Professional Documents
Culture Documents
uk
You can use this template for creating Sprint Burndown charts. The example is for a typical 2-week Sprint in which story po
Sprints can be a maximum of 4 weeks. Simply adjust the number of rows in the data table to reflect your Sprint length. The
dividing the total estimated capacity of the team in the Sprint (in this case, 120 story points) by the number of working day
row of the first 'Planned' column (under 'Burned Down'). The actual burndown is created by entering the estimated size of
'Actual' column under 'Burned down' . Remember Burndown reports the estimated effort remaining over time. This will be
estimates are not used
Trend Line
Actual Burndown
5/19/2014
Sprints Burned down Balance Completed Added to
Remaining Planned Actual Planned Actual in Sprint Sprint
5 60 53 300 300 53 0
4 60 64 240 247 64 70
3 60 65 180 253 65
2 60 66 120 188 66
1 60 #N/A 60 122 #N/A 350
0 60 #N/A 0 #N/A #N/A
300
250
200
150
100
50
0
5 4 3 2
Trendline
Actual Burndown
4 3 2 1 0