Proceedings of the 2017 25th International Conference on Nuclear Engineering

ICONE25
July 2-6, 2017, Shanghai, China

ICONE25-66757

Downloaded from https://asmedigitalcollection.asme.org/ICONE/proceedings-pdf/ICONE25/57793/V001T01A026/4252551/v001t01a026-icone25-66757.pdf by johnsummerton@ymail.com on 06 March 2020


TRANSITION FROM TIME‐BASED PREVENTIVE MAINTENANCE
TO CONDITION‐ BASED MAINTENANCE

Liu Xiaonian Wang Liansheng


China National Nuclear Corporation CNNP China National Nuclear Corporation CNNP
Haiyan, Zhejiang, China Haiyan, Zhejiang, China

ABSTRACT to ensure safety and operating reliability. However, it was


An optimized maintenance strategy is being pursued in the discovered that many types of failures could not be prevented
nuclear power industry, so as to reduce the maintenance cost or effectively reduced by such maintenance activities. Timothy
and improve equipment reliability. Transition from time-based Allen (2005) made a survey to the failure rates from studies
preventive maintenance (TBM) to Condition-based conducted previously by airlines and the U.S. Navy, and from
Maintenance (CBM) or Predictive Maintenance (PdM) is being his own studies. The survey concluded that a significant
set as a site initiative by different utilities. This paper analyzes percentage of failures (71−92%) are not age dependent [2]. To
the key elements a plant should focus on to achieve a some extent, TBM can contribute little to the reliability of a
successful CBM transition; discusses the implementation steps specific piece of equipment. Furthermore, it introduces human
and matters needing attention for the pilot project of CBM error during intrusive maintenance, which reduces the
transition; and depicts precursors for CBM such as CBM availability and reliability of the equipment. According to
equipment scope screening, equipment failure history incomplete statistics, in 12 mechanical seal failure events
collection, failure mode and degradation mechanism analysis, reports to COG (Candu Owners Group), 2 cases were caused
monitoring parameters and frequency setting, CBM result by improper alignment and foreign material.
evaluation, and CBM planning. The paper also discusses the Challenged by MW price and the problems caused by TBM,
impacts and challenges of CBM transition campaign to the more and more nuclear power plant managers are recognizing
existing production scheme. the value of CBM which can tremendously reduce maintenance
cost by properly arranging preventive maintenance as required.
INTRODUCTION However, lots of effort should be taken for a stable and firm
The main concern of the world nuclear power industry is transition from TBM to CBM.
moving from nuclear safety to addressing “nuclear power plant
is too big, too complex and too expensive, which makes many 1. ORGANIZATION PREPARATION FOR CBM
countries who wish to develop nuclear power can't afford to TRANSITION
build and use” [1] while nuclear safety is ensured. In 2013, the
United States closed four nuclear power units permanently; in 1.1Management support
2014, one unit was closed, and in 2016 another eight units were Support from the management is a key factor in successful
announced retirement prematurely. Most of the decisions were CBM transition. The management should set a vision and let
made on economic factors. Nuclear power plants are facing plant personnel know why to change the maintenance strategy
pricing challenges both from new energy and from power grid to CBM and how the plant and personnel will benefit from it in
regulation requirements. As a result, more concerns are being the long term. Plant managers should provide supports to the
given to generating cost after nuclear safety than ever. Lots of transition project by fiscal budget, human resources and
nuclear power plants still adopt TBM strategy. The traditional management policy, etc.
approach to scheduled maintenance programs is based the
concept that every item on a piece of complex equipment has a 1.2 CBM Group
‘right age’ at which complete overhaul is necessarily conducted

1 Copyright © 2017 ASME


CBM group, as the owner of CBM, plays a key role in the To Component in Qinshan
22 246 619 373 252 10
project [3]. Different departments of the plant are involved in NPP
the CBM transition, such as operations, maintenance, A: Acoustic
engineering, work management, chemistry and IT. Close U: Ultrasonic

Downloaded from https://asmedigitalcollection.asme.org/ICONE/proceedings-pdf/ICONE25/57793/V001T01A026/4252551/v001t01a026-icone25-66757.pdf by johnsummerton@ymail.com on 06 March 2020


collaborations and communication among the departments are Vib: Vibration Analysis
vital in putting forward CBM transition. It is suggested that the Lu: Lubricant Analysis
CBM group be lead directly by the managers. A good practice V: Valves Testing
is to set up sub- groups under the CBM group, such as the InT: Infrared Thermography
rotating component group, the high volt electrical component Table 1: investigation result example for CBM
group and etc. The group is responsible not only for CBM technologies application
coordination and planning, but also for the CBM
implementation on site. 2.2 Investigation for the Existing Monitoring Point and
Available Monitoring Data
1.3 Personnel Training An investigation for the existing monitoring point and
The managers, operators, maintainers, component engineers, available monitoring data should be taken to collect the
chemical workers, planners and IT engineers should be trained potential data which could be used in CBM. If the data is
with the CBM principle, CBM technologies and knowledge of available, more details should be further investigated to find
CBM assessment reports. Also, varying levels of awareness of where it is saved and abstracted from. Table 2 is an example for
CBM program activities, goals, roles and responsibilities, and the investigation result for existing monitor point.
results should be effectively communicated to the appropriate
plant and support personnel [4]. CBM technologists or Tag Equipment Available Data in Data
component engineers should be properly trained to perform the data Tag
condition monitoring and analyze the result of the monitoring. CEX00 CEP A Bearing PI XCEX1
Sampling personnel should be trained for right behavior during 1PO Vib. 01KT
sampling. Human error and safety risk should be paid attention CEX00 CEP B Bearing PI XCEX1
to during the training [5]. Critical activities should require 2PO Vib. 02KT
formal certification. Management should support certification … … … … …
of personnel in CBM technologies [4]. Table 2: an example for available monitoring data for
rotating component
2. TECHNICAL PREPARATION FOR CBM
TRANSITION 2.3 CBM Process, Procedure Preparation and Work
The CBM process involves new PdM technologies, Management System Optimization
numerous individual activities, and interactions of different The following process would be affected by the application
groups within the utilities. According to the existing good of CBM: plant work planning and scheduling; preventive
practices for CBM, it is suggested that the following maintenance (PM) program; corrective action program;
preparation should be considered before transition. performance monitoring programs; operator rounds; outage
planning and scheduling; spare parts procurement. The CBM
2.1 Preparation for CBM Technologies process, including its interface with all engineering groups,
At present, the following CBM technologies are common for maintenance, operations, and work planning and control,
most of nuclear power plants (may not be used in a way of should be well defined and well understood by those
CBM): vibration analysis, infrared thermography, lubricant performing the work. In addition, the processes should be
analysis, motor-operated valves testing, air-operated valves documented and supported by procedures and guidelines [4].
testing, transformer oil analysis, gas analysis, acoustic and Directed by TBM strategy, work management system usually
ultrasonic monitoring. The CBM group needs to make a survey comes up with PM work orders at a certain frequency.
of the application status of CBM technologies for the utilities. However, CBM triggers a PM work order when there is a
The gap could be found and the supplement of equipment, tool, requirement from condition monitoring result assessment. The
and software should be well planned for supporting CBM work management system should be effective at planning and
technologies. Table 1 is the investigation result for Qinshan scheduling PM work orders called for by the CBM program.
nuclear power plants on CBM technologies application status. There should be a formal, timely, and effective process for
Vibration analyses are the most common-used CBM work orders to be triggered based upon CBM data and analysis.
technologies.
2.4 CBM Information Platform
There should be an information platform for CBM because
PdM technology Application A U Vib Lu V InT
thousands of data points need to be saved, tracked, evaluated
and fed back. One of feasible ways is to optimize the current

2 Copyright © 2017 ASME


work management system, while another way is to design new integrated status of anomalies for component engineers to
software which could store data, alarm the limit, help review [4].
judgments made on equipment condition, trigger a work order
and give feedback. The interface should be user-friendly. The 3. COMPONENT SCREENING FOR CBM

Downloaded from https://asmedigitalcollection.asme.org/ICONE/proceedings-pdf/ICONE25/57793/V001T01A026/4252551/v001t01a026-icone25-66757.pdf by johnsummerton@ymail.com on 06 March 2020


software should be graphical orientated and equipment A CBM screening process of equipment is necessary and
performance data are easy to be withdrawn, trended and should be done before implementation, because not all
assessed. equipment in a nuclear power plant is suitable for CBM
strategy. Firstly, not all failure modes of components can be
detected at early stages (or at all). Secondly, some failure
modes develop so rapidly that there is no enough time for
reaction to renew the equipment condition. Thirdly, some
equipment, Single-Point-Vulnerability as an example, tends to
adopt the TBM rather than CBM, because any interruption of
the equipment running for CBM activities will
cause production loss which is unacceptable. Therefore, it is
strategically important to find out what categories of equipment
are CBM applicable, what are TBM applicable, and what are
TBM and condition-monitoring combination applicable. As a
supplementary to CBM and TBM, a comprehensive
combination of TBM and condition monitoring, which is not
regarded as a CBM strategy application, is advisable to be
adopted to protect equipment against all failure modes.
Equipment condition-monitoring plan, which is mainly for
incipient failure detection, troubleshooting or CBM strategy
determination, also relies on equipment maintenance categories,
namely CBM or TBM.
The CBM scope needs to be defined and screened prudently.
Figure 1. An illustration of CCW pump/motor
It is suggested that equipment screening for CBM be conducted
conditioning
as the following steps.
All related actions and information for CBM should be
3.1 On-line Maintainability
recorded and maintained in the database. The operation
During the first step for component screening, those
information includes operating time, duty cycle, operator
components which could be accessible and be repaired during
rounds and operating testing result. The maintenance
plant operation should be considered, such as the components
information includes As-Found/As-Left status, maintenance
in Balance of Plant.
cost, maintenance work plan and corrective maintenance
history, and experience from other plants. The engineering
3.2 CBM Technologies Attainability
information includes design data, engineer walk down,
The condition monitoring technologies are highly relied on
operating parameters and trending, modification and chemical
when deciding the component types for CBM. For example,
data. The cost of spare parts is also useful information and
vibration analysis, oil analysis and infrared thermography could
should be entered in the database. Information integration tools
detect the bearing wear potential failure in rotating equipment.
should be included to make the above data available on a
Infrared thermography could detect the poor termination of
broader basis for plant-wide decision making. The software
breaker, motor control center and high volt electricity
should be capable of accepting common, one-time entry of
equipment. It is suggested the following equipment could be
information on costs, physical descriptions, and identifications
scoped for CBM because the related technologies are well used
that can be permanently stored in the database and easily
in industry: pump; motor; compressor; fan; high volt electricity
retrieved for future reference [4]. The software is expected to
equipment, air operated valve, motor operated valve.
have the capability to be updated by analysts, trigger
recommended actions, and be accessible to various users to
3.3 Equipment Classification
provide an overall assessment of current condition of the plant
The result of classification for the equipment is another
equipment or a certain piece of equipment.
consideration in CBM screening. The critical equipment should
Component condition confirmation information should be
be scoped in while the non-critical equipment should be listed
accessible in a timely and integrated manner with effective user
on condition that CBM is more cost-effective compared with
interfaces. There should be a process in place to generate and
TBM. Run-to-maintenance Equipment should not be put in.
distribute component condition reports including a technology-

3 Copyright © 2017 ASME


3.4 Safety Regulation Requirements and Specification equipment group for CBM strategy application. On one hand, it
Limitations is difficult to determine the frequency of monitoring activity,
When regulations require TBM, the equipment should not be and experience needs to be accumulated to give an appropriate
listed in the scope of CBM [2]. Some instrumentation whose value to ensure that potential failure symptom is not missed. On

Downloaded from https://asmedigitalcollection.asme.org/ICONE/proceedings-pdf/ICONE25/57793/V001T01A026/4252551/v001t01a026-icone25-66757.pdf by johnsummerton@ymail.com on 06 March 2020


calibration is included in technical specifications should be the other hand, oil analysis, vibration monitoring and infrared
screened out. thermography monitoring are suggested to be considered
firstly, because these technologies are relatively mature.
3.5 Condition Monitoring Feasibility
When monitoring is impractical due to technology 4.2 Failure Mechanism Analysis
implementation difficulties, the component should not be Further analysis should be carefully carried out for pilot
included in CBM equipment list. For example, the fan in a equipment before CBM is in active. The analysis is a key step
cabinet whose vibration could not be effectively monitored; the of CBM transition which could help the CBM group members
panel for high volt electricity equipment could not be opened comprehend component failure while it may be tedious and
so that infrared thermography could not be used for monitor the expensive. The right PdM tasks could be easily selected to
termination status; there is no high quality sample point for ensure all fail modes are multiply covered by conducting
lubrication oil of the pump so that lubrication analysis is not FMEA analysis. Before conducting analysis of the pilot
feasible. equipment, failure history, maintainer feedback, As-Found/As-
Left data and operation experience from the plant and the other
3.6 Equipment Duty Cycle Consideration plants should be collected. The FMEA template could be used
For the equipment which stays at standby as normal state and to check which parts would fail mostly and what kind of failure
runs for periodic test, it is not suitable for CBM strategy. The modes would be a predominant failure mode.
operation data for this equipment is very limited, which brings Analysis should include failure cause, failure character and
difficulties to explain the true condition of equipment; yet it is whether there is enough time for the implementation of the
not recommended to add a function test for getting monitoring corrective action after a potential failure symptom is detected.
data. As an alternation, failure-finding activities can be applied What kind of predictive maintenance technology is more
to this equipment. economically feasible should be compared. Analysis process
could refer to the flowchart of Annex A.
An equipment list covered by CBM strategy could be If all the predominant degradations can be monitored, then
eventually made with other considerations may be taken after the strategy for the equipment might be CBM. However, if
the above steps, such as personnel skills, maintenance risk etc.. some degradation can be adequately monitored and some
The whole process of layered screening must be clearly others might require an intrusive inspection, then the total
recorded and archived in the form of technical documents, on strategy is CBM plus TBM [2]. It is important to decide
which the follow-up review could be based. Change of external monitoring parameters and monitoring interval beforehand.
conditions or equipment modification could initiate a review of Monitoring interval couldn’t be too long, which would miss a
the equipment list, which could be used for CBM planning potential failure, and couldn’t be too short, which would
during CBM wide spread application later. increase unnecessary maintenance cost and reduce the value of
CBM at last [6]. A feasible solution is to refer the experience of
4. CBM PILOT the pilot project and good practices from the other power
According to the experience of most plants who have plants.
successfully applied CBM program, the transition usually takes
3 to 5 years [2]; it is relatively a safe way to transfer the N
Data Nom
Alarm Alarm Setpoint
strategy by starting from a pilot project. The plant can benefit o Parameter Setpoint by by Manual
Tag value
from the pilot project by finding out the key points in CBM . CBM
transition. The engineers involving the project will get Bearing
XC
experience and ability improving by problem solving. Pilot Tempera-
EX1 <75 >=70 >=75 >=75 >=85
project can also reduce the resource pressure for power plants. 1 ture 1 of
01K ℃ ℃ ℃ ℃ ℃
The achievement of the pilot project will bring confidence to CEX
T
pump A
the manager and make the plant personnel buy into the
program. Table 3: an example for equipment monitoring
parameters and limits
4.1 Pilot Equipment Selection
During pilot equipment selection, it should be considered 4.3 Monitoring Point and Monitoring Device
how to complete CBM transition at a low risk. Usually it would If continuous monitoring is required for equipment,
be a good choice to select non-critical rotating equipment in monitoring sensors and instruments generally needs to be
BOP system with high cost of preventive maintenance as pilot installed to ensure the effectiveness of monitoring. In early

4 Copyright © 2017 ASME


design of nuclear power plants, there is usually no monitoring for imminent failure and decide which failure mode should be
device. Under this situation, mobile monitoring or a focused on later.
modification for adding online monitoring device or sampling
point may be adopted. Attention should be paid to setting 5. ASSESSMENT AND WIDE APPLICATION

Downloaded from https://asmedigitalcollection.asme.org/ICONE/proceedings-pdf/ICONE25/57793/V001T01A026/4252551/v001t01a026-icone25-66757.pdf by johnsummerton@ymail.com on 06 March 2020


identifications for the monitoring points or the sampling points When the pilot project for CBM is on line, an assessment or
to ensure that each time the detected values are identical and summary for the project should be made per half a year or a
comparable. year. The object is to find out the strengths and weaknesses,
improve performance of the CBM group, and optimize the
4.4 Equipment Maintenance Plan CBM transition process. The assessment should include the
Equipment maintenance plan should be prepared after failure CBM indicators calculation and analysis.
mechanism analysis is finished. It is very important that no There are many evaluation methods for CBM performance.
delay occurs between the time of potential failure found and Self-assessment is used more often [4], which could judge the
corrective work taken on the equipment, which could reduce performance of CBM by answering some questions. Another
the failure consequences effectively. Any potential failure way for evaluation is a peer review. The CBM group could
detected by CBM monitoring will trigger a maintenance request invite experts for the review from other plants who have
for the equipment. Therefore, maintenance plan, spare parts and performed very well in CBM strategy application. CBM
tools must be ready as required and be easily reached. application improvement could be achieved by learning the
internal and external CBM transition operation experience
4.5 CBM Performance Indicators feedback. The CBM group could find a shortcut to
The purpose of setting performance indicators for pilot continuously optimize CBM work from these OE.
project is that the CBM group could verify the effectiveness of Upon completion of pilot, the CBM group would gradually
CBM so that there would be a reliable proof for CBM benefit. apply CBM strategy to all applicable non-critical equipment in
The indicators would be put in the report for the manager the list, finally extended to the critical equipment in important
before spread application of CBM. It is suggested that the systems. Before application to critical equipment, it should be
indicators should be set up before the CBM transition starts up. ensured that there are appropriate tasks for all the important
Data should be collected from the beginning, as a benchmark in failure modes, in addition to condition monitoring tasks
the future. The indicators should be able to reflect the change selection for dominant failure modes.
of equipment reliability, availability and maintenance cost.
The following is an example for the indicators: 6. IMPACT AND CHALLENGES
z Equipment Failure Events The impact and challenges brought by CBM application to
z Improve Equipment Performance improvement nuclear power plant management, component engineers,
z Unavailability of Equipment Due to Preventive maintainers, operators and planners are as follows:
Maintenance
z Unavailability of Equipment Due to Failure 6.1 Manager
z Preventive Maintenance Costs The introduction of CBM strategy would bring a
z Spare Parts Costs maintenance concept transformation for the manager, and test
z Spare Parts Inventory the collaboration of the existing organization. The CBM
strategy would bring some new change in the number of
4.6 Implementation of CBM Corrective Maintenance (CM): the numbers of CM work order
Condition monitoring is part of the maintenance activities, would come up [2]. The management should pay attention to
but generally performed by technical personnel. All the this change and actively respond when developing stimulating
monitoring activities should be carried strictly in accordance policy or assessment indicators. Introduction of new PdM
with the analysis results. When an abnormal condition is found, technologies and installation of monitoring sensors would give
other monitoring technologies could be used for reconfirmation burden to Change Management.
when possible. It is necessary to evaluate whether follow-up
monitoring cycle should be shortened to catch potential failure 6.2 Engineering
effectively. For example, if a bearing vibration trend showed Engineering personnel would face a challenge from CBM
a small deviation, the CBM group could put up a work request technologies. Sometimes it is very difficult to make a decision
for an extra oil sample for the bearing and conduct vibration on equipment conditions with abnormal monitoring results. The
monitoring more frequently. The CBM group should confirm group would also face emergent demand of spare parts.
an abnormal condition and determine whether equipment needs
to be shut down for maintenance. When equipment is stopped 6.3 Maintenance
as required, the CBM group should attend visual inspection on CBM strategy has a higher expectation for the worker in that
site, verify whether equipment As-Found status is coincided they are to response rapidly to the emergency work request
with the condition evaluation of the group, examine other parts from CBM, and to feedback in high quality. To satisfy this new

5 Copyright © 2017 ASME


expectation, the preparation of maintenance activity should be [2] Guidelines for Transitioning from Time-Based
enhanced. The maintenance organization would be expected to Maintenance to Condition-Based Maintenance. EPRI,
leave more time and resources for preparation of maintenance Palo Alto, CA: 2013. 3002000493. pp. 24,40-42,52,55,56,
activity. Strategy transition is also likely to bring some changes 61

Downloaded from https://asmedigitalcollection.asme.org/ICONE/proceedings-pdf/ICONE25/57793/V001T01A026/4252551/v001t01a026-icone25-66757.pdf by johnsummerton@ymail.com on 06 March 2020


of maintenance organization. [3] Condition-Based Maintenance Guideline. EPRI, Palo
Alto, CA: 2011.1022957. pp.56-60
6.4 Operations [4] Predictive Maintenance Self-Assessment Guidelines for
The transition of the strategy would strengthen operator Nuclear Power Plants, EPRI, Palo Alto, CA: 2000.
routine rounds and improve communication with other 1001032. pp.26,27,30,49,52
organizations. Operators should give suggestions on more [5] Performance Metrics for Condition-Based Maintenance
reasonable equipment duty cycle, such as coping with Technology Application Programs, EPRI, Palo Alto, CA:
monitoring or sampling frequency [2]. 2003. 1003682. pp.48
[6] John Moubray, RCM II, Industrial Press Inc., New York.
6.5 Planning 1992
CBM strategy would bring changes to existing planning
method. Firstly, it would affect unit outage scope management
[2]. Work orders may be raised from CBM after the unit outage
work scope is frozen. Secondly, CBM task planning is different
from corrective maintenance planning or time-based preventive
maintenance planning. All condition monitoring tasks need to
be arranged on time while the overhaul tasks which are
triggered by the evaluation result on abnormal monitoring data
need to be identified, graded, and scheduled properly.

Conclusion: The application of CBM strategy has been proved


to an important way in improving equipment reliability and
reducing the maintenance cost. The successful implementation
of CBM transition relies on a good technical preparation,
organization, motivation and step-by-step moving forward.
CBM practices in Qinshan NPP concluded:
1) The determined CBM group ensures the smooth
transition and minimizes the impact on the existing
organization;
2) The CBM technologies are the bases and should be
grasped and fully applied to the plant;
3) CBM transition takes certain steps such as
investigation, component screening, piloting transition etc.
should be basically followed;
4) The CBM process, component screening criteria,
information platform should be set up with the CBM
progress;
5) A continuous support from the management and
visible CBM Indicators will bring the CBM transition
completed.

ACKNOWLEDGMENTS
This paper is based upon equipment reliability enhancement
campaign in Qinshan Nuclear Power Plants.

REFERENCES
[1] Wen Hongjun, The World's Nuclear Power Technology,
the New Trend of Market Development, Nuclear Power of
Information And Technology, 2014 ,Vol. 3, pp.10

6 Copyright © 2017 ASME


ANNEX A

CBM ANALYSIS FLOW CHART

Downloaded from https://asmedigitalcollection.asme.org/ICONE/proceedings-pdf/ICONE25/57793/V001T01A026/4252551/v001t01a026-icone25-66757.pdf by johnsummerton@ymail.com on 06 March 2020


Maintenance
Analysis FMEA History/OPEX/
No As Found

Failure mode
FMEA analysis Failure Predominant Defense for
Equipment Yes caused by Yes
available? Location 1, 2... Failure Mode human error
Human error?

No
A

Failure is age-
No Yes Optimize TBM
related?

CBM
Technology No
available?

Yes

P-F analysis Yes


No

Other
P-F time enough
No technology
for intervene?
available?

Yes

Determine CBM monitor


parameter\frequency
Compare the
technologies, determine
the one used

Critical
No CBM
Equipment?

Yes

Any other
A Yes critical failure No
mode?

7 Copyright © 2017 ASME