Professional Documents
Culture Documents
Tutorial 3
Tutorial 3
1. List down and discuss the various types of certificates an architect is empowered to
issue in a building contract
-Interim Certificate, this certificate issued is to allow the contractor to claim payment of
work done from the client or developer. In the PAM2018 clause 30, the contractor
submitted a payment application for interim claim with the complete details and
particulars as required by the Architect or Consultant Quantity Surveyor. Then, the
Architect or CQS/ M&E Engineer will go to the site to ascertain the amount claimed by
the contractor. CQS is to issue a valuation certificate including M&E Enginneer’s
recommendation to the Architect within 7 days and upon receipt of CQS valuation
certificate; the Architect must issues Architect Certificate to the employer within 21 days
from receipt of contractor’s claim. After receipt of the Architect certificate; the employer
shall need to pay the amount certified to the Contractor within the Period of Honoring
Certificates.
-Final certificate, this certificate is issued by the Architect signifies that the Contractor
has completed his various obligations under the contract. This certificate shall be issued
upon the issuance of the Certificate of Making Good Defects and the Consultant
Quantity Surveyor must also complete the Final Account within the period as stipulated.
Moreover, the period to complete the final account by CQS is stated in the appendix. If
none is stated it shall be 15 months from the date of Certificate of Practical Completion.
The final payment to Contractor; Architect shall issue a Final Certificate to the
Employer. Additionally, Final certificate shall be issued within 28 days after Certificate of
Making Good Defects has been issued or within 21 days after the period of honoring of
certificate for the payment of the Penultimate Certificate. Final Certificate contains final
payment to Contractor based on the Final Account less all sums certified in previous
payment certificates to Contractor.
-Penultimate certificate
Once the penultimate certificate has been issued, it means that there is no more work
to evaluate and trigger the final progress payment. Only remains the final certificate that
has not been issued by the Architect. This certificate is required to be issued by an
Architect not later than fourteen days after the Certificate of Making Good Defects has
been issued for penultimate payment. The difference between penultimate certificate
and normal certificate for a progress payment is that the half of the retention sum which
is 2.5% has been released. Apart from this, the penultimate payment shall be made by
the Employer within the period of honoring certificate (21days). There will be no further
payments will be made until any of the defects have been rectified and the final
certificate is issued. At this point, the final payment will be made, including the release
of the remaining retention fund.
A provision is a legal clause that is designed to protect the interests of one or all
of the parties involved in a building contract. As an employer, he/she has the
responsibility of taking one of the important provisions that should be listed on the
building contract which is the contingent payment provisions. The contingent payment
provisions had a common concern among contractors in the construction industry is the
risk of non-payment for work that has been completed . If the provision is clearly
expressed as setting a condition precedent in which the general contractor is not
obligated to pay the subcontractor unless payment is received by the employer, it is
considered a pay-if-paid provision.
Interim Certificates are being used oftenly in the building construction contracts
and it is only to be issued by the architect at regular intervals based on periodic
estimates of the value of works properly executed and materials and goods supplied for
the works. In order to arrive at an amount due in interim certificates, interim valuations
are to be carried out upon receipt of the contractor’s claim with details and particulars.
In addition to issuing the Interim Certificate, the Architect is also required to direct
the Contractor as to the amounts payable to any of the Nominated Sub-Contractors and
Nominated Suppliers under the Interim Certificate. Other than that,the Architect also
informs or notify the relevant Nominated Sub-Contractor and Nominated Supplier as to
the amounts due to them under the Interim Certificate.