Conventional Shuttering Planning Calculations

C- Type Building (3No's)

A Area Statement

3 Blds/ G+7/ Each floor 8 flats/ 3 blds x 7 floors x 8 flats = 168 flats (units)
Each floor area 881 m2 x 8 slabs + terrace 55 m2 = 7103 m2 for each building
Total for 3 building = 7103 m2 x 3 blds = 21309 m2 ( 2,29,285 sft)
Shuttering Planning 1 set of 881 m2 to each blds.= 881 m2 x 3 blds = 2643 m2
So, Repetation of shuttering = 21309/2643 = 8 Repetation

B Construction Schedule

As per Bar RCC finish


Start Finish
Chart Date
C1 03-04-20 26-07-21 30-01-21
C2 27-05-20 18-09-21 25-03-21
C3 25-07-20 16-11-21 23-05-21

C Shuttering Material Calculation Details (881 m2 plain area- for 1 building)

C.1) For Columns ( total 128 no's)

Assume 25 column sets of 230x600x2.55

Material Description Unit MF Quantity Calculation

1) One Ply Area=2.97 Sqm,


8'x4' Ply Nos - 36 2) Total Area= ((0.23+0.6+0.23+0.6)*2.55)* 20 =35.4 Sq.M
3) No. of Ply=35.4/2.99= 36 Nos

1) Assume 60 Rft Required for One Ply.


2"x3" Silver Patti Rft 60 Rft/Ply 2160
2) Total Qty= 36*60 = 2160 Rft

1) Assume 20 Rft Required for One Ply.


3"x4" Back Timber Chavi Rft 20 Rft/Ply 720
2) Total Qty= 36*20 = 720 Rft

1) Assume 8 Nos Required for One Column


Shikanja 3 ft Nos 8 Nos/Column 200
2) Total Qty= 25*8= 200 Nos

1) Assume 8 Nos Required for One Column


Shikanja 2 ft Nos 8 Nos/Column 200
2) Total Qty= 25*8= 200 Nos

18 1) Assume 18 Nos Required for One Column


Props Nos 450
Nos/Column 2) Total Qty= 25*8= 450 Nos

C.2) For Slab & beam ( Plate area 881 m2, So contact area 1.7 times =16121 sft)

Material Description Unit MF Quantity Calculation

1) One Ply Area=2.97Sqm,


8'x4' Ply Nos - 504
2) No. of Ply=(881*1.7) / 2.97 = 504 Nos

1) Assume 60 Rft Required for One Ply.


2"x3" Silver Patti Rft 60 Rft/Ply 30240
2) Total Qty= 504*60 = 2160 Rft
1) Assume 20 Rft Required for One Ply.
20 Rft *Beam
3"x4" beam bot & side Rft 6048 2) Assume Beam Bottom 600 mm
Btm Area
3) Total Qty= 504*20*0.6 = 6048 Rft

1) Assume 1 Nos of Prop Required for 0.6 Sqm Area.


Props -beam bot. Nos - 1468
2) Total Qty= 881 / 0.60 = 1468 Nos

25% of Beam
Props -beam side. Nos 367 1) No. of Props= Total Beam Bot. Props * 25% =367
bot.

Shikanja 2 ft beam bottom Nos 881/1 881


C.3) For Slab - Cup lock material (881 m2)

Material Description Area Constant Req. For 1 Bld For 3 Bld's.

Vertical 2.0 m 881 1.6 1410 1410 Nos 4229


0.5 m 881 1.6 1410 1410 Nos 4229
Ledger 1.5 m 881 2.05 1806 1806 Nos 5418
1.2 m 881 0.8 705 705 Nos 2114
1.0 m 881 0.8 705 705 Nos 2114
0.8 m 881 0.35 308 308 Nos 925
Screw Jack 881 1.6 1410 1410 Nos 4229
Base Plate 881 1.6 1410 1410 Nos 4229
ISMC 100 881 1.4 1233 1233 Rmt 3700
50 mm2 tube 881 1.8 1586 1586 Rmt 4757

C.4) Summery for 1 bld

Material Description Unit 1 Bld 3 blds


8'x4' Ply (Column+ Slab) Nos 540 1620
2"x3" Silver Patti (Column+ Slab) Rft 32400 97200
3"x4" Back Timber Chavi (Column+ Slab) Rft 6768 20304
Shikanja 3 ft (Column) Nos 200 600
Shikanja 2 ft (Column+ Slab) Nos 1081 3243
MS Props (Column+ Slab) Nos 2285 6855

C.5) Consumable Material Calculation


Shuttering
Consumable Material Unit MF Total Quantity
Quantity
Shuttering oil Lits 4822 0.01 48

Nut/bolt (Wage pin)*10% per reptn Kg 4822 0.014 68

Nails/binding wire Kg 4822 0.09 434

Prepared By:- Nitin M. Rathod