMENT ............................................................................. 7
6 CHECK ON EXISTING FLOOR SLAB ................................................................................... 9
7 FLOOR HOLE STRENGTHENING ........................................................................................ 15
8 CONCLUSION ...................................................................................................................... 18
1 INTRODUCTION
1.1 BRIEF DESCRIPTION
Two additional floor openings are required on a panel at the Substation to enable
access for Electrical Switch Gear HV and LV cables.
For purpose of clarity, only 8 panels to the left of the expansion joint were
considered in this verification analysis.
Future load due to switchgear has been covered within the applied blanket floor
live load of 20 kN/m2, hence no additional load is applied in this report.
Calculated design bending moment when applying the continuous beam
approach, is greater than the bending moment in the existing Structural Design
Therefore, as a conservative design, one-direction was considered for the
verification analysis of the floor slab.
Further strengthening will be done under the floor opening with L 100 x 100 x 10
section and M8 (12mm) HSL-3 heavy-duty expansion anchors as per Hilti Anchor
Fastening Technical Guide to withstand loads from the Electrical panel.
To check for the suitability of existing concrete slab with two additional floor
openings.
1.3 ABBREVIATIONS
BM - Bending Moment
DL - Dead Load
FAR - Field Auxiliary Room
HV - High Voltage
LC - Load Condition
LL - Live Load
LV - Low Voltage
SF - Shear Force
SLS - Serviceability Limit State
SS - Substation
UC - Unity Check
ULS - Ultimate Limit State
2 BASIC DESIGN PARAMETERS
Basic design parameters were adopted from the existing reference documents.
Concrete cover, c = 40 mm
3 DESIGN ASSUMPTIONS
STAAD.Pro software was utilized in the concrete floor slab analysis for BM and SF
for continuous beam with 1m strip.
Validation/check at the critical section was done for 2m after considering twice
the BM and SF from the 1m-strip analysis.
BS 8110-1: 1985 was used for uniformity with existing floor slab verification
calculation.
Conservatively, the existing floor slab is assumed to be cracked.
At the critical section, the effective width equals cut section plus twice the slab
thickness on each side. See [Fig. 6.1] and Section 3.1, [Ref. 3].
Design assumptions are as per referenced documents.
4 DIMENSIONS & LOADINGS
4.1 WEIGTH & DIMENSIONS OF ELECTRICAL PANEL
Weight of new Electrical panel = 1,000 kg = 10 kN
Concrete cover c = = 40 mm
Floor Slab thickness h = = 260 mm
Yield strength of steel fy = = 460 N/mm2
Using unit length approach b = = 1,000 mm
Diameter of main reinforcement Ø = = 20 mm
Effective depth d = h - c - Ø/2 = 210 mm
Design moment at Grid 'E' (strength check) MEd = = 88.2 kNm/m
K = MEd/bd2fcu = 0.067
z = d[0.5 + (0.25 - K/0.9)1/2] = 100.3 mm
0.95d = 199.5 mm
Bar spacing provided s = = 200 mm
Minimum area of reinforcement required As,min = 0.13% x bh = 338 mm2/m
Area of reinforcement required without considering cut section As,rw = Mmax /0.87fy z = 1,105 mm2/m
Area of top/hogging reinforcement adequate for existing floor slab As,prov = T20 @ 200mm = 1,570 mm2/m
Before opening of floor slab, capacity utilisation = 1,105 < 1,570 UC = 0.70
COMPUTATION OUTPUT
Check for shear resistance
Concrete cover c = = 40 mm
Floor Slab thickness h = = 260 mm
Yield strength of steel fy = = 460 N/mm2
Diameter of main reinforcement Ø = = 20 mm
Effective depth d = h - c - Ø/2 = 210 mm
Stress would be redirected on each side of floor opening to (2 x h) after
2h = = 520 mm
cutting reinforcement at floor opening
Approximate width of cut sections cs = = 500 mm
Effective width of slab affected by cut be = 1943 mm = 2,000 mm
Reduced width of slab considered br = be - c s = 1,500 mm
Effective depth d = h - c - Ø/2 = 210 mm
Design moment (due to effective width) Me = MEd x be = 176.4 kNm
K = Me/bd2fcu = 0.089
Minimum area of reinforcement required As,min = 0.13% x bh = 507 mm2
Area of reinforcement required considering cut section As,rc = Me/0.87fy z = 2,209 mm2
Area of top reinforcement provided on floor slab due to reduced width As,r = br x As,prov = 2,355 mm2
After opening of floor slab, capacity utilisation increased to = 2,209 < 2,355 UC = 0.94
COMPUTATION OUTPUT
Check for shear resistance