Description Week 1
HSEIA - Operations Study for EPC for
BAB Integrated Facilities Project (BIFP)
Project Award and KOM
Project Execution Plan
Data Review
Environment Impact Assessment
EIA Scoping
Development of EIA and draft report submission
Control of Major Accident Hazards (COMAH)
QRA Assumption Register
QRA Study & Draft QRA Report Submission
Review of EPC Stage Bow-ties
Update of HSECSE PS
MOPO ToR, Workshop and Report
Consolidation of COMAH and draft report submission
Review of EPC Stage HSEMS and ERP Review for inclusion in HSEIA
Occupational Health Risk Assessment
Site Survey for Occupational Exposure Monitoring & Health Surveillance Plan
Development of OHRA and draft report submission
Consolidation of Operations Phase HSEIA and submission of draft HSEIA Dossier
Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8