Assumption
Cost of Sika Top-Seal cement and sand mix (1:3) = RM 2763.85 per m3
Output of spreader = 3m2 per hour
No. of labourer = 1 persons
Wages of labour = RM 60 per day
Working hours = 8 hours per day
Working days = 26 days
Material waste = 5%
Profit and overhead = 10%

Material Cost RM RM/no


Cost of cement and sand (0.02mx RM 2763.85/m3) = 55.28
Material waste= 55.28x5% = 2.76
Cost of material per m2 = 58.04
Cost of material per m= RM58.04x0.15m = 8.71

Labour Cost
i) Laying a 20mm thick bed (2:1)
Cost of labourer per hour (1xRM 60/8)/6m2 = 1.25
Total labour cost per m2 = 1.25
Additional labour (25%) = 0.31
Total labourer per m2 = 1.56
Total labour cost per m= Rm 1.56x0.10m = 0.16

Total cost for 20mm thick cement and sand (1:3) to outlet = 8.87
Add profit and overhead (Rm8.87x10%) = 0.89
Total Unit rate (RM/no) = 9.76

Rounding up = 9.80