You are on page 1of 11

Energy and Buildings 43 (2011) 3646–3656

Contents lists available at SciVerse ScienceDirect

Energy and Buildings


journal homepage: www.elsevier.com/locate/enbuild

A fault-tolerant and energy efficient control strategy for primary–secondary


chilled water systems in buildings
Dian-ce Gao, Shengwei Wang ∗ , Yongjun Sun
Department of Building Services Engineering, The Hong Kong Polytechnic University, Hong Kong

a r t i c l e i n f o a b s t r a c t

Article history: Primary–secondary chilled water systems with decoupled bypass in building air-conditioning often can-
Received 12 July 2011 not work in healthy condition as desired in practical operation, due to excess secondary flow demand
Received in revised form 7 September 2011 resulting in deficit flow in the bypass line. This paper presents a fault-tolerant and energy efficient control
Accepted 26 September 2011
strategy for secondary chilled water pump systems to solve this operation and control problem providing
enhanced operation performance and energy efficiency of chilled water systems. The strategy employs
Keywords:
the flow-limiting technique that ensures the water flow of secondary loop not exceed that of the primary
Chilled water system
loop while still maintaining highest possible delivery capacity of cooling to terminals. The strategy is also
Primary–secondary chilled water system
Deficit flow
integrated with a differential pressure set-point optimizer to determine the optimal set-point. The per-
Fault-tolerant control formance of this strategy is evaluated in a simulated real-life environment representing the chilled water
Energy efficient control system in a super high-rise building by comparing it with two conventional control strategies. Results
show that the proposed strategy can effectively eliminate the deficit flow at both starting and normal
operation periods. The energy saving in the secondary chilled water pumps can be up to over 70% and
50% at system starting and normal operation periods respectively compared with the other strategies.
© 2011 Elsevier B.V. All rights reserved.

1. Introduction primary loop under full load condition and should be less than that
of primary loop under part load condition. When the deficit flow
Over the last decades, primary–secondary chilled water sys- problem exists, the temperature differential produced by the ter-
tems have been widely used in commercial buildings. In a typical minals will be much lower than its design values, which is known as
primary–secondary chilled water system, the primary constant low delta-T syndrome [2–5]. Kirsner [2] pointed out that low delta-
speed pumps ensure the chillers operate with constant flow rate, T chilled water plant syndrome exists in almost all large distributed
and the secondary variable speed pumps vary the flow rate accord- chilled water systems.
ing to the cooling demands of the terminals. It is an energy efficient The deficit flow may cause a series of operational problems, such
configuration when compared with a constant flow system [1]. as the high supply water temperature, the over-supplied chilled
While in real application, most of the primary–secondary systems, water, and the increased energy consumption of the secondary
from time to time, cannot work as efficient as expected due to the pumps. If such phenomenon cannot be eliminated, a vicious cir-
excess secondary flow demand, which causes deficit flow problem cle in the secondary loop may be caused. It means that, when the
(i.e., the required flow rate of secondary loop exceeds that of the deficit flow occurs, the mixing of the return chilled water to the
primary loop). The excess return water flow rate will flow through supply chilled water results in higher temperature of chilled water
the bypass line and mix with the main supply chilled water, result- supplied to the terminal air-handling units (AHU). The increased
ing in increased temperature of water supplied to building and temperature in the supply chilled water consequently leads to an
thus higher flow demand from terminals. Since the cooling coils increased chilled water flow rate which further worsens the deficit
are selected to produce a temperature rise at full load that is equal flow. The deficit flow will not disappear until the flow rate in the pri-
to the temperature differential selected for the chillers. The flow mary loop is increased greatly (e.g., an additional chiller is switched
rate of secondary loop should be therefore equal to that of the on).
Many possible reasons of the deficit flow problems have been
studied in previous studies [6–8]. Taylor [7] pointed out that some
∗ Corresponding author. Tel.: +852 27665858. causes can be avoided, such as improper set-point or controls cal-
E-mail address: beswwang@polyu.edu.hk (S. Wang). ibration, the use of three-way valves, improper coil and control

0378-7788/$ – see front matter © 2011 Elsevier B.V. All rights reserved.
doi:10.1016/j.enbuild.2011.09.037
D.-c. Gao et al. / Energy and Buildings 43 (2011) 3646–3656 3647

valve selection, no control valve interlock, and uncontrolled process 2. Formulation of the fault-tolerant control strategy
load, etc. While some causes cannot be avoided, such as reduced
coil effectiveness, outdoor air economizers and 100% outdoor air In previous studies, a number of researchers have paid great
systems. efforts on the energy efficient control and operation of variable
In the last two decades, some researchers and experts in the speed pumps to enhance their energy efficiencies [16–21]. How-
HVAC field have devoted considerable efforts to deal with the low ever, when the deficit flow occurs, these control strategies cannot
delta-T syndrome and deficit flow problem [9–11]. Among the stud- handle this problem, resulting in the fact that the chilled water sys-
ies, Kirsner [2] stated that the standard primary–secondary chilled tem is hard to be controlled as the anticipation with high robustness
water design cannot solve the low delta-T syndrome and a new and energy efficiency in real applications. The developed fault-
paradigm with variable-flow primary pumps should be adopted for tolerant control strategy for secondary pumps is to avoid deficit
chilled water design. Fiorino [10] indicated strongly that a higher flow in the bypass line and improve the low delta-T syndrome while
delta-T can be achieved by proper application of cooling coils, con- taking the energy saving of the secondary pumps into consideration
trols systems, distribution pumps, and piping systems. Up to 25 at the same time.
practical methods are recommended to achieve high chilled water
delta-T ranging from component selection criteria to configurations 2.1. Outline of the fault-tolerant control strategy
of distribution systems.
Besides the approaches concerning the design and commission- The fault-tolerant control strategy for secondary pumps is
ing, the implementation of check valve on the bypass line has developed not only to eliminate the deficit flow problem but also
attracted more attention. The check valve actually is a one way to enhance the energy efficiency of the chilled water distribution
valve, which only permits the water flow direction from the supply systems. It provides a method based on flow-limiting technique
side to the return side and avoids the flow at the reverse direc- that can ensure the flow rate in the bypass line is positive (a nega-
tion in the bypass line. Kirsner [4] analyzed the advantage the tive value means deficit flow). Fig. 1 illustrates this control strategy,
use of check valve in the bypass line and thought that installing which consists of a set-point reset control of differential pressure
check valve in the bypass line is a cheap and a simple improvement at remote (DP2), a flow-limiting controller, a differential pressure
to primary–secondary design of chilled water plants that allows reset controller at supply (DP1), and a pump controller.
a plant to deal with low delta-T syndrome. Avery [5] presented In this strategy, the secondary pumps are controlled to achieve
a case study that installing a check valve in the bypass line of a two objectives: one is to eliminate the deficit flow in the bypass line
primary–secondary chilled water system that serves a HVAC sys- and the other is to maintain a lowest pump head while still satisfy-
tem and meets industrial requirements. The results showed that ing the cooling demands of all AHUs. A modified cascade control is
the secondary supply water temperature stabilized at 7 ◦ C and the employed to achieve a balance of stable control and fast response
annual chiller power consumption decreased by 20% per year. On which involves two loops. In the outer loop, the DP1 set-point reset
the contrary, the disadvantages of check valve application arouse controller determines the differential pressure set-point (DP1set ) at
the concerns of researchers [12–15]. Taylor [12] pointed out that the main supply by comparing the measured differential pressure
the secondary pumps will be deadheaded if the primary pumps of at remote (DP2) with the set-point (DP2set ). In the inner loop,
are off and chiller isolation valves are closed while the secondary DP1 is compared with the differential pressure set-point at supply
pumps are on. Rishel [15] stated that check valve may not be the (DP1set ) in by the pump controller to control the speed of the pumps.
answer to the low delta-T syndrome under some situations, like DP1set,max is introduced as the maximum value of DP1set in the outer
the system utilizing the energy storage system or water side econ- loop, which is determined by the flow-limiting controller. The func-
omizers. tion of introducing DP1set,max is to eliminate the deficit flow, which
All these studies demonstrate that low delta-T syndrome and is reset according to the measured flow rate (Mby ) in the bypass
deficit flow problem widely existed in the primary–secondary line. When deficit flow occurs, DP1set,max will be reduced gradu-
chilled water system and the elimination of this problem can ally by feedback control until the deficit flow disappears. The DP2
improve the energy efficiency of the chilled water system. How- set-point reset controller might be eliminated in practical applica-
ever, most of the studies pay more attention to analyzing the tions to simplify the application of the strategy or the valve opening
possible causes and solutions of this problem from the view of information is not available. It is worthy noticing that, to simplify
design and commissioning. In practice, even the HVAC systems the control strategy in implementation, resetting of the differential
were properly designed and well commissioned, deficit flow still pressure at the supply (DP1set ) can be achieved by maintaining a
cannot be completely avoided in the operation period due to some differential pressure at remote (DP2) at certain level without using
disturbances, e.g., improper control. There are no reliable, robust the valve opening information or by using directly the valve open-
and secure solutions that can eliminate deficit flow in real appli- ing information without using the differential pressure at remote
cations. The research associated with proper control of secondary (DP2).
pumps to eliminate deficit flow and low delta-T syndrome for real The working principle of this control strategy is illustrated in
applications is missing. Further more, many of the proposed solu- Fig. 2 and more detailed descriptions of this control strategy are
tions from the viewpoint of design might be only feasible to be presented in the following section.
adopted in new systems, while solutions from the viewpoint of
operation and control are practical and preferable for the large 2.2. Control of secondary pumps
number of existing systems suffering from the deficit flow and low
delta-T syndrome. 2.2.1. Description of flow-limiting controller
Therefore, this paper aims at developing a fault-tolerant and The flow-limiting controller is employed to limit the water flow
energy efficient control strategy for secondary pumps to elimi- rate of the secondary loop not larger than that of the primary loop
nate deficit flow problem of the primary–secondary chilled water (i.e., to avoid deficit flow in the bypass line), as shown in Fig. 2.
systems concerning both operating efficiency and tolerance to This strategy utilizes a feedback control using the measured water
unhealthy and faulty balances of chilled water systems. The perfor- flow rate in the bypass line. A threshold , which represents the
mance of this strategy is validated in the case studies on a simulated expected minimal and positive (negative means deficit flow) flow
dynamic system constructed based on a real system in a supper- rate in the bypass line, is set by the users.  can be determined
high-rise building in Hong Kong. according to the system design or practical requirements. If  is
3648 D.-c. Gao et al. / Energy and Buildings 43 (2011) 3646–3656

DP2

DP2set

Flow threshold µ DP1set


DP1UL Flow-limiting Pump DP2 set-point
DP1 set-point DP1
controller DP1 control reset (optional)
DP1LL reset
set,max
DP1set,min •••
Mbp



CHILLER

CHILLER

• • •

Bypass line
Secondary pumps

AHU

AHU

AHU
M • • •
DP1 DP2

Primary
pumps

Fig. 1. Outline of the fault-tolerant control strategy.

set to zero exactly, the water flow rate is possible to be negative decrease the speed of the secondary pumps and therefore limit the
because of the fluctuations of the control process resulting lower flow supplied to building to avoid deficit flow in the bypass line.
control stability. Therefore, it is better to set  to a small but posi-
tive value in order to avoid deficit flow in the bypass line for stable 2.2.2. Description of the set-point reset of differential pressure at
control. In this study,  is set to be about 3% of the design water supply (DP1)
flow rate of a single chiller. A PID controller compares the mea- The DP1 set-point reset controller is utilized to generate the dif-
sured water flow rate (Mby ) in the bypass line with the predefined ferential pressure set-point at the supply (DP1set ) as shown in Fig. 2.
threshold  to generate a control signal ˛ (between 0 and 1). ˛ is In this process, the PID-1 generates the control signal by compar-
rescaled to generate DP1set,max , the maximum value (upper limit) ing the measured differential pressure (DP2) at remote with its
for the differential pressure set-point DP1set of the DP1 set-point set-point (DP2set ), which is optimized in the set-point of the dif-
reset controller by using Eq. (1). ferential pressure at remote (DP2set ) reset controller. The control
signal is rescaled to generate the set-point of the differential pres-
sure at supply (DP1set ) for the pump control. Fig. 3 shows rescale
DP1set,max = DP1LL + ˛(DP1UL − DP1LL ), ˛ ∈ (0, 1) (1)
function for the determination of the differential pressure set-point
using a linear relationship between DP1set and the output of PID-
where, ˛ is the output of the PID control (PID-1), DP1LL and DP1UL 1. When the output of PID-1 increases, when more chilled water
are the lower and upper limits for the DP1set,max respectively. They is required, DP1set will increase accordingly. DP1set,min is the lower
can be determined based on the practical chilled water system limit of the controlled differential pressure at supply side, which
design data considering the operation safety and stability. is a constant determined by operators based on system design or
DP1set,max is a variable that is used as the maximum value for practical requirements. The selection of DPset,min should consider
the differential pressure set-point DP1set to control the speed (and the operating stability of the pumps. DP1set,max is the upper limit for
number) of secondary pumps to ensure the water flow rate in the DP1set , which is a variable generated by the flow-limiting controller.
bypass line is not less than the predefined threshold . DP1set,max When the flow demands of AHUs increase, the AHU valves
is reset according to the measured flow rate in the bypass line. will open more and the DP1set will increase consequently. When
When Mby is larger than the predefined threshold , DP1set,max will deficit flow occurs, the higher temperature of the supply water to
increase gradually (to leasing the limit for supply flow control) until AHUs will result in higher flow demand and consequently higher
reaching its upper limit DP1UL . On the contrary, when Mby is less DP2set . When the AHU outlet air temperatures cannot reach their
than the predefined threshold , DP1set,max will decrease gradually set-points, DP2set will increase to its maximum value rapidly. Con-
(to limit to supply flow) until reaching the lower limit DPLL . The sequently, the output of PID-1 in the DP1 set-point reset controller
reduction of DP1set,max will consequently lower the DP1set that will will increase to a very high value. If such DP1set is used directly for

Fig. 2. Principle of pump and flow limiting controls.


D.-c. Gao et al. / Energy and Buildings 43 (2011) 3646–3656 3649

Start
DPset-point
(kPa)
Collect the opening signal (OS)
DPset,max of valves and other measurements

Search the OS max and count the


DPset number of valves with the OS max

No
OSmax=100% ?
DPset,min
Yes
Yes
Number>1?
0% Output of PID-1 100%
No
Fig. 3. The working principle of the determination of DPset . Yes
Ta,sup-Ta,set > ?
pump control without applying proper constraints, one can image No
that the pump might work at full speed and the deficit flow will
be further deteriorated. In this strategy, DP1set,max determined by DP2set,k= DP2set,k=
DP2set,k= DP2set,k-1
DP2set,k-1 + P DPset,k-1 P
the flow-limiting controller performs the role of limiting the flow
in the secondary loop when deficit flow occurs as shown in Fig. 3.
Although deficit flow results in the increase of DP2set , DP1set,max Limit checking
will be reduced simultaneously by the flow limit controller. As a
overall result, the set-point of DP1 will eventually drop resulting
in reduced pump speed until the deficit flow disappears. Note, the Optimal PD set-point
reduced total chilled water supplied to terminal units (AHUs) to
eliminate the deficit flow in case it occurs will not reduce the total
cooling capacity of the terminal units as the high chilled water flow Return
of higher temperature cannot provide higher cooling capacity in
reality, which is discussed later in this paper. Fig. 4. Control logic flow chat of set-point reset of differential pressure at remote
(DP2).
2.2.3. Description of the set-point reset of differential pressure at
remote (DP2)
This set-point reset control is used to produce an optimal differ- loop hydraulically. Therefore, providing enough and just enough
ential pressure set-point (DP2set ) at remote, as shown in Fig. 4. This chilled water to the hydraulically critical loop to satisfy the cooling
strategy is developed to search the optimal differential pressure demand and minimizing its water resistance by fully opening its
set-point that can make the secondary pumps provide the enough valve can minimize the pressure drop of secondary pumps.
and just enough differential pressure to the hydraulically critical
loops at all times. This objective can be achieved by increasing
or reducing the differential pressure set-point to keep only one 2.2.4. Description of pump speed and sequence control
valve fully open and to ensure this AHU can satisfy the cooling The pump controller generates the speed signal for the sec-
demand. As shown in Fig. 4, at time k, the strategy will firstly check ondary pumps. It compares the measured differential pressure
whether the maximum valve opening (OSmax ) of all AHUs reached at the supply side (DP1) with its set-point (DP1set ) given by DP1
100% or not. Then, the number of the valves with 100% opening set-point reset controller to output a control signal. PID feedback
will be counted. Last, the supply air temperature (Ta,sup ) from the control is used to modulate the speed of the pumps.
only one AHU with 100% opening valve will be checked whether The sequence control strategy for secondary pumps determines
it has reached the set-point (Ta,set ) or not. By judging the three the operating number of pumps. In this study, a conventional strat-
these conditions, the strategy will modulate the differential pres- egy is utilized. Using this strategy, an additional pump is switched
sure set-point (DP2set,k ) based on the previous setting (DP2set,k−1 ) by on when the frequencies of operating pumps exceed 90% (corre-
increasing or decreasing a predefined incremental (P). The prede- sponding to 45 Hz) of their nominal capacity. One of the operating
fined pressure incremental is different in various practical systems, pumps is switched off when the frequencies of the operating pumps
which is determined to keep the control process stable and flexible. are lower than 60% (corresponding to 30 Hz) of the nominal capac-
In this study, P is equal to 1.5% of the required pressure drop of ity. In addition, in order to ensure the reliability and stability of the
the remote loop under full load condition. chilled water distribution system, a minimal time interval is set
For a given water network with air-handling units whose valves when changing the operating number of pumps.
opening are controlled to maintain the outlet air temperature at
the set-point, the secondary pumps should provide enough chilled
water to all the terminal units to satisfy the cooling demands. If one 2.3. Description of the detailed steps
of the AHUs cannot reach its supply air temperature set-point, its
valve will fully open to allow the highest possible water flow. If the A flow meter is installed on the bypass line which can monitor
supply air temperature of an AHU has reached its set-point, its valve the quantity and direction of water flow rate in the bypass line.
will be closed down to decrease water flow rate. When only one of The proposed fault-tolerant control strategy for secondary pumps
all those valves fully opens, it indicates that this AHU is the critical works as the following steps as illustrated in Fig. 5.
3650 D.-c. Gao et al. / Energy and Buildings 43 (2011) 3646–3656

Table 1
Design specifications of chillers and pumps in the chilled water system.

Chillers Number Cooling capacity (kW) Mw,ev (L/s) Mw,cd (L/s) W (kW) Wtot (kW)

Chiller-1,2 2 7230 345 410.1 1346 2792

Pumps Number Mw (L/s) Head (m)  (%) W (kW) Wtot (kW)

PCHWP-1,2 2 345 31.6 84.5 126 256


SCHWP-1–3 3 345 41.4 85.7 163 323

i. Check the valve control signals and bypass flow measurement AHUs are implemented in the air-conditioning system to provide
using a filter; cooled air for indoor thermal comfortable control. The valves of
ii. determine the maximum value (DP1set,max ) for the differential AHUs are controlled to maintain the supply air temperature at its
pressure set-point (DP1set ) by comparing the measured water set-point (i.e., 13 ◦ C in this study). The AHU fans are also equipped
flow rate (Mbp ) in the bypass line with the predefined threshold with VFDs to vary supply air flow rate and the VAV boxes are used to
by the flow-limiting controller; maintain the indoor air temperature at a fixed set-point (i.e., 23 ◦ C
iii. determine the optimal differential pressure set-point at remote in this study). The models of chillers, cooling towers, pumps, and
(DP2set ); cooling coils are all detailed physical models that can simulate the
iv. determine the differential pressure set-point at supply (DP1set ) real chilled water system.
for secondary pumps control by DP1 set-point reset controller The multi-zone building model of TRNSYS 16 is employed to
according to Fig. 3; simulate a building with 75 floors. Each floor is simplified to be
v. determine the operating number for the secondary pumps using square and the floor area is 1600 m2 . The floor to floor height is 3.5 m
pump sequence controller; and the external wall has three layers. The external and internal
vi. the final decision will be made by the control supervisor after layers of the external walls are 5 mm thick concrete layers and the
checking control constraints. middle layer is a massive brick layer with thickness of 240 mm.
The ratio of widow to wall is 0.5. The heat load from the occupants,
3. Test platform equipment and lighting system and weather data are considered in
the simulation as an input file. The weather condition used is the
It is hard to compare various control strategies in real air- data of the typical year in Hong Kong.
conditioning systems due to its extreme complexity. The proposed
fault-tolerant control strategy was validated and evaluated using 4. Performance tests and evaluation of the fault-tolerant
a dynamic simulation platform representing a typical chilled control strategies
water system for a building, as shown in Fig. 6. This is a typi-
cal primary–secondary chilled water system, in which two water In order to compare the control performance and energy effi-
cooled centrifugal chillers with rated cooling capacity of 7230 kW ciency of the chilled water system before and after the utilization
are installed to generate the chilled water of 7 ◦ C at design condi- of this proposed fault-tolerant control strategy (Strategy #3), two
tion. Each chiller is associated with a constant speed primary pump. conventional control strategies are used for comparison, as shown
In the secondary loop, there are three identical secondary pumps in Table 2. In the first conventional control strategy (Strategy #1),
distribute chilled water to the terminals, one of which is a standby secondary pumps are controlled to maintain a fixed differential
pump. All the secondary pumps are equipped with VFDs to control pressure of the remote loop, which is the upper limit of the differ-
the pump speed according to the terminal cooling demand. The ential pressure set-point constrains under the full load condition
detailed parameters for chillers and pumps are listed in Table 1. in the Strategy #3. The second conventional strategy (Strategy #2)
uses an optimal differential pressure set-point that can ensure one
of the valves associated with the heavily loaded terminal unit fully
open at all times.
The chiller sequence control strategies used in the simulations
are as follows according to the conventional operation of a real
system in Hong Kong. Chiller is sequenced only based on the cooling
load of the terminals. When the measured cooling load exceeds the
nominal cooling capacity of the chiller for ten minutes, another
chiller is switched on. When the remaining chiller can handle the
cooling load, one of the chillers is switched off.
Two cases will be studied to test and validate the operation and
energy performance of the chilled water system using the fault-
tolerant strategy. One case is to evaluate the strategy in a chilled

Table 2
Description of the control strategies.

No. Strategies Description

1 Strategy #1 Using a fixed set-point for


differential pressure at remote
2 Strategy #2 Using the optimal set-point for
differential pressure at remote
3 Strategy #3 Using the optimal set-point for
differential pressure at remote and
flow-limiting control
Fig. 5. The flow chart of the detailed control procedures.
D.-c. Gao et al. / Energy and Buildings 43 (2011) 3646–3656 3651

Fig. 6. Schematic of the chilled water system.

water system without faults, the other one is in a system with faults period by estimating the total energy consumptions under different
that will cause deficit flow. Both morning start period and normal operating chillers. During normal operation period, the chillers
operating period are studied. were sequenced based on the measured cooling load of terminal
A typical air-conditioning system usually experiences two typ- units. Only detailed performance data in the sunny-summer test
ical working modes, namely (morning) start period and normal case are presented here.
operating period. In the start period, the chilling system is switched Fig. 8 presents the water flow rates of the bypass line in the
on before occupation to cool down the indoor air temperature to the sunny-summer test case using the three different control strate-
comfortable level. In normal operating period, the indoor thermal gies. It can be observed that there was no deficit flow in the bypass
comfort condition has been achieved and the secondary water flow line using the proposed fault-tolerant strategy (Strategy #3) during
rate is controlled based on the terminal cooling demand. Gener- the day. While the other two conventional strategies (Strategies #1
ally speaking, deficit flow will not take place during normal period and #2) offered significant deficit flow, up to about −340 L/s, during
in a healthy chilled water system with proper design and com- the start period from 7:00 to 9:00am. This is because that all the sec-
missioning. However, a lot of field investigations and tests show ondary pumps worked under their high limit speeds while not all
that deficit flow frequently occurs during start period particularly the chillers and primary pumps are switched on when using Strate-
when not all the chillers are switched on. For instance, Fig. 7 shows gies #1 and #2. Using conventional strategies, secondary pumps
the measured water flow rates of the bypass line in three working were controlled to maintain the pressure drop of the critical loop
days (0:00 28/9/2010 to 18:00 30/09/2010) in a real building chilled at a set-point, whether fixed or optimal. During the start period, the
water system. It can be found that the deficit flow began to occur indoor air temperature was higher than its set-point and the outlet
on each morning start period. air temperature of AHUs could not reach their set-points, resulting
in that the valves fully opened. The fully open valves reduced the
4.1. Case 1: evaluation of the fault-tolerant strategy with water resistance of the total terminals and increased the frequen-
fault-free system cies and operating numbers of secondary pumps to deliver more
water in order to maintain the differential pressure at its set-point.
In this case study, the simulation tests focus on how the fault- Using the proposed fault-tolerant control strategy with flow-
tolerant strategy can offer its advantages in a typical working day limiting technique, the differential pressure set-point used for
from 7:00 am to 19:00 pm under three weather conditions (i.e., pumps control is not only dependent on the valve opening, but
spring, mild-summer and sunny-summer). During start period, dif- also based on the flow rates of the bypass line. When the deficit
ferent operating numbers of chillers consume different electric flow detected in the bypass line, the flow-limiting controller rapidly
energy to lower down the indoor air temperature to a desire level. decreased the differential pressure set-point, which limited the
The operating number of chillers in this test is chose to minimize operating speed of secondary pumps to ensure the secondary flow
the total energy consumption during the start period using the rate not more than that of the primary. Therefore, the proposed
existing model-based control strategy in [22], in which the opti- fault-tolerant strategy could effectively eliminate the deficit flow
mal operating numbers of chillers can be determined during start and accordingly save energy of secondary pumps.

400
300
Water flow rate (l/s)

200
100
0
-100
Deficit flow

-200
-300
-400
-500 Water flow rate of the bypass line
-600
0 6 12 18 24 30 36 42 48 54 60 66
Time (hour)

Fig. 7. Measured water flow rates of the bypass line in three working days in a real Fig. 8. Water flow rates in bypass line using three control strategies in the sunny-
building chilled water system in Hong Kong. summer test case.
3652 D.-c. Gao et al. / Energy and Buildings 43 (2011) 3646–3656

Table 3
Electrical energy consumption under different control strategies during the start period (7:00–9:00am).

Strategies Wpump (kW h) Wchiller (kW h) Wpump + Wchiller (kW h) Wpump saving Wchiller saving Total saving

(kW h) (%) (kW h) (%) (kW h) (%)

Spring
Strategy #1 437.6 2517.0 2954.5 – – – – – –
Strategy #2 432.7 2515.7 2948.4 4.9 1.11 1.3 0.05 6.1 0.21
Strategy #3 134.5 2507.8 2642.3 303.1 69.27 9.1 0.36 312.2 10.57

Mild-summer
Strategy #1 546.8 2613.2 3160.0 – – – – – –
Strategy #2 546.8 2613.3 3160.1 0.0 0 −0.1 0 −0.1 0
Strategy #3 155.7 2606.1 2761.8 391.1 71.53 7.1 0.27 398.2 12.60

Sunny-summer
Strategy #1 679.5 2671.5 3351.0 – – – – – –
Strategy #2 679.3 2671.3 3350.6 0.2 0.03 0.2 0.01 0.4 0.01
Strategy #3 154.6 2656.5 2811.1 524.9 77.25 15 0.56 539.9 16.11

enhance the heat transfer effect. However, as shown in Fig. 11, due
to the occurrence of deficit flow, the supply water temperatures
to terminal units were much higher than that using the proposed
strategy, which reduces the heat transfer effect. As the result, the
proposed strategy with lower supply water temperature and less
water flow rate to terminal units offered similar (slightly higher)
overall heat transfer effects of AHUs compared with that using the
conventional strategies with higher supply water temperature and
higher water flow rate to terminal units.
Tables 3–5summarize the energy use and savings of secondary
pumps and chillers under three strategies during start period, nor-
mal operation period and the whole day respectively. Strategy #1
was used as the benchmark for comparison. It can be seen that the
energy consumption of the chillers of the three strategies under
different weather conditions was very close.
Fig. 9. Indoor temperatures of critical zones using three control strategies in the Table 3 presents a comparison between the energy con-
sunny-summer test case. sumptions of pumps and chillers using three strategies during
start period. It is very obvious that Strategy #3 saved about
The zone with the highest cooling load in the building (i.e., the 69.27–77.25% of the secondary pumps energy, which account for
critical zone) is selected as an example to compare the indoor cool- about 10.57–16.11% of the total energy of pumps and chillers during
ing effect under the three control strategies. It is worthy noticing start period in three typical summer days, compared with Strategy
that the indoor air temperatures of the critical zone under three #1. The energy consumptions of pumps and chillers using Strate-
strategies were very close during morning start period, as shown gies #1 and #2 were very close. That means that Strategy #2 using
in Fig. 9. This indicates that the proposed strategy could offer equiv- optimal differential pressure set-point failed to offer obvious bene-
alent cooling capacity to the terminal units although the delivered fit during start period when compared with Strategy #1 using fixed
water flow rates were much lower when compared with the other set-point. Therefore, the energy saving during start period by Strat-
two conventional strategies. It is known that the heat transfer egy #3 mainly benefited from the flow-limiting technique. It also
between the water and the air in AHUs is affected by the water flow can be found that the energy saving by Strategy #3 in the sunny-
rate, inlet water temperature, air flow rate and inlet air tempera- summer test case was more than that in the other two test cases
ture. During morning start period, when using Strategies #1 and during start period.
#2, the deficit flow caused more supply water flow rates through
AHUs, as shown in Fig. 10. The higher flow rate should be able to

Fig. 10. Total water flow rates of secondary loop using three control strategies in Fig. 11. Supply water flow rate to terminals using three control strategies in the
the sunny-summer test case. sunny-summer test case.
D.-c. Gao et al. / Energy and Buildings 43 (2011) 3646–3656 3653

Table 4
Electrical energy consumptions under different control strategies during the normal operation period (9:00 am to 19:00 pm).

Strategies Wpump (kW h) Wchiller (kW h) Wpump + Wchiller (kW h) Wpump saving Wchiller saving Total saving

(kW h) (%) (kW h) (%) (kW h) (%)

Spring
Strategy #1 681.5 13,282.0 13,963.5 – – – – – –
Strategy #2 430.6 13,277.2 13,707.8 250.9 36.82 4.8 0.04 255.7 1.83
Strategy #3 430.4 13,261.2 13,691.6 251.1 36.84 20.8 0.16 271.9 1.95

Mild-summer
Strategy #1 983.7 17,906.0 18,889.6 – – – – – –
Strategy #2 718.1 17,888.0 18,606.1 265.5 26.99 18.0 0.10 283.5 1.50
Strategy #3 727.8 17,851.9 18,579.7 255.9 26.01 54.1 0.30 309.9 1.64

Sunny-summer
Strategy #1 2414.0 23,342.3 25,756.3 – – – – – –
Strategy #2 2131.1 23,339.2 25,470.2 283.0 11.72 3.1 0.01 286.1 1.11
Strategy #3 2113.8 23,337.7 25,451.5 300.2 12.43 4.6 0.02 304.8 1.18

In normal operation period as shown in Table 4, compared with


Strategy #1, Strategies 2# and #3 saved 11.72–36.84% of pumps
energy and 1.11–1.95% of total energy of pumps and chillers respec-
tively from 9:00 am to 19:00 pm. Since there was no deficit flow
during the normal operation period using the three strategies, the
energy savings were mainly contributed by using optimal differen-
tial pressure set-point. During normal operating period, Strategy
#3 achieved more energy savings in the spring test case than that
in the other two test cases.
Table 5 presents a summary of the energy consumptions
of pumps and chillers during the whole day (from 7:00 am to
19:00 pm). The fault-tolerant strategy (Strategy #3) saved about
26.67–49.52% of secondary pumps energy and 2.90–3.45% of total
energy (pumps and chillers) when compared with Strategy #1
respectively. Concerning energy saving, about 17.52–26.67% of
Fig. 12. Power consumptions of secondary pumps using three control strategies in
pumps energy and 1.9–1.92% of total energy of pumps and chillers
the sunny-summer test case.
respectively were obtained from the applications of flow-limiting
technique. It should be pointed out that Strategy #3 saved more
energy in the spring test case compared with the other two test 4.2. Case 2: evaluation of the fault-tolerant strategy with
cases during the entire day period. Fig. 12 depicts a detailed descrip- unhealthy system
tion of the energy consumption of pumps under three strategies in
the sunny-summer test case. In a healthy system, the deficit flow only occurs during start
Based on the above analysis, it can be concluded that the period particularly when not all the chillers are switched on. While
proposed fault-tolerant control strategies for secondary pumps in an unhealthy system, such as water system fouling or improper
can effectively eliminate the deficit flow during the start period controls, the deficit flow is possible to occur at any operation period.
due to the implementation of flow-limiting techniques. More- As far as the deficit flow occurs, the main supply water tempera-
over, the proposed strategies can save significant secondary pump ture to the terminal units will increase and the secondary pumps
energy compared with other two conventional strategies using will consume more energy. It is necessary to ensure the chilled
fixed differential pressure set-point and optimal pressure set-point water system works efficiently even it suffered from some faults
respectively. that can cause deficit flow. In practice, many causes can lead to
the deficit flow problem as mentioned before. In order to evaluate
whether the proposed strategy can handle the deficit flow, a fault

Table 5
Electrical energy consumption under different control strategies during the whole typical day (7:00 am to 19:00 pm).

Strategies Wpump (kW h) Wchiller (kW h) Wpump + Wchiller (kW h) Wpump saving Wchiller saving Total saving

(kW h) (%) (kW h) (%) (kW h) (%)

Spring
Strategy #1 1119.0 15,799.0 16,918.0 – – – – – –
Strategy #2 863.3 15,792.9 16,656.2 255.7 22.85 6.1 0.04 261.8 1.55
Strategy #3 564.8 15,769.0 16,333.9 554.2 49.52 29.9 0.19 584.1 3.45

Mild-summer
Strategy #1 1530.5 20,519.2 22,049.6 – – – – – –
Strategy #2 1264.9 20,501.3 21,766.2 265.5 17.35 17.9 0.09 283.4 1.29
Strategy #3 883.5 20,458 21,341.5 647.0 42.27 61.2 0.30 708.1 3.21

Sunny-summer
Strategy #1 3093.5 26,013.8 29,107.3 – – – – – –
Strategy #2 2810.4 26,010.5 28,820.8 283.2 9.15 3.3 0.01 286.5 0.98
Strategy #3 2268.4 25,994.2 28,262.6 825.1 26.67 19.6 0.08 844.7 2.90
3654 D.-c. Gao et al. / Energy and Buildings 43 (2011) 3646–3656

Fig. 13. Water flow rates in bypass line using three control strategies in spring test case (unhealthy system).

Fig. 14. Chilled water flow rates in secondary loop using three control strategies in spring test case (unhealthy system).

Fig. 15. Supply chilled water temperature to terminal units using three control strategies in spring test case (unhealthy system).

is artificially introduced in this study by decreasing the supply air to ask for more chilled water. When the demand secondary water
temperature set-point of the AHUs from 13 ◦ C (design condition) exceeds the primary water, the deficit flow was triggered. Three
to 10 ◦ C. An improper set-point of supply air temperature usually typical weather conditions were selected to test and evaluate the
is reset by the tenants or the operators to try to achieve a lower operation stability and energy performance of the proposed fault-
indoor air temperature. Actually, an extremely lower supply air tolerant control strategy in the unhealthy system with faults under
temperature set-point than design value forced the AHU terminals the typical spring days, mild-summer days and sunny-summer

Table 6
Electrical energy consumption under different control strategies during the five typical days (unhealthy system).

Strategies Wpump (kW h) Wchiller (kW h) Wpump + Wchiller (kW h) Wpump saving Wchiller saving Total saving

(kW h) (%) (kW h) (%) (kW h) (%)

Spring
Strategy #1 9889.0 114,643.1 124,532.2 – – – – – –
Strategy #2 6965.0 114,523.1 121,488.0 2924.1 29.57 120.0 0.10 3044.1 2.44
Strategy #3 4519.3 114,468.6 118,987.9 5369.7 54.30 174.5 0.15 5544.3 4.45

Mild-summer
Strategy #1 11,565.4 141,349.5 152,914.9 – – – – – –
Strategy #2 81,92.1 141,911.7 150,103.7 3373.3 29.17 −562.2 −0.40 2811.2 1.84
Strategy #3 75,78.2 140,405.8 147,984.0 3987.2 34.48 943.7 0.67 4930.9 3.22

Sunny-summer
Strategy #1 15,222.5 158,030.0 173,252.5 – – – – – –
Strategy #2 11,115.5 157,765.8 168,881.3 4107.0 26.98 264.2 0.17 4371.2 2.52
Strategy #3 10,508.4 157,228.6 167,737.0 4714.1 30.97 801.4 0.51 5515.5 3.18
D.-c. Gao et al. / Energy and Buildings 43 (2011) 3646–3656 3655

Fig. 16. Power consumption of secondary pumps using three control strategies in spring test case (unhealthy system).

days respectively. Every test lasted five continuous days without Above results show that the deficit flow occurred in the
stopping air-conditioning. Only detailed performance data in the unhealthy system significantly affected the energy performance
spring test case are presented here. of the chilled water system under conventional strategies (Strate-
As shown in Fig. 13, deficit flow frequently occurred in the five gies #1 and #2) whether the set-point was fixed or optimal. The
spring days under the conventional strategies (Strategies #1 and proposed strategy (Strategy #3) using flow-limiting technique was
#2). This is because that the AHU terminals demanded more chilled proved to be a fault-tolerant control strategy for secondary pumps
water than their design conditions to try to make the outlet air tem- in eliminating the deficit flow and enhancing the energy efficiency
perature reach the lowered set-point. When the set-point was too of pumps. Actually, the proposed strategy cannot diagnose the
low to be reached, the pumps had to work with full speed, resulting faults and fully correct them. However, the proposed strategy can
in highly degraded operation performance. However, the proposed relieve the energy waste of pumps caused by deficit flow as far as
fault-tolerant strategy (Strategy #3) could eliminate the deficit flow possible while still satisfying the cooling demand or delivering the
by using the flow-limiting technique in this case. Using Strategy highest possible cooling to terminal units.
#3, the frequencies of secondary pumps were restricted to limit
the secondary water flow rates and consequently the deficit flow
was eliminated. Therefore, compared with Strategies #1 and #2, 5. Conclusions
Strategy #3 offered the same cooling capacity while delivering less
chilled water flow rates to terminal units, as shown in Fig. 14. The A fault-tolerant control strategy for secondary chilled water
reason is that the elimination of deficit flow by Strategy #3 allowed pumps is developed not only for eliminating the deficit flow but also
to maintain a continuous low supply water temperature to terminal for enhancing the energy efficiency of the chilled water distribution
units, as shown in Fig. 15, which is positive for enhancing the heat systems. This fault-tolerant strategy employs the developed flow-
transfer between inlet air and inlet water in AHUs. As a result, the limiting technique that is activated when deficit flow tends to occur
chilled water system using Strategy #3 achieved a higher temper- and eliminates it by resetting the differential pressure set-point
ature difference between air and water in AHUs when compared for pumps control. This strategy also integrates optimal differen-
with that using Strategies #1 and #2. tial pressure set-point that can minimize flow resistance of chilled
Table 6 presents a summary of the electrical energy consump- water loop while still satisfying cooling energy demand.
tions of secondary pumps and chillers using the three control The operation and energy performance of the proposed fault-
strategies in the unhealthy system under three typical weather con- tolerant strategy was evaluated on a typical primary–secondary
ditions. Compared with the conventional Strategy #1 using fixed chilled water system in a high-rise building by simulation tests. In
differential pressure set-point, the proposed Strategy #3 using a healthy chilled water system, the results indicate that the pro-
optimal differential pressure set-point and flow-limiting tech- posed fault-tolerant strategy can avoid the deficit flow during the
nique saved about 5369.7 kW h (54.30%), 3987.2 kW h (34.48%), start period particularly when not all the chillers are switched on.
and 4714.1 kW h (30.97%) of the secondary pumps energy, and Compared with the two conventional control strategies, the fault-
5544.3 kW h (4.45%), 4930.9 kW h (3.22%), 5515.5 kW h (3.18%) of tolerant strategy can save about 69.27–77.25% of secondary chilled
the total energy of the pumps and chillers in the three weather water pump energy consumption during the start period due to the
conditions. The energy consumptions of the chillers using the three application of flow-limiting technique, which accounts for about
strategies were very close. The energy savings by the proposed 10.57–16.11% of the total energy of pumps and chillers. It also
strategy were mainly benefited from the reducing the consumption can save about 26.67–49.52% of the secondary chilled water pump
of secondary pumps. energy during a working day when compared with strategy using
It can be also found from Table 6 that Strategy #2 using the opti- fixed differential pressure set-point.
mal differential pressure set-point can save 26.98–29.57% of the In an unhealthy chilled water system with the occur-
secondary pump energy compared with Strategy #1 using the fixed rence of deficit flow under conventional controls, the proposed
set-point. The energy savings mainly benefited from the optimal fault-tolerant strategy was proved eliminating deficit flow and
differential pressure set-point that reduces the water resistance of improving the energy efficiency of pumps. About 30.97–54.30% of
the secondary loop. On the other hand, about 30.97–54.30% of the the secondary chilled water pump energy can be saved by using the
pump energy can be saved by Strategy #3 when compared with proposed strategy when compared with the conventional strategy
Strategy #1. This is because that Strategy #3 employs both opti- with fixed differential pressure set-point (Strategy #1), in which
mal differential pressure set-point and flow-limiting technique. about 3.99–24.73% of the secondary chilled water pumps energy
Therefore, about 3.99–24.73% of the pumps energy can be saved saving were contributed by using flow-limiting technique. This
due to the use of flow-limiting technique alone. Fig. 16 provides fault-tolerant control strategy is not complex but practical for real
the detailed comparison of the energy consumption of secondary in situ applications. The online implementation and test of the strat-
pumps under three strategies in spring test days. egy is being conducted in a real high-rise building in Hong Kong.
3656 D.-c. Gao et al. / Energy and Buildings 43 (2011) 3646–3656

Acknowledgements [10] D.P. Fiorino, How to raise chilled water temperature differentials, ASHRAE
Transactions 108 (1) (2002) 659–665.
[11] G. Avery, Improving the efficiency of chilled water plants, ASHRAE Journal 43
The research presented in this paper is financially supported by (5) (2001) 14–18.
a grant (PolyU5308/08E) of the Research Grant Council (RGC) of the [12] S.T. Taylor, Primary-only vs. primary–secondary variable flow systems, ASHRAE
Hong Kong SAR, a grant of The Hong Kong Polytechnic University. Journal 44 (2) (2002) 25–29.
[13] K.R. Luther, Chilled water system forensics, ASHRAE Transactions 108 (1) (2002)
The work is also supported by Sun Hung Kai Real Properties Limited. 654–658.
[14] W.J. Coad, A fundamental perspective on chilled water systems, HPAC Engi-
References neering 70 (8) (1998) 59–66.
[15] J.B. Rishel, System analysis vs. quick fixes for existing chilled water systems,
HPAC Engineering 70 (1) (1998) 131–133.
[1] S.W. Wang, Intelligent Buildings and Building Automation, Spon Press (Taylor [16] Z.J. Ma, S.W. Wang, W.K. Pau, Secondary loop chilled water in super high-rise,
& Francis), London and New York, 2010. ASHRAE Journal 50 (5) (2008) 42–52.
[2] W. Kirsner, Demise of the primary–secondary pumping paradigm for chilled [17] D.W. Jack, B. Thomas, G. Devine, Pump scheduling and cost optimization, Civil
water plant design, HPAC Engineering 68 (11) (1996) 73–78. Engineering Systems 8 (4) (1991) 197–206.
[3] J.P. Waltz, Variable flow chilled water or how I learned to love my VFD, Energy [18] D.V. Chase, L.E. Ormsbee, Computer-generated pumping schedules for satisfy-
Engineering 97 (6) (2000) 5–32. ing operational objectives, Journal of the American Water Works Association
[4] W. Kirsner, Rectifying the primary–secondary paradigm for chilled water plant 85 (7) (1993) 54–61.
design to deal with low T central plant syndrome, HPAC Engineering 70 (1) [19] G. Yu, R.S. Powell, M.J.H. Sterling, Optimized pump scheduling in water distri-
(1998) 128–131. bution systems, Journal of Optimization Theory and Applications 83 (3) (1994)
[5] G. Avery, Controlling chillers in variable flow systems, ASHRAE Journal 40 (2) 463–488.
(1998) 42–45. [20] G. McCormick, R.S. Powell, Optimal pump scheduling in water supply systems
[6] McQuay, Chiller Plant Design: Application Guide AG 31-003-1, McQuay Inter- with maximum demand charges, Journal of Water Resources Planning and
national, 2002. Management 129 (3) (2003) 372–379.
[7] S.T. Taylor, Degrading chilled water plant delta-T: causes and mitigation, [21] Z.J. Ma, S.W. Wang, Energy efficient control of variable speed pumps in complex
ASHRAE Transaction 108 (1) (2002) 641–653. building central air-conditioning systems, Energy and Buildings 41 (2) (2009)
[8] T.H. Durkin, Evolving design of chiller plants, ASHRAE Journal 47 (11) (2005) 197–205.
40–50. [22] Y.J. Sun, S.W. Wang, G.S. Huang, Model-based optimal start control strategy
[9] D.P. Fiorino, Achieving high chilled-water delta Ts, ASHRAE Journal 41 (11) for multi-chiller plants in commercial buildings, Building Services Engineering
(1999) 24–30. Research and Technology 31 (2) (2010) 113–129.

You might also like