You are on page 1of 40

EN ENGLISH

SP SERIES
Horizontal Split Case Pumps
Installation, Operation, and Maintenance Manual

franklinwater.com
Table of Contents
4 ...............INTRODUCTION
4 ...............SAFETY CONSIDERATIONS
5 ...............PUMP IDENTIFICATION
5 ...............MANUFACTURER
5 ...............TYPE OF PUMP
5 ...............DATE OF MANUFACTURE
5 ...............INSTALLATION, OPERATION & MAINTENANCE MANUAL IDENTIFICATION
5 ............... WARRANTY
5 ...............GENERAL INSTRUCTIONS
6 ...............HANDLING AND TRANSPORT
6 ...............METHOD OF TRANSPORT
6 ...............STORAGE
7 ...............INSTALLATION & ALIGNMENT
7 ...............PREPARATION
8 ...............PUMP LOCATION
8 ...............FOUNDATION
8 ...............FACTORY PRELIMINARY ALIGNMENT PROCEDURE
8 ...............RECOMMENDED PROCEDURE FOR BASE PLATE INSTALLATION & FINAL FIELD ALIGNMENT
10 ...............PIPING CONNECTION – SUCTION & DISCHARGE
11 ...............SUCTION PIPING
12 ...............DISCHARGE PIPING
13 ...............PUMP AND SHAFT ALIGNMENT CHECK
13 ...............MECHANICAL SEAL
13 ...............PACKING
13 ...............PIPING CONNECTION – SEAL/PACKING SUPPORT SYSTEM
14 ...............BEARING LUBRICATION
14 ...............COUPLING
15 ...............PUMP OPERATION
15 ...............ROTATION CHECK
15 ...............PRE START-UP CHECKS
15 ...............PRIMING
15 ...............ENSURING PROPER NPSHA
15 ...............MINIMUM FLOW
16 ...............STARTING THE PUMP AND ADJUSTING FLOW
17 ...............RUNNING THE PUMP
17 ...............OPERATION IN SUB-FREEZING CONDITIONS
17 ...............SHUTDOWN CONSIDERATIONS
17 ...............STOPPING THE PUMP
17 ...............TROUBLESHOOTING
23 ...............MAINTENANCE
23 ...............PREVENTIVE MAINTENANCE
23 ...............NEED FOR MAINTENANCE RECORDS
23 ...............NEED FOR CLEANLINESS
23 ...............MAINTENANCE OF PUMP DUE TO FLOOD DAMAGE

2
24 ...............DISASSEMBLY
25 ...............RE-ASSEMBLY
32 ...............APPENDIX A
32 ...............CRITICAL MEASUREMENTS AND TOLERANCES FOR MAXIMIZING MTBPM
34 ...............SPECIAL PARAMETERS CHECKED BY FPS-PUMPS
35 ...............APPENDIX B
36 ...............APPENDIX C

3
INTRODUCTION Maximum Lifting Speed: 15 feet/second.

The pumps covered in this manual, when installed correctly, will last If in a climate where the fluid in the system could freeze, never leave
for many years in service. In order to gain the most from this equip- liquid in the pump casing. Drain the system completely. During win-
ment, this manual should be read thoroughly and followed during all ter months and cold weather, the liquid could freeze and damage the
stages of installation and operation. system components. Always remember to drain the casing assemblies
complete.
SAFETY CONSIDERATIONS Do not run the equipment dry or start the pump without the proper
The Franklin Electric SP Series Horizontal Split Case pumps have been prime (flooded system). Significant damage can occur to the unit if
designed and manufactured for safe operation. In order to ensure safe even run for a short time period without a fully filled casing assembly.
operation, it is very important that this manual be read in its entirety
prior to installing or operating the system. Franklin Electric shall not Never operate the pump(s) for more than a short interval with the
be liable for physical injury, damage or delays caused by a failure to discharge valve closed. The length of the interval depends on several
observe the instructions for installation, operation and maintenance factors including the nature of the fluid pumped and it’s temperature.
contained in this manual. Technical Support for additional support if required.

Remember that every pump has the potential to be dangerous be- Never operate the system with a closed suction valve.
cause of the following factors:
Excessive pump noise or vibration may indicate a dangerous operating
• Parts are rotating at high speeds condition. The pump must be shut down immediately.
• High pressures may be present
Do not operate the pump and/or the system for an extended period of
• High temperatures may be present
time below the recommended minimum flow.
• Highly corrosive and/or toxic chemicals may be present
It is absolutely essential that the rotation of the motor be checked
Paying constant attention to safety is always extremely important.
before starting any pump in the system. Incorrect rotation of the
However, there are often situations that require special attention.
pump(s) for even a short period of time can cause severe damage to
These situations are indicated throughout this book by the following
the pumping assembly.
symbols:
If the liquid is hazardous, take all necessary precautions to avoid dam-
age and injury before emptying the pump casing.

Residual liquid may be found in the pump casing, suction and


discharge manifolds. Take the necessary precautions if the liquid is
DANGER - Immediate hazards which WILL result in severe personal hazardous, flammable, corrosive, poisonous, infected, etc.
injury or death.
Always lockout power to the driver before performing pump mainte-
nance.

Never operate the pump without the coupling guard (if supplied) and
all other safety devices correctly installed.

Do not apply heat to disassemble the pump or to remove the impeller.


WARNING – Hazards or unsafe practices which COULD result in severe Entrapped liquid could cause an explosion.
personal injury or death.
If any external leaks are found while pumping hazardous product, im-
mediately stop operations and repair.

CAUTION – Hazards or unsafe practices which COULD result in minor


personal injury or product or property damage.

4
PUMP IDENTIFICATION WARRANTY
MANUFACTURER This product is covered by a Limited Warranty for a period of 12
months from the date of original purchase by the consumer. For
Franklin Electric complete warranty information, refer to www.franklinwater.com; or,
125 Morrison Drive contact Technical Support for a printed copy.
Rossville, TN 38066
United States of America Phone: (901) 850-5115
Fax: (901) 850-5119

TYPE OF PUMP
GENERAL INSTRUCTIONS
The Franklin Electric SP split case pump is a horizontal, double suc-
tion, single stage, axially split centrifugal pump. The pump and motor unit must be examined upon arrival to ascer-
tain any damage caused during shipment. If damaged immediately
DATE OF MANUFACTURE notify the carrier and/or the sender. Check that the goods correspond
exactly to the description on the shipping documents and report any
The date of manufacture is indicated on the pump data plate. differences as soon as possible to the sender. Always quote the pump
type and serial number stamped on the data plate.
INSTALLATION, OPERATION & MAINTENANCE
The pumps must be used only for applications for which the manufac-
MANUAL IDENTIFICATION turers have specified:

All pumps are identified by serial number, model number and size. • The construction materials
This information is stamped on a stainless steel identification plate • The operating conditions (flow, pressure, temperature,
which is permanently attached to the pump. Do not remove this plate etc.)
as it will be impossible to identify the pump without it. Refer to the • The field of application
pump information in this manual for specific information.
In case of doubt, contact Technical Support.
NAMEPLATE INFORMATION Upon receipt of the pump, a visual check should be made to deter-
mine if any damage has been incurred during transit or shipment. The
main areas to diligently inspect are:

• Broken or cracked castings, including the base, motor,


pump feet and suction and discharge flanges
• Bent or damaged shafts
• Broken motor end bells, bent lifting eye bolts or damaged
conduit boxes on the driver
• Missing parts

Parts and/or accessories are sometimes wrapped individually or fas-


tened to the equipment. Coupling hubs are shipped in separate boxes.
If any damage or loss has been incurred, promptly contact Technical
FIGURE 1 – Pump Data Plate
Support and the freight company that delivered the equipment.
MODEL : Pump model designation
S/N : Pump Serial Number
PEICL : Pump Energy Index
P/N : Pump Part Number
SIZE : Discharge x Suction - # of Stages
GPM : Pump Rated Capacity
RPM : Pump Rated Speed
TDH : Pump Rated Total Dynamic Head
BHP : Pump Max HP
IMP DIA. : Impeller Trim Diameter

5
HANDLING AND TRANSPORT Read and follow the storage instructions carefully because care of the
pump during this period before installation can be as important as
maintenance after operation has begun.
METHOD OF TRANSPORT
Check all parts against the packing list to make sure nothing is miss-
The pump must be transported in the horizontal position ing. It is much better to find out now than during the installation.
Report any discrepancies immediately to Technical Support.
INSTALLATION
During installation and maintenance, all components must be handled
STORAGE
and transported securely by using suitable slings. Handling must be
carried out by specialized personnel to avoid damage to the pump SHORT-TERM STORAGE
and persons. The lifting rings attached to various components should
be used exclusively to lift the components for which they have been Normal packaging is designed to protect the pump during shipment
supplied. and for dry, indoor storage for up to two months or less. If the pump
is not to be installed or operated soon after delivery, store the unit in
a clean, dry place, having slow changes in environmental conditions.
Steps should be taken to protect the pump against moisture, dirt and
foreign particulate intrusion. The procedure followed for this short-
term storage is summarized below:

Standard Protection for Shipment :


Maximum lifting speed: 15 feet/second
a. Loose unmounted items, including, but not limited
It is important to exercise extreme care in handling and installing all to, oilers, packing, coupling spacers, stilts and mechanical
parts. Certain items are precision machined for proper alignment and, seals are packaged in a waterproof plastic bag and placed
if dropped, banged, sprung, or mistreated in any way, misalignment under the coupling guard. Larger items are boxed and metal
and malfunction will result. Other components, such as the electrical banded to the base plate. For pumps not mounted on a base
cable, may be vulnerable to gouging or scuffing. Parts which are too plate, the bag and/or carton is placed inside the shipping
heavy to be lifted from the transporting car or truck should be skidded carton. All parts bags and cartons are identified with the FPS
slowly and carefully to the ground to prevent damage. Never unload sales order number, the customer purchase order number
by dropping parts directly from the carrier to the ground and never and the pump item number (if applicable).
use shipping crates for skids.
b. Inner surfaces of the bearing housing, shaft (area through
bearing housing) and bearings are coated with Cortec VCI-
329 rust inhibitor or equal.

Note: Bearing housings are not filled with oil prior to ship-
ment.

For complete base mounted assemblies, NEVER lift on the pump or c. Regreasable bearings are packed with grease (Exxon
motor. Always lift equally at the four corners of the base assembly. Mobile Polyrex EM).

If job site conditions permit, you may be able to install directly from d. After a performance test, if required, the pump is tipped
the truck that delivered the pump. If not, move the components to the on the suction flange for drainage (some residual water
installation area and lay them out in a clean and protected space con- may remain in the casing). Then, internal surfaces of fer-
venient to the work location. Column pipe sections should be placed rous casings, covers, flange faces and the impeller surface
on suitable timbers to keep them out of the dirt, arranged so that the are sprayed with Calgon Vestal Labs RP-743m, or equal.
coupling ends point toward the wellhead. The motor assembly should Exposed shafts are taped with Polywrap.
be left on the skids until lifted for installation. The power cable and
motor leads must receive special protection to avoid damage to the e. Flange faces are protected with plastic covers secured
jacket or insulation. with plastic drive bolts. 3/16 in (7.8 mm) steel or 1/4 in (6.3
mm) wood covers with rubber gaskets, steel bolts and nuts
If installation cannot begin within a few days after delivery, segre- are available at extra cost.
gate and identify all components of the shipment so they won’t be
confused with other equipment arriving at the job site.

6
f. All assemblies are bolted to a wood skid which confines assembly to provide protection from the elements and handling. This
the assembly within the perimeter of the skid. packaging will provide protection up to twelve months without dam-
age to mechanical seals, bearings, lip seals, etc. due to humidity, salt
g. Assemblies with special paint are protected with a plastic laden air, dust, etc. After unpacking, protection will be the responsi-
wrap. bility of the user. Addition of oil to the bearing housing will remove
the inhibitor. If units are to be idle for extended periods after addition
h. Bare pumps, when not mounted on base plates, are of lubricants, inhibitor oils and greases should be used.
bolted to wood skids.
Every three months, the shaft should be rotated approximately 10
i. All assemblies having external piping (seal flush and cool- revolutions.
ing water plans), etc. are packaged and braced to withstand
normal handling during shipment. In some cases compo- INSTALLATION & ALIGNMENT
nents may be disassembled for shipment. The pump must be
stored in a covered, dry location. PREPARATION
It is recommended that the following procedure is taken: Before installing the pump, clean the suction and discharge flanges
thoroughly. Remove any protective coatings that may be on the shaft.
1. Ensure that the bearings are packed with the recom-
mended grease (if grease lubricated) or coated with oil (if If the pump is coming from Short-Term or Long-Term storage and has
oil lubricated) to prevent moisture from entering the bearing been prepared for storage in the manner above, remove all grease
housings. and/or oil from the bearings. The bearings should be flushed with an
appropriate fluid to remove any contamination prior to placing the
2. Remove all glands, packing and lantern rings from the
pump into service.
stuffing box (if packed). If the pump is supplied with a
mechanical seal, remove the mechanical seal and coat it with
a light film of oil. PUMP LOCATION
3. Ensure that the suction and discharge flanges are covered The pump should be installed as close to the source of the liquid as
and secured with cardboard, plastic or wood to prevent the job-site allows, with the shortest and most direct suction line
foreign objects from entering the pump. possible.

4. If the pump is to be stored outdoors with no overhead The pump should also be installed with future inspection and mainte-
covering, cover the unit with a tarp or other suitable cover- nance in mind. Ample space and headroom for a lifting crane or hoist
ing. to sufficiently lift the entire unit should be considered.

Ensure that there is suitable power available for the pump driver.
LONG-TERM STORAGE You must confirm that the appropriate power is available and that it
matches the requirements on the motor data plate.
Long-term storage is defined as more than two months, but less than
12 months. The procedure Franklin Electric follows for long-term stor-
age of pumps is given below. These procedures are in addition to the FOUNDATION
short-term procedure above.
The foundation should be sufficiently sized to reduce vibration and
Solid wood skids are utilized. Holes are drilled in the skid to accom- rigid enough to avoid any movement both axially and/or radially. The
modate the anchor bolt holes in the base plate, or the casing and foundation mass should be four (4) to six (6) times the complete mass
bearing housing feet holes on assemblies less base plate. Tackwrap of the entire pumping assembly.
sheeting is then placed on top of the skid and the pump assembly is
placed on top of the Tackwrap. Metal bolts with washers and rub- The foundation should be poured without interruption to within 0.500
ber bushings are inserted through the skid, the Tackwrap and the in. (13 mm) to 1.500 in. (38 mm) of the finished height. The top sur-
assembly from the bottom of the skid and are then secured with hex face of the foundation should be well scored and grooved before the
nuts. When the nuts are “snugged” down to the top of the base plate concrete sets. This provides a bonding surface for the grout. Founda-
or casing and bearing housing feet, the rubber bushing is expanded, tion bolts should be set into the concrete as shown in FIGURE 2. Allow
sealing the hole from the atmosphere. Desiccant bags are placed on enough bolt length for grout, shims, lower baseplate flange, nuts and
the Tackwrap. The Tackwrap is drawn up around the assembly and washers. The foundation should be allowed to cure for several days
hermetically (heat) sealed across the top. The assembly is com- before the baseplate is shimmed and grouted.
pletely sealed from the atmosphere and the desiccant will absorb
any entrapped moisture. A solid wood box is then used to cover the
7
FACTORY PRELIMINARY ALIGNMENT RECOMMENDED PROCEDURE FOR BASE
PROCEDURE PLATE INSTALLATION & FINAL FIELD
The purpose of factory alignment is to ensure that the user will have
ALIGNMENT
full utilization of the clearance in the motor holes for final job-site
alignment. To achieve this, the factory alignment procedure speci- NEWLY GROUTED BASE PLATES
fies that the pump be aligned in the horizontal plane to the motor,
with the motor foot bolts centered in the motor holes. This procedure 1. The pump foundation should be located as close to
ensures that there is sufficient clearance in the motor holes for the the source of the fluid to be pumped as practical. There
customer to field align the motor to the pump, to zero tolerance. This should be adequate space for workers to install, operate
philosophy requires that the customer be able to place the base in the and maintain the pump. The foundation should be suf-
same condition as was the case at the factory. Thus the factory align- ficient to absorb any vibration and should provide a rigid
ment will be done with the base sitting in an unrestrained condition support for the pump and motor. Recommended mass of a
on a flat and level surface. This standard also emphasizes the need to concrete foundation should be four (4) to six (6) times that
ensure the shaft spacing is adequate to accept the specified coupling of the pump, motor and base. Note that foundation bolts
spacer. The factory alignment procedure is summarized below: are imbedded in the concrete inside a sleeve to allow some
movement of the bolt.
1. The base plate is placed on a flat and level work bench in a
free and unstressed position. 2. Level the pump base plate assembly. If the base plate has
machined coplanar mounting surfaces, these machined sur-
2. The base plate is leveled as necessary. Leveling is accom- faces are to be referenced when leveling the base plate. This
plished by placing shims under the rails (or feet) of the base may require that the pump and motor be removed from the
at the appropriate anchor bolt hole locations. Levelness is base plate in order to reference the machined faces. If the
checked in both the longitudinal and lateral directions. base plate is without machined coplanar mounting surfaces,
the pump and motor are to be left on the base plate. The
3. The motor and appropriate motor mounting hardware is proper surfaces to reference when leveling the pump base
placed on the base plate and the motor is checked for any plate assembly are the pump suction and discharge flanges.
planar soft-foot condition. If any is present it is eliminated DO NOT stress the base plate. DO NOT bolt the suction or
by shimming. discharge flanges of the pump to the piping until the base
plate foundation is completely installed. If equipped, use
4. The motor feet holes are centered around the motor leveling jackscrews to level the base plate. If jackscrews
mounting fasteners. are not provided, shims and wedges should be used. See
FIGURE 2. Check for levelness in both the longitudinal and
5. The motor is fastened in place by tightening the nuts on lateral directions. Shims should be placed at all base anchor
two diagonal motor mounting studs. bolt locations and in the middle edge of the base if the base
is more than five feet long. Do not rely on the bottom of the
6. The pump is put onto the base plate and leveled. If an base plate to be flat. Standard base plate bottoms are not
adjustment is necessary, we add or delete shims between the machined and it is not likely that the field mounting surface
pump foot and the base plate. is flat.

7. The spacer coupling gap is verified. 3. After leveling the base plate, tighten the anchor bolts.
If shims were used, make sure that the base plate was
8. The parallel and angular vertical alignment is made by shimmed near each anchor bolt before tightening. Failure to
shimming under the motor. do this may result in a torsional twist of the base plate which
could make it impossible to obtain final alignment. Check
9. All four motor feet are tightened down. the level of the base plate to make sure that tightening the
anchor bolts did not disturb the level of the base plate. If
10. The pump and motor shafts are then aligned horizon-
the anchor bolts did change the level adjust the jackscrews
tally, in both parallel and angular, by moving the pump to
or shims as needed to level the base plate. Continue adjust-
the fixed motor. The pump feet are tightened down.
ing the jackscrews or shims and tightening the anchor bolts
until the base plate is level.
11. Both horizontal and vertical alignment are again final
checked as is the coupling spacer gap.
4. Check initial alignment. If the pump and motor were
removed from the base plate proceed with step 5 first, the
pump and motor should be reinstalled onto the base plate

8
using Franklin Electric Factory Preliminary Alignment Pro- c. The area under an elevated motor pedestal should also
cedure and then continue with the following. As described be completely filled with grout.
above, pumps are given a preliminary alignment at the
factory. This preliminary alignment is done in a way that d. After the grout has thoroughly hardened, check the
ensures that, if the installer duplicates the factory condi- foundation bolts and tighten if necessary.
tions, there will be sufficient clearance between the motor
hold down bolts and motor foot holes to move the motor e. Approximately 14 days after the grout has been poured
into final alignment. If the pump and motor were properly or when the grout has thoroughly dried, apply an oil base
reinstalled to the base plate or if they were not removed paint to the exposed edges of the grout to prevent air and
from the base plate and there has been no transit dam- moisture from coming in contact with the grout.
age and if the above steps where done properly, the pump
and driver should be within 0.015 in. (0.38 mm) FIM (Full Make sure that the grout fills the area under the base plate.
Indicator Movement) parallel and 0.0025 in/in (0.0025 mm/ After the grout has cured, check for voids and repair them.
mm) FIM angular. If this is not the case first check to see if
the driver mounting fasteners are centered in the driver feet 6. Run piping to the suction and discharge of the pump.
holes. If not, re-center the fasteners and perform a prelimi- There should be no piping loads transmitted to the pump
nary alignment to the above tolerances by shimming under after connection is made. Recheck the alignment to verify
the motor for vertical alignment and by moving the pump for that there are no significant loads.
horizontal alignment.
7. Perform final alignment. Check for soft-foot under the
3/4” TO 1-1/2” LEVELING WEDGES
ALLOWANCE OR SHIM - driver. An indicator placed on the coupling, reading in the
FOR GROUT LEFT IN PLACE vertical direction should not indicate more than 0.002 in
(0.05 mm) movement when any driver fastener is loosened.
FINISH GROUTING Align the driver first in the vertical direction by shimming
underneath its feet. When satisfactory alignment is ob-
1/4” GROUT
tained the number of shims in the pack should be minimized.
It is recommended that no more than five shims be used
under any foot. Final horizontal alignment is made by mov-
ing the driver. Maximum pump reliability is obtained by hav-
ing near perfect alignment. Franklin Electric recommends
no more than 0.002 in (0.05mm) parallel and 0.0005 in/in
(0.0005 mm/mm) angular misalignment.

8. Operate the pump for at least an hour or until it reaches


final operating temperature. Shut the pump down and
PIPE SLEEVE recheck alignment while the pump is hot. Piping thermal
expansion may change the alignment. Realign pump as
DAM
WASHER necessary.
LUG
EXISTING GROUTED BASE PLATES
When a pump is being installed on an existing grouted base plate, the
TOP OF FOUNDATION LEFT
ROUGH - CLEAN AND WET DOWN procedure is somewhat different from the previous section “NEWLY
GROUTED BASE PLATES.”
FIGURE 2 – Base Plate Foundation
1. Mount the pump on the existing base plate.
5. Grout the base plate. A non-shrinking grout should be
used. Grout compensates for uneven foundation, distributes 2. Level the pump by putting a level on the discharge flange.
weight of unit and prevents shifting. Use an approved, non- If not level, add or delete shims between the pump foot and
shrinking grout after setting and leveling unit. the base plate.
a. Build strong form around the foundation to contain 3. Check initial alignment. (Step 4 above)
grout.
4. Run piping to the suction and discharge flanges of the
b. Soak top of concrete foundation thoroughly, then pump. (Step 6 above)
remove surface water.

9
5. Perform final alignment. (Step 7 above) Install piping as straight as possible, avoiding unnecessary bends.
Where necessary, use 45-degree or long sweep 90-degree fitting to
6. Recheck alignment after pump is hot. (Step 8 above) decrease friction losses.

All piping must be independently supported, accurately aligned and Make sure that ALL piping joints are air-tight.
preferably connected to the pump by a short length of flexible pip-
ing. The pump should not have to support the weight of the pipe or Where flanged joints are used, assure that inside diameters match
compensate for misalignment. It should be possible to install suction properly.
and discharge bolts through mating flanges without pulling or prying
either of the flanges. All piping must be tight. Pumps may vapor- Remove burrs and sharp edges when making up joints.
lock if air is allowed to leak into the piping. If the pump flange(s)
have tapped holes, select flange fasteners with thread engagement at Do not “spring” piping when making any connections.
least equal to the fastener diameter but that do not bottom out in the
tapped holes before the joint is tight. Provide for pipe expansion when hot fluids are to be pumped.

All alignment procedures should be conducted while the unit is cold SUCTION PIPING
and then checked when the unit is up to operating temperature. For
high temperature applications, a hot alignment must also be con- When installing the suction piping, observe the following precautions.
ducted to make sure that the thermal expansion of the entire assembly See FIGURE 3.
is taken into consideration.
The sizing and installation of the suction piping is extremely impor-
After final alignment, the pump and driver feet can be dowel to the tant. It must be selected and installed so that pressure losses are
baseplate to make sure nothing moves while operating in service. minimized and sufficient liquid will flow into the pump when started
and operated. Many NPSH (Net Positive Suction Head) problems can
PIPING CONNECTION – SUCTION & be attributed directly to improper suction piping systems.

DISCHARGE Friction losses caused by undersized suction piping can increase the
fluid’s velocity into the pump. As recommended by the Hydraulic
When installing the pump piping, be sure to observe the following Institute Standard ANSI/HI 1.1-1.5-1994, suction pipe velocity should
precautions: not exceed the velocity in the pump suction nozzle. In some situations
pipe velocity may need to be further reduced to satisfy pump NPSH
Piping should always be run to the pump. requirements and to control suction line losses. Pipe friction can be
reduced by using pipes that are one to two sizes larger than the pump
Do not move pump to pipe. This could make final alignment impos- suction nozzle in order to maintain pipe velocities less than 5 feet/
sible. second.
Both the suction and discharge piping should be supported inde- Suction piping should be short in length, as direct as possible and
pendently near the pump and properly aligned, so that no strain is never smaller in diameter than the pump suction opening.
transmitted to the pump when the flange bolts are tightened. Use
pipe hangers or other supports at necessary intervals to provide If the suction pipe is short, the pipe diameter can be the same size as
support. When expansion joints are used in the piping system, they
must be installed beyond the piping supports closest to the pump. Tie the suction opening. If longer suction pipe is required, pipes should
bolts should be used with expansion joints to prevent pipe strain. Do be one or two sizes larger than the opening, depending on piping
not install expansion joints next to the pump or in any way that would length.
cause a strain on the pump resulting from system pressure changes. It
Suction piping for horizontal double suction pumps should not be
is usually advisable to increase the size of both suction and discharge
installed with an elbow close to the suction flange of the pump, except
pipes at the pump connections to decrease the loss of head from fric-
when the suction elbow is in the vertical plane.
tion.
A suction pipe of the same size as the suction nozzle, approaching
at any angle other than straight up or straight down, must have the
elbow located 10 pipe diameters from the suction flange of the pump.
Vertical mounted pumps and other space limitations require special
piping.
Piping Forces: Take care during installation and operation to minimize
pipe forces and/or moments on the pump casing.

10
CHECK VALVE
GATE VALVE There is always an uneven turbulent flow around an elbow. When it is
SUCTION PIPE INSTALLED WITH
A GRADUAL RISE TO PUMP INCREASER in a position other than the vertical it causes more liquid to enter one
LEVEL side of the impeller than the other. See FIGURE 4. This results in high
un-equalized thrust loads that will overheat the bearings and cause
CL OF PIPE CORRECT
rapid wear, in addition to affecting hydraulic performance.

AIR POCKET When operating on a suction lift, the suction pipe should slope
upward to the pump nozzle. A horizontal suction line must have a
gradual rise to the pump. Any high point in the pipe will become
filled with air and thus prevent proper operation on the pump. When
INCORRECT
reducing the piping to the suction opening diameter, use an eccentric
reducer with the eccentric side down to avoid air pockets.

AIR POCKET NOTE: When operating on suction lift, never use a straight taper
reducer in a horizontal suction line as it tends to form an air pocket in
the top of the reducer and the pipe.
INCORRECT
To facilitate cleaning pump liquid passage without dismantling pump,
a short section of pipe (Dutchman or spool piece), so designed that
AIR POCKET
it can be readily dropped out of the line, can be installed adjacent to
the suction flange. With this arrangement, any matter clogging the
impeller is accessible by removing the nozzle (or pipe section).
INCORRECT
WATER PRESSURE
INCREASES HERE CAUSING CASING RINGS
A GREATER FLOW TO ONE PUMP CASING
GRADUAL RISE
TO PUMP SIDE OF THE IMPELLER

NO AIR
POCKETS
CORRECT

NO AIR GRADUAL RISE


POCKETS TO PUMP
PUMP SUCTION
FLANGE IMPELLER
SUCTION
ECCENTRIC
REDUCER ELBOW
CORRECT
FIGURE 4 – Un-equalized Thrust Loads
DISTANCE PLUS
ECCENTRIC REDUCER
STRAIGHTENS FLOW

CORRECT

PATH OF
WATER

INCORRECT

FIGURE 3 – Good Piping Practices

11
Valves in Suction Piping
When installing valves in the suction piping, observe the following
precautions:

a. If the pump is operating under static suction lift condi-


tions, a foot valve may be installed in the suction line to When fluid velocity in the pipe is high, for example 10 ft/s (3 m/s)
avoid the necessity of priming each time the pump is started. or higher, a rapidly closing discharge valve can cause a damaging
This valve should be of the flapper type, rather than the pressure surge. A dampening arrangement should be provided in the
multiple spring type, sized to avoid excessive friction in the piping.
suction line. (Under all other conditions, a check valve, if
used, should be installed in the discharge line (See “Valves Pressure Gauges
in Discharge Piping” below).
Properly sized pressure gauges should be installed in both the suc-
b. When foot valves are used or where there are other possi- tion and discharge nozzles in the gauge taps (which are provided on
bilities of “water hammer,” close the discharge valve slowly request). All SP split case pumps have a suction and discharge gauge
before shutting down the pump. tap supplied standard. The gauges will enable the operator to easily
observe the operation of the pump, and also determine if the pump
c. Where two or more pumps are connected to the same suc- is operating in conformance with the performance curve. If cavita-
tion line, install gate valves so that any pump can be isolated tion, vapor binding or other unstable operation should occur, widely
from the line. Gate valves should be installed on the suction fluctuating discharge pressure will be noted.
side of all pumps with a positive pressure for maintenance
purposes. Install gate valves with stems horizontal to avoid Pump Insulation
air pockets. Globe valves should not be used, particularly
where NPSH is critical. On chilled water applications most pumps are insulated. As part of
this practice, the pump bearing housings should not be insulated since
d. The pump must never be throttled by the use of a valve this would tend to “trap” heat inside the housing.
on the suction side of the pump. Suction valves should be
used only to isolate the pump for maintenance purposes and This could lead to increased bearing temperatures and premature
should always be installed in positions to avoid air pockets. bearing failures.

e. A pump drain valve should be installed in the suction pip-


ing between the isolation valve and the pump.
PUMP AND SHAFT ALIGNMENT CHECK
After connecting piping, rotate the pump drive shaft clockwise (view
DISCHARGE PIPING from motor end) by hand several complete revolutions to be sure
there is no binding and that all parts are free. Recheck shaft align-
If the discharge piping is short, the pipe diameter can be the same as ment. If piping caused unit to be out of alignment, correct piping to
the discharge opening. If the piping is long, pipe diameter should be relieve strain on the pump.
one or two sizes larger than the discharge opening. On long horizon-
tal runs, it is desirable to maintain as even a grade as possible. Avoid
high spots, such as loops, which will collect air and throttle the system
MECHANICAL SEAL
or lead to erratic pumping. When the pump is intended to be equipped with a mechanical seal, it
is Franklin Electric standard practice to install the mechanical seal in
Valves in Discharge Piping the pump prior to shipment. Specific order requirements may specify
that the seal be shipped separately, or none be supplied. It is the
A triple duty valve should be installed in the discharge. The triple pump installer’s responsibility to determine if a seal was installed. If a
duty valve placed on the pump protects the pump from excessive back seal was supplied but not installed, the seal and installation instruc-
pressure and prevents liquid from running back through the pump in tions will be shipped with the pump.
case of power failure.

12
(69 to 103 kPa) above the stuffing box pressure.

The gland should be adjusted to give a flow rate of 20 to 30 drops per


minute for clean fluid. For abrasive applications, the regulated flow
rate should be 1-2 gpm (0.06-0.13 l/s).

Failure to ensure that a seal is installed may result in serious leakage of Grease lubrication, when compatible with the pumpage, may be used.
the pumped fluid. In non-abrasive applications the pumpage itself may be sufficient to
lubricate the packing without need for external lines.
Seal and seal support system must be installed and operational as
specified by the seal manufacturer. Abrasive Packing Arrangement – The installation procedures are the
same as the standard packing with some exceptions. A special lip seal
Mechanical seals are preferred over packing on some applications is installed first, followed by two lantern ring assemblies, then two of
because of better sealing qualities and longer serviceability. the packing rings provided.

Leakage is eliminated when a seal is properly installed, and normal A flush line from a clean external source should be connected to the
life is much greater than that of packing on similar applications. top of the stuffing box.

Pumps containing single mechanical seals normally utilize the BEARING LUBRICATION
pumped liquid to lubricate the seal faces. This method is preferred
when the pumped liquid is neither abrasive nor corrosive. Grease lubricated ball bearings are packed with grease at the factory
and ordinarily will require no attention before starting, provided the
PACKING pump has been stored in a clean, dry place prior to its first operation.
The bearings should be watched the first hour or so after the pump has
When the pump is intended to be equipped with shaft packing, it is been started to see that they are operating properly.
Franklin Electric standard practice to install the packing in the stuff-
ing box prior to shipment. It is the pump installer’s responsibility to The importance of proper lubrication cannot be over emphasized. It
check the packing in the stuffing box and that the packing leakage is is difficult to say how often a bearing should be greased since that
adjusted properly. depends on the conditions of operation. It is well to add one ounce of
grease at regular intervals but it is equally important to avoid adding
too much grease. For average operating conditions, it is recommend-
ed that 1 oz. of grease be added at intervals of three to six months
and only clean grease be used. It is always best if unit can be stopped
while grease is added to avoid overloading.

Failure to ensure that packing is installed may result in serious leakage


of the pumped fluid.

PIPING CONNECTION – SEAL/PACKING


SUPPORT SYSTEM
Excess grease is the most common cause of overheating.

A lithium based NLGI-2 grade grease should be used for lubricating


bearings where the ambient temperature is above -20°F. Grease lu-
bricated bearings are packed at the factory with Exxon Mobile Polyrex
EM. Other recommended greases are Texaco Multifak 2, Shell Alvania
2 and Mobilux No. 2 grease. Greases made from animal or vegetable
oils are not recommended due to the danger of deterioration and
If the pump has a seal support system, it is mandatory that this system forming of acid. Do not use graphite. Use of an ISO VG 100 mineral
be fully installed and operational before the pump is started. base oil with rust and oxidation inhibitors is recommended.
If packing is used: The maximum desirable operating temperature for ball bearings is
180°F. Should the temperature of the bearing housing rise above
Packing Lubrication – Water, when compatible with the pumpage,
180°F, the pump should be shut down to determine the cause.
should be introduced into the packing box at a pressure 10 to 15 PSI

13
Quality mineral oil with rust and oxidation inhibi- PUMP OPERATION
Mineral Oil tors. Mobile DTE Heavy/Medium ISO VG 68 or
equivalent. ROTATION CHECK
Royal Purple SynFilm 68, Conoco SYNCON 68 or
Synthetic equivalent. Some synthetic lubricants require
Viton O-rings.
Grease Exxon Mobile Polyrex EM, Chevron SRI #2 (or
compatible).

It is absolutely essential that the rotation of the motor be checked


FIGURE 5 – Recommended Lubricants
before connecting the shaft coupling. Incorrect rotation of the pump,
for even a short time, can dislodge and damage the shaft sleeves,
Maximum Oil Tem- ISO Viscosity Minimum Viscosity impeller, casing, shaft and shaft seal.
perature Grade Index
Up to 160°F (71°C) 46 95 SP pumps can turn clockwise or counter-clockwise and therefore
rotation must be specified at time of order. Right-hand rotation is
160-175°F (71°- 68 95
standard unless otherwise specified.
80°C)
175-200°F (80°- 100 95
94°C)
PRE START-UP CHECKS
Prior to starting the pump it is essential that the following checks are
FIGURE 6 – Oil Viscosity Grades
made. These checks are all described in detail in the Maintenance Sec-
tion of this booklet.
Under 60°F 160-175°F 175-200°F
Lubricant
(71°C) (71-80°C) (80-94°C) • Pump and Motor properly secured to the base plate and
Grease 6 mo 3 mo 1.5 mo the complete assembly is properly grouted
• Check alignment of pump and motor
Mineral Oil 6 mo 3 mo 1.5 mo • Coupling guard in place and not rubbing
Synthetic • Rotation check, see above
18 mo 18 mo 18 mo
Oil**
THIS IS ABSOLUTELY ESSENTIAL
FIGURE 7 – Re-lubrication Intervals
• Shaft seal and/or packing properly installed
Bearing lubrication, regardless of whether it is grease or oil, must • Seal support system operational
be checked prior to any rotational check or operation of the pump • Bearing lubrication (Pump & Driver)
unit. Bearings run without lubrication will catastrophically fail in an • Pump instrumentation is operational
extremely short time period. • Pump is primed
• Rotation of shaft by hand with no rubbing of components
COUPLING • Motor is correctly wired to the starting device, voltage has
been checked, phase and frequency at the job-site match the
A direction arrow is cast on the casing. Make sure the motor rotates in motor nameplate
the same direction before coupling the motor to the Pump.
As a final step in preparation for operation, it is important to rotate
It is absolutely essential that the rotation of the motor be checked the shaft by hand to be certain that all rotating parts move freely and
before connecting the shaft coupling. Incorrect rotation of the pump, that there are no foreign objects in the pump.
for even a short time, can dislodge the shaft sleeves which may cause
serious damage to the pump. PRIMING
The coupling should be installed as advised by the coupling manufac- If the pump is installed with a positive head on the suction, it can be
turer. Pumps are shipped without the spacer installed. If the spacer primed by opening the suction and vent valve and allowing the liquid
has been installed to facilitate alignment it must be removed prior to to enter the casing. If the pump is installed with a suction lift, priming
checking rotation. Remove protective material from the coupling and must be done by other methods such as foot valves, ejectors or by
any exposed portions of the shaft before installing the coupling. manually filling the casing and suction line.

14
ENSURING PROPER NPSHA 60 Hz 50 Hz

Pump Size Minimum Minimum


Net Positive Suction Head – Available (NPSHA) is the measure of the
RPM Flow RPM Flow
energy in a liquid above the vapor pressure. It is used to determine
(% of BEP) (% of BEP)
the likelihood that a fluid will vaporize in the pump. It is critical
because a centrifugal pump is designed to pump a liquid, not a vapor. Module 1 3500 25% 2900 21%
Vaporization in a pump will result in damage to the pump, deteriora- Module 1 1750 25% 1450 21%
tion of the Total Differential Head (TDH) and possibly a complete
Module 2 3500 25% 2900 21%
stopping of pumping.
Module 2 1750 33% 1450 28%
Net Positive Suction Head – Required (NPSHR) is the decrease of fluid All Other
energy between the inlet of the pump and the point of lowest pressure ANY 15% ANY 15%
Sizes
in the pump. This decrease occurs because of friction losses and fluid
accelerations in the inlet region of the pump and particularly accelera- FIGURE 8 - Minimum Continuous Safe Flow
tions as the fluid enters the impeller vanes. The value for NPSHR for
the specific pump purchased is given in the pump data sheet and on Note: “Minimum intermittent flow” value of 50% of the “minimum
the pump performance curve. continuous flow” as long as that flow is greater than the “minimum
thermal flow.”
For a pump to operate properly the NPSHA must be greater than the
NPSHR. Good practice dictates that this margin should be at least 5 ft All SP pumps also have a “Minimum Thermal Flow.” This is defined as
(1.5 m) or 20%, whichever is greater. the minimum flow that will not cause an excessive temperature rise.
Minimum Thermal Flow is application dependent.

Ensuring that NPSHA is larger than NPSHR by the suggested margin


will greatly enhance pump performance and reliability. It will also
reduce the likelihood of cavitation, which can severely damage the Do not operate the pump below Minimum Thermal Flow, as this could
pump. cause an excessive temperature rise. Contact Technical Support for
determination of Minimum Thermal flow.

MINIMUM FLOW
STARTING THE PUMP AND ADJUSTING FLOW
Minimum continuous stable flow is the lowest flow at which the pump
can operate and still conform to the bearing life, shaft deflection and 1. Open the suction valve to full open position. It is very
bearing housing vibration limits of the HI standard. Pumps may be important to leave the suction valve open while the pump
operated at lower flows, but it must be recognized that the pump may is operating. Any throttling or adjusting of flow must be
not conform to one or more of these limits. For example, vibration done through the discharge valve. Partially closing the suc-
may exceed the limit set by the HI standard. The size of the pump, the tion valve can create serious NPSH and pump performance
energy absorbed and the liquid pumped are some of the consider- problems.
ations in determining the minimum flow.
Never operate pump with both the suction and discharge valves
Typically, limitations of 20% of the capacity at the best efficiency closed. This could cause an explosion.
point (BEP) should be specified as the minimum flow. However,
2. A standard centrifugal pump will not move liquid unless
Franklin Electric has determined that several pumps must be limited to
the pump is primed. A pump is said to be “primed” when
higher minimum flows to provide optimum service. The following are
the casing and the suction piping are completely filled with
the recommended minimum flows for these specific pumps:
liquid. Open discharge valve a slight amount. This will
allow any entrapped air to escape and will normally allow
the pump to prime, if the suction source is above the pump.
When a condition exists where the suction pressure may
drop below the pump’s capability, it is advisable to add a
low pressure control device to shut the pump down when the
pressure drops below a predtermined minimum.

15
3. All cooling, heating, and flush lines must be started and 3. A sufficient amount of discharge pressure is not being
regulated. delivered.

4. Start the driver (typically, the electric motor). 4. Loss of liquid after starting of the pump.

5. Excessive vibration from the pump or driver.

6. Driver is running hot or overheating.

7. Pump bearings are running hot or overheating.

5. Slowly open the discharge valve until the desired flow RUNNING THE PUMP
is reached, keeping in mind the minimum flow restrictions
listed above. While the pump is running, periodic checks should be made to the
following:
It is important that the discharge valve be opened within a short inter-
val after starting the driver. Failure to do this could cause a dangerous 1. Stuffing box leakage (when supplied). Ensure that there
build up of heat and possibly an explosion. is sufficient leakage to lubricate the packing.

6. Reduced capacity 2. Bearings. Check the pump and driver bearings for high
Avoid running a centrifugal pump at drastically reduced temperature. Pump bearings should not exceed the pumped
capacities or with discharge valve closed for extended fluid temperature or 250°F (121°C), whichever is lower.
periods of time. This can cause severe temperature rise and
the liquid in the pump may reach its boiling point. If this 3. Mechanical Seals. Check to make sure that there is no
occurs, the mechanical seal will be exposed to vapor, with no visible leakage out of any mechanical seal.
lubrication, and may score or seize to the stationary parts.
4. Gauges. Confirm that the suction and discharge gauges
Continued running under these conditions when the suction
are operational and that the data displayed meets the per-
valve is also closed, can create an explosive condition due
formance curve of the pumping assembly.
to the confined vapor at high pressure and temperature.
Thermostats may be used to safeguard against over heating
by shutting down the pump at a predetermined temperature. OPERATION IN SUB-FREEZING CONDITIONS
Safeguards should also be taken against possible operation When using the pump in sub-freezing conditions where the pump is
with a closed discharge valve, such as installing a bypass periodically idle, the pump should be properly drained or protected
back to the suction source. The size of the bypass line and with thermal devices which will keep the liquid in the pump from
the required bypass flow rate is a function of the input freezing. High chrome iron pumps are not recommended for applica-
horsepower and the allowable temperature rise. tions below 0°F (-18°C).

7. Reduced Head SHUTDOWN CONSIDERATIONS


Note that when discharge head drops, the pump’s flow rate
usually increases rapidly. Check motor for temperature rise When the pump is being shut down, the procedure should be the
as this may cause overload. If overloading occurs, throttle reverse of the start-up procedure. First, slowly close the discharge
the discharge. valve, shut down the driver, then close the suction valve. Remember,
closing the suction valve while the pump is running is a safety hazard
8. Surging Condition and could seriously damage the pump and other equipment.
A rapidly closing discharge valve can cause a damaging
pressure surge. A dampening arrangement should be pro-
vided in the piping.
STOPPING THE PUMP
Slowly close the discharge valve and shut down the driver per the
The pump should be shut down IMMEDIATELY and the issue identified manufacturer’s instructions.
if the pump is running at it’s rated speed and any of the following
issues are occurring: Shut off any external sealing flush lines to relieve any residual stuffing
box pressure.
1. No liquid delivered.
Re-check the alignment once the unit has been shut down to make
2. A sufficient amount of liquid is not being delivered. sure the equipment is rigidly mounted to the base assembly.
16
TROUBLESHOOTING
The following is a guide to troubleshooting problems with Franklin
Electric. Common problems are analyzed and solutions are offered.
Obviously, it is impossible to cover every possible scenario. If a prob-
lem exists that is not covered by one of the examples, then contact
Technical support or your representative for assistance.

17
POSSIBLE EFFECT

Pump operating for a short time, then stops

Pump is pulling high horsepower


Not enough discharge pressure
Not enough liquid delivered

Cavitation noise from pump

Pump bearings running hot


Loss of liquid after starting

Excessive vibration
No liquid delivered

Driver running hot


PROBLEM
Pump not primed/lack of prime/incomplete priming
Loss of prime
Suction lift too high
Discharge head too high
Rotational speed too low
Incorrect direction of rotation
Impeller plugged/impeller partially blocked by debris
Air leak in suction line
Air leak in discharge line
Insufficient Net Positive Suction Pressure Available (NPSHA)
Damaged impeller
Defective packing
Foot valve too small or partially blocked
Inlet pipe not submerged enough
Impeller diameter too small
Obstruction in water passageways
Entrained air or gas in liquid
Discharge head lower than previously thought
Specific gravity of liquid higher than previously thought
Viscosity of liquid higher than previously thought
Bent or damaged shaft

18
Bearings worn

Defect in driver

Rotor assembly binding


Rotational speed too high
Foundation not rigid enough
Misalignment of pump and driver
PROBLEM

Lubrication grease and/or oil dirty & contaminated


Voltage and/or frequency lower than previously thought

19
No liquid delivered

Not enough liquid delivered

Not enough discharge pressure

Loss of liquid after starting

Pump operating for a short time, then stops

Pump is pulling high horsepower


POSSIBLE EFFECT

Driver running hot

Excessive vibration

Cavitation noise from pump

Pump bearings running hot


PROBLEM POSSIBLE CAUSE RECOMMENDED REMEDY
Problem #1 1.1 Recalculate NPSH available. It must be
Pump not reaching design flow rate. Insufficient NPSHA. (Noise may not be pres- greater than the NPSH required by pump at
ent) desired flow. If not, redesign suction piping,
holding number of elbows and number of
planes to a minimum to avoid adverse flow
rotation as it approaches the impeller.
1.2 Reduce system head by increasing pipe size
System head greater than anticipated. and/ than or reducing number of fittings.
Increase impeller diameter.
NOTE: Increasing impeller diameter may
require use of a larger motor.
1.3 Air leak from atmosphere on suction side.
Entrained air. 1. Check suction line gaskets and threads for
tightness.
2. If vortex formation is observed in suction
tank, install vortex breaker.
3. Check for minimum submergence.
1.4 Process generated gases may require larger
Entrained gas from process. pumps.
1.5 Check motor speed against design speed.
Speed too low.
1.6 After confirming wrong rotation, reverse
Direction of rotation wrong. any two of three leads on a three-phase mo-
tor. The pump should be disassembled and
inspected before it is restarted.
1.7 Replace with proper diameter impeller.
Impeller too small. NOTE: Increasing impeller diameter may
require use of a larger motor.
1.8 Replace impeller and/or case wear rings.
Impeller clearance too large.
1.9 1. Reduce length of fiber when possible.
Plugged impeller, suction line or casing 2. Reduce solids in the process fluid when
which may be due to a product or large possible.
solids. 3. Consider larger pump.
1.10 Replace part or parts.
Wet end parts (casing cover, impeller) worn,
corroded or missing.
Problem #2.0 2.1 Refer to remedies listed under Problem #1.0
Pump not reaching design head (TDH). Refer to possible causes under Problem and #3.0.
#1.0.
Problem #3.0 3.1 Repeat priming operation, recheck instruc-
No discharge or flow Not properly primed. tions. If pump has run dry, disassemble and
inspect the pump before operation.

20
PROBLEM POSSIBLE CAUSE RECOMMENDED REMEDY
Cont. Problem #3.0 3.2 After confirming wrong rotation, reverse
No discharge or flow Direction of rotation wrong. any two of three leads on a three-phase mo-
tor. The pump should be disassembled and
inspected before operation.
3.3 Air leak from atmosphere on suction side.
Entrained air. Refer to recommended remedy under Prob-
lem #1.0, Item #1.3.
3.4 Refer to recommended remedy under Prob-
Plugged impeller, suction line or casing lem #1.0, Item #1.9.
which may be due to a fibrous product or
large solids.
3.5 Replace damaged parts.
Damaged pump shaft, impeller.
Problem #4.0 4.1 Refer to recommended remedy under Prob-
Pump operates for short period, then loses Insufficient NPSHA. lem #1.0, Item #1.1.
prime. 4.2 Air leak from atmosphere on suction side.
Entrained air. Refer to recommended remedy under Prob-
lem #1.0, Item #1.1.
Problem #5.0 5.1 Refer to recommended remedy under Prob-
Excessive noise from wet end. Cavitation - insufficient NPSH available. lem #1.0, Item #1.1.
5.2 Redesign suction piping, holder number of
Abnormal fluid rotation due to complex elbows and number of planes to a minimum
suction piping. to avoid adverse fluid rotation as it ap-
proaches the impeller.
5.3 1. Replace impeller and/or case wear rings.
Impeller rubbing. 2. Check outboard bearing assembly for
axial end play.
Problem #6.0 6.1 1. Work with clean tools in clean surround-
Excessive noise from bearings. Bearing contamination appearing on the ings.
raceways as scoring, pitting, scratching or 2. Remove all outside dirt from housing
rusting caused by adverse environment and before exposing bearings.
entrance of abrasive contaminants from 3. Handle with clean dry hands.
atmosphere. 4. Treat a used bearing as carefully as a new
one.
5. Use clean solvent and flushing oil.
6. Protect disassembled bearing from dirt
and moisture.
7. Keep bearings wrapped in paper or clean
cloth while not in use.
8. Clean inside of housing before replacing
bearings.
9. Check oil seals and replace as required.
10. Check all plugs and tapped openings to
make sure that they are tight.

21
PROBLEM POSSIBLE CAUSE RECOMMENDED REMEDY
Cont. Problem #6.0 6.2 When mounting the bearing on the out-
Excessive noise from bearings. Brinelling of bearing identified by indenta- board end use a proper size ring and apply
tion on the ball races, usually caused by the pressure against the inner ring only. Be
incorrectly applied forces in assembling the sure when mounting a bearing to apply the
bearing or by shock loading such as hitting mounting pressure slowly and evenly.
the bearing or drive shaft with a hammer.
6.3 1. Correct the source of vibration.
False brinelling of bearing identified again 2. Where bearings are oil lubricated and
by either axial or circumferential indenta- employed in units that may be out of service
tions usually caused by vibration of the balls for extended periods, the drive shaft should
between the races in a stationary bearing. be turned over periodically to re-lubricate
all bearing surfaces at intervals of one-to
three months.
6.4 1. Follow correct mounting procedures for
Thrust overload on bearing identified by bearings.
flaking ball path on one side of the outer
race or in the case of maximum capacity
bearings, may appear as a spalling of the
races in the vicinity of the loading slot.
(Please note: maximum capacity bearings
are not recommended in SP pumps.) These
thrust failures are caused by improper
mounting of the bearing or excessive thrust
loads.
6.5 Handle parts carefully and follow recom-
Misalignment identified by fracture of ball mended mounting procedures. Check all
retainer or a wide ball path on the inner parts for proper fit and alignment.
race and a narrower cocked ball path on the
outer race. Misalignment is caused by poor
mounting practices or defective drive shaft.
For example bearing not square with the
center-line or possibly a bent shaft due to
improper handling.
6.6 1. Where current shunting through the bear-
Bearing damaged by electric arcing identi- ing cannot be corrected, a shunt in the form
fied as electro-etching of both inner and of a slip ring assembly should be incorpo-
outer ring as a pitting or cratering. Electri- rated.
cal arcing is caused by a static electrical 2. Check all wiring, insulation and rotor
charge emanating from belt drives, electri- windings to be sure that they are sound and
cal leakage or short circuiting. all connections are properly made.
3. Where pumps are belt driven, consider
the elimination of static charges by proper
grounding or consider belt material that is
less generative.

22
PROBLEM POSSIBLE CAUSE RECOMMENDED REMEDY
Cont. Problem #6.0 6.7 1. Be sure the lubricant is clean.
Excessive noise from bearings. Bearing damage due to improper lubri- 2. Be sure proper amount of lubricant is
cation, identified by one or more of the used. The constant level oiler supplied with
following: SP pumps will maintain the proper oil level
1. Abnormal bearing temperature rise. if it is installed and operating properly. In
2. A stiff cracked grease appearance. the case of greased lubricated bearings,
3. A brown or bluish discoloration of the be sure that there is space adjacent to the
bearing races. bearing into which it can rid itself of exces-
sive lubricant, otherwise the bearing may
overheat and fail prematurely.
3. Be sure the proper grade of lubricant is
used.

MAINTENANCE area should be clean and free from dust, dirt, oil, grease, etc. Gloves
should be clean. Only clean towels, rags and tools should be used.
PREVENTIVE MAINTENANCE
MAINTENANCE OF PUMP DUE TO FLOOD
The following sections of this manual give instructions on how to per-
form a complete maintenance overhaul. However, it is also important DAMAGE
to periodically repeat the “PRE START-UP CHECKS” listed on page 15.
The servicing of centrifugal pumps after a flooded condition is a com-
These checks will help extend pump life as well as the length of time
paratively simple matter under normal conditions.
between major overhauls.
Bearings are a primary concern on pumping units. First, dismantle
Routine maintenance is the only way to ensure minimizing downtime.
the bearings, clean and inspect them for any rusted or badly worn
Routine maintenance is a sound insurance policy against minimizing
surfaces. If bearings are free from rust and wear, re-assemble and
downtime.
re-lubricate them with one of the recommended pump lubricants. De-
pending on the length of time the pump has remained in the flooded
NEED FOR MAINTENANCE RECORDS area, it is unlikely that bearing replacement is necessary, however, in
the event that rust or worn surfaces appear, it may be necessary to
A procedure for keeping accurate maintenance records is a critical part replace the bearings.
of any program to improve pump reliability. There are many variables
that can contribute to pump failures. Often long term and repetitive Next, inspect the stuffing box and clean out any foreign matter that
problems can only be solved by analyzing these variables through might clog the box. Mechanical seals should be cleaned and thor-
pump maintenance records. oughly flushed.
Depending on the operation and environmental conditions together Couplings should be dismantled and thoroughly cleaned.
with a comparison of previous inspections, the frequency of inspec-
tions may be altered to maintain minimal downtime. Any pump that is properly sealed at all joints and connected to both
the suction and discharge should exclude outside liquid.
NEED FOR CLEANLINESS
Therefore, it should not be necessary to go beyond the bearings, stuff-
One of the major causes of pump failure is the presence of contami- ing box and coupling when servicing the pump.
nants in the bearing housing. This contamination can be in the form
of moisture, dust, dirt and other solid particles such as metal chips.
Contamination can also be harmful to the mechanical seal (especially
the seal faces) as well as other parts of the pumps. For example, dirt
in the shaft threads could cause the impeller to not be seated properly
against the shaft sleeve. This, in turn, could cause a series of other
problems. For these reasons, it is very important that proper cleanli-
ness be maintained. Some guidelines are listed below.

If it is contaminated, determine the cause and correct. The work

23
ROUTINE MAINTENANCE CHART 7. Drain the pump by removing the vent plug at the top of
the casing (#179A).
Visually check for leaks
Check for lubrication 8. Remove the fasteners holding the upper casing (#179A)
Adjust glands as necessary to to the lower casing (#179B). Remove any external piping
Every Week
maintain proper leakage if supplied. Remove the two (2) casing dowel pins (#591C)
Hand test bearing housing for from the casing assembly.
any sign of temperature rise
Check bearing temperature 9. Insert a screwdriver or pry bar into the slots between the
Every Month upper (#179A) and lower (#179B) casing halves and separate
with a thermometer
the halves, lifting off the upper (#179A) casing half. Discard
Check the packing and replace
the casing gasket (#364G).
if necessary
Check alignment of the pump
Every 6 Months and motor
Check holding down bolts for
tightness
Check coupling for wear
Check rotating element for The upper casing (#179A) is heavy. It is important to follow plant
wear safety guidelines when lifting it.
Check wear ring clearances
Every Year
Check and re-grease bearings 10. Lightly tap the stuffing boxes (#812) with a soft headed
Measure total dynamic suction hammer to break the seal between the stuffing box (#812)
and discharge head and the lower casing (#179B). Lift the rotating assembly out
of the lower casing half (#179A). Discard the stuffing box
FIGURE 9 - Routine Maintenance Chart o-rings (#364A).

DISASSEMBLY 11. Remove the four cap screws (#708NA) from each bearing
housing cap (#164N & #164P).
Refer to the parts list shown in FIGURES 23 & 24 for item number
references used throughout this section. 12. Remove the locknut (#708N) and lock washer (#544N)
from the outboard end of the shaft (#728). Using a puller,
1. Before performing any maintenance, disconnect the driver pull the outboard bearing (#069N) from the shaft (#728)
from its power supply and lock it off line. and discard.

13. Using a puller, pull the inboard bearing (#069P) from


the shaft (#728) and discard.

Lock out power to driver to prevent personal injury.

2. Close the discharge & suction valves and drain all liquid
from the pump. Damaged can be caused by exerting force against the outer ring of a
ball bearing.
3. Close all valves on auxiliary equipment and piping, then
disconnect all auxiliary piping. NOTE: Locknut and lock washer are not used on inboard end
of shaft.
4. Decontaminate the pump as necessary. If FPS Pumps
contain dangerous chemicals, it is important to follow plant 14. Remove outboard lip seal (#364L) and discard. Remove
safety guidelines to avoid personal injury or death. inboard lip seal (#364L) and discard.
5. Remove the coupling guard. 15. Remove the outboard and inboard bearing adapters
(#008).
6. Remove the spacer coupling and drive key.

24
27. Unscrew shaft sleeve (#756) from the outboard end and
DISASSEMBLY OF PACKED PUMPS slide off of shaft (#728).
16. Remove four cap screws that hold the outboard bearing
arm (#028) and inboard bearing arm (#028) to the stuffing Left-Hand Rotation
box (#812). Loosen and remove gland nuts (#544G) from
the outboard and inboard locations. Remove bearing arms 28. Unscrew shaft sleeve (#756) from the inboard end
(#028) and gland assemblies (#372) from outboard and and slide off of shaft (#728). Discard shaft sleeve o-ring
inboard locations. (#364B).

17. Slide outboard and inboard stuffing boxes (#812) off of 29. Remove the impeller (#444), slide back the impeller key
shaft assembly. (#472A) and remove the other shaft sleeve (#756). Dis-
card shaft sleeve o-ring (#364B). Remove the impeller key
18. Remove and discard all rings of packing (#372P), since (#472A) from shaft (#728).
replacement with new packing is recommended when-
ever pump is disassembled. Be sure to remove all pack- RE-ASSEMBLY
ing (#372P) from the stuffing boxes (#812). Remember
there are rings of packing behind the lantern ring (#676L).
Inspect the lantern ring (#676L) for damage and replace if
BEARING INSTALLATION
necessary. Mounting of bearings on shafts must be done in a clean environment.
Bearing life can be drastically reduced if even very small foreign par-
19. Remove both casing wear rings (#676A) from impeller ticles work their way into the bearings.
(#444).
Bearings should be removed from their protective packaging only
Right-Hand Rotation immediately before assembly to limit exposure to possible contamina-
tion. After removing the packaging they should only come in contact
20. Unscrew shaft sleeve (#756) from the outboard end with clean hands, fixtures, tools and work surfaces.
and slide off of shaft (#728). Discard shaft sleeve o-ring
(#364B). The chart shown in FIGURE 10 gives the SKF part numbers for bearings
in Franklin Electric SP pumps. Note that the term “Inboard bearing”
Left-Hand Rotation refers to the bearing nearest to the motor. “Outboard bearing” refers
to the bearing farthest from the motor.
21. Unscrew shaft sleeve (#756) from the inboard end
and slide off of shaft (#728). Discard shaft sleeve o-ring This manual and it’s instructions are not intended to supersede any
(#364B). information issued by any bearing manufacturer. When handling care
and maintenance of the bearings must be taken seriously. Be sure that
22. Remove the impeller (#444), slide back the impeller key
the bearings you use:
(#472A) and remove the other shaft sleeve (#756). Dis-
card shaft sleeve o-ring (#364B). Remove the impeller key 1. You correctly lubricate the bearings at intervals as laid out
(#473) from shaft (#728). in the routine maintenance chart contained in this manual.

DISASSEMBLY OF MECHANICALLY SEALED PUMPS 2. You remove, clean and refit them into the pump with care.
When you remove a bearing from the pump during mainte-
23. Slide outboard and inboard seal chambers (#812) off of nance or service, replace the bearing with a new one.
shaft assembly.
3. The tools you use when handling the bearings should
24. Drive the mechanical seal stationary (#372M) out of seal be clean and contaminate free. This will minimize cross
chamber (#812). contamination.

25. Slide the rotating elements of the mechanical seal In the SP split case product line, bearings can be inspected and/or
(#372M) off of the shaft (#728). replaced without removing the casing top. This greatly reduces main-
tenance time. Ball bearings should never be disassembled.
26. Remove both casing wear rings (#676A) from impeller
(#444). Clean bearings thoroughly prior to installing them into the pump.
Check that the bearing, bearing housing and shaft are free of damage
Right-Hand Rotation PRIOR to installing bearings.

25
Inboard Location Outboard Location
Module Type of Bearings Single Row, Single
Deep Groove Deep Groove
Oil bath/mist – Open 6306-C3 6306-C3
Regreasable – Single Shielded 6306-ZC3 6306-ZC3
1, 2, 3
Greased for life – Double Shielded 6306-2ZC3 6306-2ZC3
Sealed for life – Double Sealed 6306-2RSIC3 6306-2RSIC3

Oil bath/mist – Open 6309-C3 6309-C3


Regreasable – Single Shielded 6309-ZC3 6309-ZC3
4, 5, 6
Greased for life – Double Shielded 6309-2ZC3 6309-2ZC3
Sealed for life – Double Sealed 6309-2RSIC3 6309-2RSIC3
Oil bath/mist – Open 6312-C3 6312-C3
Regreasable – Single Shielded 6312-ZC3 6312-ZC3
7
Greased for life – Double Shielded 6312-2ZC3 6312-2ZC3
Sealed for life – Double Sealed 6312-2RSIC3 6312-2RSIC3

FIGURE 10 – Franklin Electric Pumps SP Bearings

These bearings are open on both sides. They are lubricated by oil bath or oil mist.
These bearings are pre-greased by Franklin Electric. Replacement bearings will generally not be pre-greased, so grease must be applied by the user. They have a single shield,
which is located on the side next to the grease buffer, or reservoir. The bearings draw grease from the reservoir as it is needed. The shield protects the bearing from getting too much
grease, which would generate heat. The grease reservoir is initially filled with grease by Franklin Electric. Lubrication fittings are provided, to allow the customer to periodically
replenish the grease, as recommended by the bearing and/or grease manufacturer.
These bearings are shielded on both sides. They come pre-greased by the bearing manufacturer. The user does not need to re-grease these bearings. The shields do not actually
contact the bearing race, so no heat is generated.
These bearings are sealed on both sides. They come pre-greased by the bearing manufacturer. The user does not need to re-grease these bearings. The seals physically contact
and rub against the bearing race, which generates heat. These bearings are not recommended at speeds above 1750 RPM.
The codes shown are SKF codes. Inboard and outboard bearings have the C3, greater than “Normal” clearance. These clearances are recommended by SKF to maximize bearing life.
Re-greasable – Single Shielded bearings are not available in the duplex configuration; however, open oil bath-type bearings can be used for the re-greasable configuration. These
bearings must be pre-greased during assembly. Lubrication fittings are provided, to allow the user to periodically replenish the grease, as recommended by the bearing and/or grease
manufacturer.
Not available.

26
milled-down end under the shaft sleeve (#756).
RE-ASSEMBLY OF PUMPS
4. Check impeller (#444) for correct rotation (See FIGURE
RIGHT-HAND ROTATION 12) and slide onto shaft (#728) from outboard end.

5. Screw the second shaft sleeve (#756) onto the shaft


A
(#728) locking it tight up against the impeller (#444) and
the first shaft sleeve (#756).
Mechanical Seal Packed
Pump Model
A – Inches RO TATION
2.5x3-10 SP 7.813 11.125
3x4-10 SP 7.813 11.125
4x6-10 SP 10.000 14.000
5x6-10 SP 9.938 13.250
6x8-10 SP 9.938 13.250
10x10-10 SP 12.500 16.313
5x6-11 SP 7.813 11.125
3x4-12 SP 7.813 11.125

SUCTIO N
4x5-12 SP 7.813 11.125 DISCHARGE
5x6-12 SP 9.938 13.250
6x8-12 SP 10.063 14.000
8x10-12 SP 12.500 16.313
10x10-12 SP 12.500 16.313
RIGH T-HAND RO TATION VIEWED
2x3-15 SP 7.813 11.125 FROM THE MOTOR EN D
3x4-15 SP 7.813 11.125
4x5-15 SP 10.063 14.000
5x6-15 SP 10.063 14.000 RO TATION
6x8-15 SP 10.063 14.000
8x10-15 SP 13.000 16.500
10x12-15 SP 13.000 16.500
4x5-18 SP 10.000 14.000
5x6-18 SP 13.000 16.500
6x8-18 SP 13.000 16.500
8x10-18 SP 13.000 16.500
SUCTIO N

10x12-18 SP 15.688 16.500


DISCHARGE

FIGURE 11 - Right-Hand Shaft Sleeve Dimensions

1. Place new shaft sleeve o-rings (#364B) onto shaft sleeves


(#756).

2. Wipe over shaft (#728) with clean light oil. Screw shaft
LEF T-HAND RO TATION VIEWED
sleeve (#756) onto shaft (#728) at the inboard location until
the non threaded end of the shaft sleeve (#756) is properly FROM THE MOTOR EN D
lined up with the step on the shaft (#728). See FIGURE 11. FIGURE 12 - Proper Impeller Rotation
3. Place impeller key (#472A) into shaft keyway and tap

27
6. Slide both case wear rings (#676A) onto the impeller 16. Slide the heated bearing (#069N) onto the shaft (#728)
(#444). until it abuts the bearing adapter (#008). Place the lock
washer (#708N) onto the shaft (#728) and lock the bearing
7. Lubricate and roll the seal chamber o-ring (#364A) into locknut (#544N) tight against the bearing (#069N).
the groove of the seal chamber (#812).
17. Cool the bearing to room temperature and coat both
8. Pre-lubricate the rotary part of the mechanical seal sides with two to three ounces of recommended grease.
(#372M) and slide the mechanical seals onto the shaft
(#728) from both the outboard and inboard locations. 18. Coat the inside of the bearing housing (#164N) with
grease and slide into place over the bearing (#069N). Slight
9. Press the stationary seal face (#372M) into the seal tapping of the bearing housing may be necessary as there
chamber (#812). are fairly tight tolerances between the bearing (#069N) and
the bearing housing (#164N). Secure the bearing housing
(#164N) to the bearing arm (#028) with the four hex head
IF USING MECHANICAL SEALS
cap screws (#708NA).
10. Slide the seal chamber (#812) up onto the shaft as-
sembly (#728), taking care not to damage the shaft sleeves 19. Heat the inboard ball bearing (#069P) to approximately
(#756) or the stationary seal face keeping the vortex sup- 212°F (100°C) using a bearing hot plate or lubricating oil
pressor at the top, 12 o’clock position. bath.

IF USING PACKING
11. Lubricate and roll the stuffing box o-ring (#364B) into
the groove of the stuffing box (#812).

12. Slide the stuffing boxes (#812) up onto the shaft as-
sembly (#728), taking care not to damage the shaft sleeves
(#756) keeping the vortex suppressor at the top, 12 o’clock Do not exceed 248°F (120°C). Temperatures in excess of this will
position. Install packing per INSTALLING STUFFING BOX permanently damage ball bearing.
PACKING on Page 26.
20. Cool the bearing (#069P) to room temperature and coat
13. Slide the gland assemblies (#372) and the bearing arms both sides with two to three ounces of recommended grease.
(#028) onto the shaft (#728) simultaneously and secure
bearing arm (#028) to stuffing boxes (#812) with four cap 21. Coat the inside of the bearing housing (#164P) with
screws. Secure and tighten the glands (#372) with the gland grease and slide into place over the bearing (#069P). Slight
nuts (#544G) as described in Section INSTALLING STUFFING tapping of the bearing housing may be necessary as there
BOX PACKING on Page 26. are fairly tight tolerances between the bearing (#069P) and
the bearing housing (#164P). Secure the bearing housing
14. Slide the bearing adapters (#008) onto the shaft (#728). (#164P) to the bearing arm (#028) with the four hex head
Press the oil lip seals (#364L) into the seal chambers (#812). cap screws (744NA).

15. Heat the outboard ball bearing (#069N) to approxi- 22. Place the casing gaskets (#364G) on the pump casing
mately 212°F (100°C) using a bearing hot plate or lubricating half (#179B). Pull the gaskets tight against the casing studs
oil bath. (#808A). Trim the four areas of the gasket (#364G) where
the stuffing box o-ring (#364A) meets the gasket (#364G)
flush with the casing (#179B). See FIGURE 13. Remove the
gaskets (#364G).

Do not exceed 248°F (120°C). Temperatures in excess of this will


permanently damage ball bearing.

28
Pull Gasket Tight Against Studs 2. Work outward along the shaft axis toward the stuffing
boxes in opposite quarters tightening nuts in regions 5, 6, 7
& 8.

3. Work outwards along the branch and in opposite quarters


tightening nuts in regions 9, 10, 11 & 12.

4. Repeat the entire sequence.

Trim Trim BOLT SIZE TIGHTENING TORQUE


Gasket Gasket
Metric Standard Lbf-ft Nm
4 mm 5/32” 2.7 3.6
5 mm 3/16” 5.2 7.0
6 mm 1/4” 8.9 12.0
7 mm 9/32” 14.6 19.8
Pull Gasket Tight Against Studs 8 mm 5/16” 21.8 29.6
FIGURE 13 – Casing Gasket Orientation 9 mm 11/32” 28.0 38.0
10 mm 3/8” 38.7 52.5
23. Set the rotating assembly into the bottom half of the
casing (#179B). Align the pins (#591A) for the case wear 12 mm 1/2” 65.6 89.0
rings (#676A) and the pins (#591B) for the stuffing boxes 14 mm 9/16” 99.6 135
(#812) so the rotor assembly drops down into the lower half 16 mm 5/8” 151 205
of the casing (#179B). Ensure that the stuffing box o-rings
(#364A) are not pinched or buckled. Check to make sure the 18 mm 11/16” 190 257
impeller (#444) is located in a central position within the 20 mm 3/4” 264 358
casing (#179B) and between the case wear rings (#676A). 22 mm 7/8” 321 435
The rotor assembly should rotate freely at this point. If
this is not the case, the binding point must be located and 24 mm 15/16” 411 557
eliminated. Disassembly of the rotor assembly may need to
occur. If the impeller (#444) is not located properly within FIGURE 14 – Casing Nut Torque Values
the casing (#179B), the shaft sleeves (#756) may need to be
shifted to reorient the impeller (#444) (left or right).

24. Install the gaskets (#364G) with a light spot of RTV fast
curing silicone at the inner edge where the casing gasket
(#364G) meets the stuffing box o-ring (#364A). This will
assure a good seal. It is imperative that the case gasket
(#364G) is cut flush with the bore in the casing (#179B). If 8 6
the case gasket (#364G) is not cut and installed in contact
with the stuffing box o-ring (#364A) water could leak 3 2
around this o-ring (#364A). 12 10
25. Lower the upper half of the casing (#179B) into place
and install the casing nuts (#544A).
9 11
26. Insert the casing joint dowels (#591C). Tighten the cas-
ing nuts (#544A) to the proper torque rating per FIGURE 14 1 4
and in the sequence illustrated in FIGURE 15. 5 7

Tightening Sequence

1. Tighten the four “corner” nuts marked 1, 2, 3 & 4.


FIGURE 15 – Casing Nut Tightening Sequence

29
27. Install external flush piping, if supplied. Rotate the shaft Stuffing Box Information
by hand to assure smooth turning and that it is free from Pump Model
rubbing or binding. Bore Depth Packing
2.5x3-10 SP 2.559 2.362 8 - 3/8” SQ
INSTALLING STUFFING BOX PACKING 3x4-10 SP 2.559 2.362 8 - 3/8” SQ
4x6-10 SP 3.347 2.756 8 - 1/2” SQ
Refer to FIGURE 16 for number of packing rings required by pump
model. 5x6-10 SP 2.559 2.362 8 - 3/8” SQ
6x8-10 SP 2.559 2.362 8 - 3/8” SQ
If packing is to be cut from a coil or long length:
10x10-10 SP 3.347 2.795 8 - 1/2” SQ
1. Wrap the packing around a dummy shaft, equal to the 5x6-11 SP 2.559 2.362 8 - 3/8” SQ
shaft sleeve diameter. 3x4-12 SP 2.559 2.362 8 - 3/8” SQ
2. To assist in cutting rings, two guides lines parallel to the 4x5-12 SP 2.559 2.362 8 - 3/8” SQ
shaft axis and separated by a distance equal to the packing 5x6-12 SP 2.559 2.362 8 - 3/8” SQ
section may be drawn on the spiral.
6x8-12 SP 3.347 2.795 8 - 1/2” SQ
3. Cut the rings from the spiral at an angle of 45° diagonally 8x10-12 SP 3.347 2.795 8 - 1/2” SQ
across the guide lines. No gap is left between the ends. 10x10-12 SP 3.347 2.795 8 - 1/2” SQ
Insert the first ring and tap it to the bottom of the stuffing box. Each 2x3-15 SP 2.559 2.362 8 - 3/8” SQ
following ring should be installed in the same manner and positioned 3x4-15 SP 2.559 2.362 8 - 3/8” SQ
in the stuffing box so that the split is advanced 90°. 4x5-15 SP 3.347 2.756 8 - 1/2” SQ
Install the lantern ring in its proper position to align with the internal 5x6-15 SP 3.347 2.795 8 - 1/2” SQ
flush connection allowing for movement of the ring deeper into the 6x8-15 SP 3.347 2.795 8 - 1/2” SQ
box as the packing is compressed.
8x10-15 SP 3.937 2.913 8 - 1/2” SQ
When the correct number of rings have been inserted, the last packing 10x12-15 SP 3.937 2.913 8 - 1/2” SQ
ring should not protrude past the stuffing box face, so that the gland 4x5-18 SP 3.347 2.795 8 - 1/2” SQ
may be properly started in the stuffing box bore.
5x6-18 SP 3.937 2.913 8 - 1/2” SQ
Bring the gland follower up squarely against the last packing ring and 6x8-18 SP 3.937 2.913 8 - 1/2” SQ
tighten the nuts evenly to finger pressure. Turn the shaft to ensure it 8x10-18 SP 3.937 2.913 8 - 1/2” SQ
does not bind on the bore of the gland assembly.
10x12-18 SP 3.937 2.913 8 - 1/2” SQ
Pressurize the stuffing box, ensuring air is not trapped. A packed
gland must leak and leakage should take place commencing soon after FIGURE 16 – Stuffing Box Information
the stuffing box is pressurized.

Until steady leakage takes place, the pump may overheat. If this
happens, the pump must be stopped and allowed to cool and, when
re-started, leakage should take place. If it does not, this operation
should be repeated. Gland nuts (#544G) should not be slackened.

After the pump has been running for ten (10) minutes with steady Excessive gland pressure will cause damage by cutting off lubrication
leakage, tighten the gland nuts (#544G) by one sixth of a full turn. to the packing and packing will burn and damage the shaft sleeve.
Continue to adjust at ten (10) minutes intervals, each time evenly by
one sixth of a full turn, until the leaking is reduced to an acceptable
level.

30
LEFT-HAND ROTATION

Reversing rotation of pumps from right-hand to left-hand puts the


Z
suction and discharge of the pump on opposite sides with respect to
the inboard end. The reversing of rotation DOES NOT change how and
Mechanical Seal Packed in what direction the impeller rotates with respect to the volute of the
Pump Model
A – Inches casing.
2.5x3-10 SP 8.000 11.312
To change rotation, the changes in the assembly procedure are as
3x4-10 SP 8.000 11.312 follows:
4x6-10 SP 10.188 14.188
1. Place new shaft sleeve o-rings (#364B) onto shaft sleeves
5x6-10 SP 10.125 13.438
(#756).
6x8-10 SP 10.125 13.438
10x10-10 SP 12.625 16.500 2. Wipe over shaft (#728) with clean light oil. Screw shaft
sleeve (#756) onto shaft (#728) at the outboard location
5x6-11 SP 8.000 11.312 until the non threaded end of the shaft sleeve (#756) is
3x4-12 SP 8.000 11.312 properly lined up with the step on the shaft (#728). See
4x5-12 SP 8.000 11.312 FIGURE 16.
5x6-12 SP 10.125 13.438 3. Place impeller key (#472A) into shaft keyway and tap
6x8-12 SP 10.188 14.188 milled-down end under the shaft sleeve (#756).
8x10-12 SP 12.625 16.500
4. Check impeller (#444) for correct rotation (See FIGURE 11
10x10-12 SP 12.625 16.500 or 15) and slide onto shaft (#728) from inboard end.
2x3-15 SP 8.000 11.312
5. Screw the second shaft sleeve (#756) onto the shaft
3x4-15 SP 8.000 11.312
(#728) locking it tight up against the impeller (#444) and
4x5-15 SP 10.188 14.188 the first shaft sleeve (#756).
5x6-15 SP 10.188 14.188
The rest of the assembly procedure remains unchanged from the
6x8-15 SP 10.188 14.188 Right-Hand procedure.
8x10-15 SP 13.188 16.688
10x12-15 SP 13.188 16.688
4x5-18 SP 10.188 14.188
5x6-18 SP 13.125 16.688
6x8-18 SP 12.938 16.688
8x10-18 SP 13.188 16.688
10x12-18 SP 15.688 16.688

FIGURE 17 – Left-Hand Shaft Sleeve Dimensions

31
APPENDIX A ADDITIONAL PARAMETER CHECKS
The parameters listed below are somewhat more difficult to measure and/
CRITICAL MEASUREMENTS AND TOLERANCES or may require specialized equipment. For this reason, they are not typi-
FOR MAXIMIZING MTBPM cally checked by our customers, although they are monitored by Franklin
Electric during the manufacturing and/or design process. These param-
eters are described at the end of this appendix.
PARAMETERS THAT SHOULD BE CHECKED BY USERS
Franklin Electric recommends that the user check the following measure-
ments and tolerances whenever pump maintenance is performed. Each of Suggested
Suggested
these measurements is described in more detail on the following pages. And/Or
By Major
Topic Provided
Suggested Suggested Seal
By FPS
By Major And/Or Vendors
Topic Seal Provided
Vendors By FPS Shaft - Maximum roughness at seal 16µin
in (mm) in (mm) chamber (0.40 µm)

Shaft Bearing Housing - Bore 0.001 in


Concentricity (0.025 mm)
Diameter tolerance, under bearings 0.0002 (0.005)
Complete Pump – Dynamic Shaft 0.002 in 0.002 in
Impeller Deflection* (0.05 mm) (0.05 mm)
Balance See Note 1
Bearing Housing FIGURE 19 – Specialized Measurements
Diameter (ID) tolerance at bearings 0.0005 (0.013)
*The ASME standard recommends 0.005 in (0.13 mm) max deflection at
Power End Assembly
the impeller, while Franklin Electric provides 0.002 in (0.05 mm) max de-
Shaft Runout 0.001 (0.03) 0.001 (0.03)
flection at the mechanical seal. The two recommendations are essentially
Shaft Sleeve Runout 0.002 (0.05) 0.002 (0.05) equivalent.
Radial Deflection - Static 0.003 (0.076) 0.002 (0.05)
Shaft Endplay 0.002 (0.05) 0.002 (0.05) IMPELLER BALANCING
Seal Chamber Shaft whip is deflection where the centerline of the impeller is moving
Face Squareness to Shaft 0.001 (0.03) 0.003 (0.08)
around the true axis of the pump. It is not caused by hydraulic force but
rather by an imbalance with the rotating element. Shaft whip is very hard
Register Concentricity 0.005 (0.13) 0.005 (0.13)
on the mechanical seal because the faces must flex with each revolution in
Complete Pump order to maintain contact. To minimize shaft whip it is imperative that the
Shaft movement caused by pipe strain 0.002 (0.05) 0.002 (0.05) impeller is balanced. All impellers manufactured by Franklin Electric are
Alignment See Note 2 balanced after they are trimmed. If for any reason, a customer trims an
Vibration at bearing housing See Note 3
impeller, it must be re-balanced.

The maximum values of acceptable unbalance are:


FIGURE 18 - Measurements 1800 rpm: 0.021 oz•in/lb (1500 rpm: 40 g•mm/kg) of mass
3600 rpm: 0.011 oz•in/lb (2900 rpm: 20 g•mm/kg) of mass
N.S. = Not specified The OD of the bearings should also be checked and should conform to the
min/max values given above.
Note 1: The maximum values of acceptable unbalance are: 1800 rpm: 0.021 oz•in/lb (1500
rpm: 40 g•mm/kg) of mass; 3600 rpm: 0.011 oz•in/lb (2900 rpm: 20 g•mm/kg) of mass.
Franklin Electric performs a single plane spin balance on most impellers. All balancing, BEARING ASSEMBLY
whether single or two plane, is performed to the ISO 1940 Grade 6.3 tolerance criteria.
Note 2: Franklin Electric recommends that the pump and motor shafts be aligned to within
Shaft/Shaft Sleeve Runout
0.002 in (0.05 mm) parallel F.I.M. (Full Indicator Movement) and 0.0005 in/in (0.0005 mm/ Shaft runout is the amount the shaft is “out of true” when rotated in the
mm) angular F.I.M. Closer alignment will extend MTBPM. For a detailed discussion of this pump. It is measured by attaching a dial indicator to a stationary part of
subject see the Alignment section of this IOM. the pump so that its contact point indicates the radial movement of the
Note 3: Franklin Electric recommends the following peak velocities, in in/s (mm/second):
25A/25B & 35 = 0.1 (2.5), 45 & 55 = 0.15 (3.8), 60 & 70 = 0.25 (6.3).
shaft surface as the shaft is rotated slowly. If a shaft sleeve is used then
shaft sleeve runout must be checked. It is analogous to shaft runout.

32
Measurement of shaft runout/ shaft sleeve runout will disclose any out of Alignment
roundness of the shaft, any eccentricity between the shaft and the sleeve, Misalignment of the pump and motor shafts can cause the following
any permanent bend in the shaft, and/or any eccentricity in the way the problems:
shaft or bearings are mounted in the bearing housing. • Failure of the mechanical seal
• Failure of the motor and/or pump bearings
Shaft runout can shorten the life of the bearings and the mechanical seal. • Failure of the coupling
The following diagram shows how to measure shaft/shaft sleeve runout. • Excessive vibration/noise
Note that both ends need to be checked. The runout should be 0.001 in The schematics below show the technique for a typical rim and face align-
(0.025 mm) FIM or less. ment using a dial indicator. It is important that this alignment be done
after the flanges are loaded, and at typical operating temperatures. If
Radial Deflection – Static proper alignment cannot be maintained a C-flange motor adapter and/or
Radial movement of the shaft can be caused by a loose fit between the stilt/spring mounting should be considered.
shaft and the bearing and/or the bearing and the housing. This movement
is measured by attempting to displace the shaft vertically by applying Many companies today are using laser alignment which is a more so-
an upward force of approximately ten pounds to the impeller end of the phisticated and accurate technique. With this method a laser and sensor
shaft. While applying this force, the movement of an indicator is observed measure misalignment. This is fed to a computer with a graphic display
as shown in the following diagram. The movement should be checked at a which shows the required adjustment for each of the motor feet.
point as near as possible to the location of the seal faces. A movement of
more than 0.002 in (0.05 mm) is not acceptable. Vibration Analysis
Vibration Analysis is a type of condition monitoring where a pump’s
Shaft Endplay vibration “signature” is monitored on a regular, periodic basis. The
The maximum amount of axial shaft movement, or endplay, on a FPS primary goal of vibration analysis is extension on MTBPM. By using this
pump should be 0.001 in (0.03 mm) and is measured as shown below. tool Franklin Electric can often determine not only the existence of a
Observe indicator movement while tapping the shaft from each end in problem before it becomes serious, but also the root cause and possible
turn with a soft mallet. Shaft endplay can cause several problems. It can the solution. Modern vibration analysis equipment not only detects if a
cause fretting or wear at the point of contact between the shaft and the vibration problem exists, but can also suggest the cause of the problem.
secondary sealing element. It can also cause seal overloading or under- On a centrifugal pump, these causes can include the following: unbalance,
loading and possibly chipping of the seal faces. It can also cause the faces misalignment, defective bearings, resonance, hydraulic forces, cavitation,
to separate if significant axial vibration occurs. and recirculation. Once identified, the problem can be corrected, leading
to increased MTBPM for the pump.
SEAL CHAMBER
Face Squareness to Shaft Franklin Electric does not make vibration analysis equipment, however
Also referred to as “Seal Chamber Face Run-Out.” This runout occurs Franklin Electric strongly urges customers to work with an equipment sup-
when the seal chamber face is not perpendicular to the shaft axis. This plier or consultant to establish an on-going vibration analysis program.
will cause the gland to cock, which causes the stationary seat to be The HI standard for vibration at the bearing housing is 0.25 inches/second
cocked, which causes the seal to wobble. This runout should be less than (6.35 mm/sec) peak velocity or 0.0025 inches (0.064 mm) peak-to-peak
0.003 in (0.08 mm). displacement. Franklin Electric recommends the following peak velocities:

Register Concentricity 25A/25B & 35 0.1 in/s (2.5 mm/s)


An eccentric seal chamber bore or gland register can interfere with the 45 & 55 0.15 in/s (3.8 mm/s)
piloting and centering of the seal components and alter the hydraulic 60 & 70 0.25 in/s (6.4 mm/s)
loading of the seal faces, resulting in reduction of seal life and perfor-
mance. The seal chamber register concentricity should be less than 0.005 for best practice of a properly installed and operated pump.
in (0.13 mm).
SPECIAL PARAMETERS CHECKED
COMPLETE PUMP
Shaft Movement Caused by Pipe Strain SHAFT – MAXIMUM ROUGHNESS AT SEAL CHAMBER
Pipe strain is any force put on the pump casing by the piping. Pipe strain Franklin Electric shafts do not exceed 16 µin (0.4 µm) at these areas.
should be measured as shown below. Install the indicators as shown Franklin Electric audits smoothness by using a profilometer surface finish
before attaching the piping to the pump. The suction and discharge gauge.
flanges should now be bolted to the piping separately while continuously
observing the indicators. Indicator movement should not exceed 0.002 in
(0.05 mm).

33
BEARING HOUSING – BORE CONCENTRICITY
If the bore for holding the bearing is eccentric, the bearing will be shifted
off center. This will contribute to shaft runout. Franklin Electric measures
this concentricity by using computerized measuring equipment. The
concentricity should not exceed 0.001 in (0.03 mm).

COMPLETE PUMP – DYNAMIC SHAFT DEFLECTION


In regards to pump operation, a very important factor for maximizing
pump MTBPM is the avoidance of off-design pump operation. In order to
maximize the life of the seal and bearings, a process pump should be run
as close as possible to its Best Efficiency Point (BEP).

Dynamic shaft deflection is a deflection of the shaft caused by unbalanced


hydraulic forces acting on the impeller. Dynamic shaft deflection will
change as the pump is operated on various points along the curve. When
the pump is operated at BEP, the shaft deflection is zero. This deflection is
very difficult to measure.

At a given point on the curve, the shaft deflection is constant and is


constantly in the same direction. The centerline of the impeller, though
bent from parallel, does not move. For this reason, in many cases, shaft
deflection is not particularly hard on mechanical seals. It is, however,
hard on bearings, since the force which causes shaft deflection can be a
tremendous load on them. The amount of deflection depends on three
factors: how the shaft is supported, the strength of the shaft and the
amount of unbalanced hydraulic force experienced by the shaft/impel-
ler. If there seems to be a shaft deflection problem, refer to the Franklin
Electric Engineering Manual for a detailed discussion on how to calculate
deflection.

34
APPENDIX B distributors.

The “Inpro” VBXX bearing isolator is a one piece assembly.


BEARING HOUSING OIL SEALS (LABYRINTH TYPE) The rotor must not pull out of the stator. If the rotor can be
INPRO/SEAL® VBXX BEARING ISOLATORS removed, the complete seal assembly must be replaced.

3. If the bearing arm with bronze VBXX seals is washed or


INTRODUCTION
cleaned using a caustic type bath, the bronze material may
Franklin Electric provides pumps fitted with a variety of labyrinth oil discolor (turn black). If this happens, the complete seal
seals. While these instructions are written specifically for the Inpro/ assembly must be replaced. Note: This may occur if the
Seal VBXX labyrinth, they also apply to seals of other manufacturers. housing is left in a caustic bath over a long period of time
Specific installation instructions included with the seal, regardless of (more than 8 hours).
manufacturer, should be observed.
4. To remove the VBXX bearing isolator:
The Inpro “VBXX” Bearing Isolator is a labyrinth type seal which
isolates the bearings from the environment (uncontaminated), and re- A. Remove the pump shaft as described in the pump
tains the oil in the bearing housing. The bearing isolator consists of a disassembly instructions.
rotor and a stator. The rotor revolves with the shaft, driven by a close
fitted drive ring that rotates with the shaft. The stator is a stationary B. From the inside of the bearing arm (#028), place a
component that fits into the housing bore with a press fit (nominal bar (made from a soft material such as wood or plastic)
0.002 in (0.05 mm) interference) and with an “O” ring gasket seal. against the inside face of the seal. Push the seal out by
The two pieces are assembled as a single unit, and are axially locked tapping the bar with a soft mallet or an arbor press.
together by an “O” ring. There is no mechanical contact between the
rotor and stator when the isolator is running. 5. To install a new VBXX bearing isolator, in the outboard or
inboard bearing arm:
The VBXX is not intended to be separated from the bearing arm unless
being replaced. A. Position the outboard seal in the bore of the bearing
arm (#028) with the single expulsion port at the 6 o’clock
position, (carefully keep aligned with the bore).

B. The seal stator O.D. press fits into the bore. Use an
arbor press. Place a block or bar (large enough to
protect the rotor flange) between the arbor press ram
and seal face. Press the seal down into the bore stop
ping at the shoulder on the stator O.D.

The elastomer “O” ring acts as a gasket to ensure damming up of


small imperfections in the housing bore. The “O” ring is designed to
be compressed to the point of overfilling its groove. The overfilled
material is sheared off during assembly. Remove any sheared “O”
ring material which may extrude from the bore.

FIGURE 20 – Bearing Isolator

1. If the VBXX is removed from the housing, for any reason,


it must be replaced with a new VBXX to ensure a perfect seal
with the housing bore.

2. Repair or replacement of the seals is only necessary


when excessive oil leakage is evident. However, if for any
other reason, the bearing housing is to be disassembled or
the pump shaft removed, it is recommended that the rotor
“O” rings (which seal on the shaft) be replaced. Spare
or replacement “O” rings may be obtained from “Inpro”

35
APPENDIX C 10. Use a funnel to fill the reservoir assembly 2/3rds with
the recommended oil.

BEARING HOUSING TRICO CONSTANT LEVEL OILERS 11. Place thumb over reservoir spout, invert, and insert on
lower casting assembly at the point where the bottom edge
INTRODUCTION of the reservoir assembly is at the level “X” mark from step
8. Quickly tighten set screws on the side of the reservoir
Constant level oilers provide a visible and proven way to supply oil assembly.
to both bearing housings. Read and follow the below instructions to
ensure proper operation of the oiler. 12. Start up equipment to verify proper oil level is being
maintained.
1. Prior to installing the Opto-Matic Oiler, shaft rotation
direction must be determined, typically indicated by an ar-
row on the casting of the equipment. Install oiler on the side
of the equipment facing the direction of shaft rotation to
prevent misfeeding of the oiler (FIGURE 21A).

2. Determine proper oil level, which may be indicated on the Direction of shaft rotation Figure 21A
equipment with an arrow. If that is not the case, engineering
drawings or the equipment’s operator manual can provide
the information. Indicate proper oil level on equipment us-
ing a marking device such as; a marker, scribe, paint, etc.
Spirit
Level
3. Loosen set screws on reservoir assembly. Remove reser-
voir assembly from lower casting. Figure 21B

4. Be sure all connecting hardware is free from contaminants


(burrs, chips, dirt, etc.) to prevent clogging or damage to
the equipment to be lubricated.
Spirit
Level
5. Connect lower casting to bearing chamber either through
the side connection, Type E and EH oilers (FIGURE 19B) or
the bottom connection, Type EB and EHB oilers (FIGURE
19C). Use thread compound on threaded areas. Figure 21C

6. Verify the lower casting is level and parallel with desired


oil level (FIGURE 19B and 19C). Make necessary adjustments
if needed until lower casting is level.
Level Line

7. From the oil level mark indicated on the equipment, use Oil Level

a level to put a mark on the outside of the Opto- Matic lower Figure 21D
casting to indicate where the oil level should be (FIGURE
19D).

8. Measure the distance between Opto-Matic Oiler casting X


Mark Level ÒXÓ

edge and top edge of spout angle (FIGURE 19E). Mark this Mark from
distance above the original line made in step 7 on the out- step 7

side of the Opto-Matic lower casting (FIGURE 19F). Now the Figure 21E Figure 21F
bottom of the reservoir assembly can be used as an indicator
of oil level. FIGURE 21 – Trico Oiler
9. Fill the equipment bearing chamber through the lower
casting until the oil level reaches just below the mark made
in step 7 on the lower casting. DO NOT fill at or above this
mark as it will cause your equipment to have a high oil level.

36
 

Packed Orientation Mechanically Sealed Orientation


Sleeve
Pump Model Module Nearest
Diameter A B C D E F G H J K L M
Obstruction
2.5x3-10 SP 1 1.750 2.250 2.559 2.362 1.329 1.299 0.276 ¼”- 18 4.330 3/8” - 16 1.937 2.500 2.953 0.437

3x4-10 SP 1 1.750 2.250 2.559 2.362 1.329 1.299 0.276 ¼” - 18 4.330 3/8” - 16 1.937 2.500 2.953 0.437

4x6-10 SP 4 2.375 2.625 3.346 2.755 1.496 1.594 0.453 ¼” - 18 5.512 ½” - 13 2.563 3.250 3.858 0.500

5x6-10 SP 3 1.750 2.250 2.559 2.362 1.329 1.280 0.591 ¼” - 18 4.330 3/8” - 16 1.937 2.500 2.953 0.437

6x8-10 SP 3 1.750 2.250 2.559 2.362 1.329 1.280 0.591 ¼” - 18 4.330 3/8” - 16 1.937 2.500 2.953 0.437

10x10-10 SP 6 2.375 2.625 3.346 2.795 1.496 1.575 0.846 ¼” - 18 5.512 ½” - 13 2.563 3.250 3.565 0.500

5x6-11 SP 2 1.750 2.250 2.559 2.362 1.329 1.329 0.276 ¼” - 18 4.330 3/8” - 16 1.937 2.500 2.953 0.437

3x4-12 SP 1 1.750 2.250 2.559 2.362 1.329 1.299 0.276 ¼” - 18 4.330 3/8” - 16 1.937 2.500 2.953 0.437

4x5-12 SP 2 1.750 2.250 2.559 2.362 1.329 1.329 0.276 ¼” - 18 4.330 3/8” - 16 1.937 2.500 2.953 0.437

5x6-12 SP 3 1.750 2.250 2.559 2.362 1.329 1.280 0.591 ¼” - 18 4.330 3/8” - 16 1.937 2.500 2.953 0.437

6x8-12 SP 5 2.375 2.625 3.346 2.795 1.575 1.574 0.414 ¼” - 18 5.512 ½” - 13 2.563 3.250 3.858 0.500

8x10-12 SP 6 2.375 2.625 3.346 2.795 1.496 1.575 0.846 ¼” - 18 5.512 ½” - 13 2.563 3.250 3.565 0.500

10x10-12 SP 6 2.375 2.625 3.346 2.795 1.496 1.575 0.846 ¼” - 18 5.512 ½” - 13 2.563 3.250 3.565 0.500

2x3-15 SP 2 1.750 2.250 2.559 2.362 1.329 1.329 0.276 ¼” - 18 4.330 3/8” - 16 1.937 2.500 2.953 0.437

3x4-15 SP 2 1.750 2.250 2.559 2.362 1.329 1.329 0.276 ¼” - 18 4.330 3/8” - 16 1.937 2.500 2.953 0.437

4x5-15 SP 4 2.375 2.625 3.346 2.755 1.496 1.594 0.453 ¼” - 18 5.512 ½” - 13 2.563 3.250 3.858 0.500

5x6-15 SP 5 2.375 2.625 3.346 2.795 1.575 1.574 0.414 ¼” - 18 5.512 ½” - 13 2.563 3.250 3.858 0.500

6x8-15 SP 5 2.375 2.625 3.346 2.795 1.575 1.574 0.414 ¼” - 18 5.512 ½” - 13 2.563 3.250 3.858 0.500

4x5-18 SP 5 2.375 2.750 3.346 2.795 1.575 1.574 0.414 ¼” - 18 5.512 ½” - 13 2.563 3.250 3.858 0.500

FIGURE 22A – Packing/Seal Chamber Details

37
 

Packed Orientation Mechanically Sealed Orientation


Sleeve
Pump Model Module Nearest
Diameter A B C D E F G H J K L M
Obstruction
8x10-15 SP 7 3.000 3.750 3.937 2.913 1.574 N/A 1.142 3/8” -18 6.299 ½” - 13 3.187 3.875 4.500 0.562

10x12-15 SP 7 3.000 3.750 3.937 2.913 1.574 N/A 1.142 3/8” -18 6.299 ½” - 13 3.187 3.875 4.500 0.562

5x8-18 SP 7 3.000 3.750 3.937 2.913 1.574 N/A 1.142 3/8” -18 6.299 ½” - 13 3.187 3.875 4.500 0.562

6x8-18 SP 7 3.000 3.750 3.937 2.913 1.574 N/A 1.142 3/8” -18 6.299 ½” - 13 3.187 3.875 4.500 0.562

8x10-18 SP 7 3.000 3.750 3.937 2.913 1.574 N/A 1.142 3/8” -18 6.299 ½” - 13 3.187 3.875 4.500 0.562

FIGURE 22B – Packing/Seal Chamber Detail

38
708A 812 364A 756 676A 444 179A 364B 728 676L 372P 364L 008

028

372
708NA 164P
708NB
069N
472B
508

544N
708N

069P

164N

ITEM DESCRIPTION
544G
008 BEARING ADAPTER
708GA
028 BEARING ARM
808GB
069N BALL BEARING, OUTBOARD

069P BALL BEARING, INBOARD

164N BEARING HOUSING, OUTBOARD 472A 591A 179B 591B


164P BEARING HOUSING, INBOARD

179A/B CASING ASSEMBLY

364A O-RING, STUFFING BOX

364B O-RING, SHAFT SLEEVE

364L LIP SEAL

364G CASING GASKET FIGURE 23 708E

PACKED SP SPLIT CASE PUMP


372 GLAND, PACKING

372P PACKING SET

444 IMPELLER
ITEM DESCRIPTION
472A KEY, IMPELLER 544A 544C
708NB WASHER, BEARING HOUSING
544B
472B KEY, COUPLING 808A 591C 808B
728 SHAFT
508 GREASE FITTING
756 SHAFT SLEEVE
544A ACORN NUT, CASING
808A STUD, CASING
544B ACORN NUT, CASING
808B STUD, CASING 364G
544C NUT, CASING PIN
808GB STUD, GLAND
544G STUD, GLAND
812 STUFFING BOX
544N LOCKNUT, OUTBOARD

591A PIN, CASE WEAR RING


NOTE: Recommended spare parts are
591B PIN, STUFFING BOX
in BOLD.
591C PIN, CASING

676A CASE WEAR RING

676C IMPELLER WEAR RING

676L LANTERN RING

708A CAPSCREW, BEARING ARM

708E LIFTING EYE BOLT

708GA CAPSCREW, GLAND

708GB WASHER, GLAND

708N LOCKWASHER, OUTBOARD

39
364L 812 364A 372M 364B 676C 179A 444 472A 676A 756 008 164P 508 728 472B

708NA
708NB

069N

164N

544N
708N

069P

ITEM DESCRIPTION
008 BEARING ADAPTER
591B
069N BALL BEARING, OUTBOARD

069P BALL BEARING, INBOARD 591A


164N BEARING HOUSING, OUTBOARD
179B
164P BEARING HOUSING, INBOARD

179A/B CASING ASSEMBLY

364A O-RING, STUFFING BOX

364B O-RING, SHAFT SLEEVE


708E
364L LIP SEAL

364G CASING GASKET

372M MECHANICAL SEAL


FIGURE 24
444 IMPELLER
544A 544C 544B
472A KEY, IMPELLER ITEM DESCRIPTION
808A 591C 808B
472B KEY, COUPLING 728 SHAFT

508 GREASE FITTING 756 SHAFT SLEEVE

544A ACORN NUT, CASING 808A STUD, CASING

544B ACORN NUT, CASING 808B STUD, CASING 364G

544C NUT, CASING PIN 812 SEAL CHAMBER

544N LOCKNUT, OUTBOARD

591A PIN, CASE WEAR RING NOTE: Recommended spare parts are
591B PIN, STUFFING BOX in BOLD.
591C PIN, CASING

676A CASE WEAR RING

676C IMPELLER WEAR RING

708E LIFTING EYE BOLT

708N LOCKWASHER, OUTBOARD

708NA CAPSCREW, BEARING HOUSING

708NB WASHER, BEARING HOUSING

For technical assistance, parts, or repair, please contact:

901.850.5115 | franklinwater.com
Form 10000002023 Rev. 000 06/20 40 Copyright © 2020, Franklin Electric, Co., Inc. All rights reserved.

You might also like