Professional Documents
Culture Documents
BRIGADA ESKWELA
RECORD OF DONATIONS RECEIVED
ITEMS/ MATERIALS QUANTITY DATE RECIEVED NAME OF DONOR ASSUMED COST OF ITEMS
Per Unit Total
Cement 10 bags May 22, 2017 Divina Ducusin 250 2500
Sand 18 cubic May 25, 2017 Northpoint Aggregates 1200
Gravel 15 cubic May 25, 2017 Northpoint Aggregates 1500
Soil 190 cubic May 25, 2017 Northpoint Aggregates 150
Blackboards 2 pcs May 20, 2017 Northpoint Aggregates 1500
Hollow blocks 200 pcs May 19, 2017 4 Sisters Aggregates 6
Hollow blocks 200 pcs June 1, 2017 808 aggregates 6
Paint 4 liter May 29, 2017 BJMP 400
Corrugated Sheets 10 pcs June 1, 2017 Villacruz Construction Supply 300
Pail flush 1 pc June 1, 2017 Villacruz Construction Supply 800
TOTAL
Prepared by: Noted by: