The use of scheduling agreements can shorten processing times and reduce the amount of
paperwork you are faced with. One delivery schedule can replace many discrete purchase orders or
contract release orders.
A purchase requisition of type Outline Agreement Requisition can be created with subcontracting
line items (Item Category – L Subcontracting) manually by a requestor. The purchase requisition can
be converted into a scheduling agreement or else we can create manually . The scheduling
agreement is subject to approval based on predefined parameters before you generate delivery
schedule or schedule lines (manually or via MRP run) and communicate them to the subcontractor.
With the supply of the finished material, the goods receipt is created. The invoicing process is then
triggered.
Must be select all MRP Views, and at MRP View 2: Special Procurement: 30
MRP View -4
2 Scheduling Agreement for Subcontracting Procurement Process
M.Jayababu(SAP MM /S4 HANA Sourcing and Procurement Consultant)
Here, must need Info-record, why because net price will not allow the manually at scheduling
agreement without release (LP).
3 Scheduling Agreement for Subcontracting Procurement Process
M.Jayababu(SAP MM /S4 HANA Sourcing and Procurement Consultant)
Here, I have saved with machining /service charges Rs.8 and also tax code: M0
Now check whether production version created or not via MM02/MM03 at MRP View -4
➢ Create scheduling agreement for subcontracting manually Via ME31L or convert from PR
Agreement Type: LP
Position the cursor on a schedule line and choose Item Component Overview to display the
screen for processing components. You can enter or change the individual components in the same
way as an order item.
Here, we can see the child components for each delivery schedule
8 Scheduling Agreement for Subcontracting Procurement Process
M.Jayababu(SAP MM /S4 HANA Sourcing and Procurement Consultant)
Look at here, for each finished good we need to spend approx. 1000 kgs of raw material and those
will give to the subcontract vendor
Here, I have sent 4000 kgs of raw materials to the sub-contractor at a time, so he able to supply as
on my delivery schedules
10 Scheduling Agreement for Subcontracting Procurement Process
M.Jayababu(SAP MM /S4 HANA Sourcing and Procurement Consultant)
Here, we just get the confirmation from subcontracting vendor how much quantity of raw material
he has utilized from among them. So here we need to enter the manually after getting confirmation.
Otherwise, it’s taken full quantity from BOM.
Let’s suppose, he has utilized 900 Kgs from given 1000 kgs.
12 Scheduling Agreement for Subcontracting Procurement Process
M.Jayababu(SAP MM /S4 HANA Sourcing and Procurement Consultant)
Among 4000 kgs sub-contracting vendor utilized 900 kgs for 1st delivery schedule of 50 number
13 Scheduling Agreement for Subcontracting Procurement Process
M.Jayababu(SAP MM /S4 HANA Sourcing and Procurement Consultant)
Benefits
Increase the automation of delivery schedule generation and accuracy of planning with MRP run
Enable suppliers to plan and allocate their resources more efficiently with long term planning