You are on page 1of 4

(a) (b)

Construction
Issues
discussion of construction
issues and techniques
Figure 1. a) Hilti Kwik Bolt-TZ Anchor; b) Hilti HSL-3 Anchor.

P
ost-installed expansion anchors are • the friction between the washer and fixture
used to attach fixtures to concrete • the friction between the fixture and
and masonry. Expansion anchor types concrete surface®

E
include torque-controlled anchors, which • the amount of wedge expansion
must be torqued to expand wedges, and displace- • the concrete compressive strength

R
ment-controlled anchors, which require impact • the angle between the installed anchor and
forces on a sleeve or plug to expand wedges. fixture surface

U
Expansion anchors that rely ht on torque to expand • the elapsed time after the installation
yrig

T
Copwedges are referred to as torque has been applied
torque-controlled expan- Figure 2 illustrates the effect an external tension
How Installation Torque Can
C
sion anchors. This article load has on a torque-controlled expansion anchor.

e
U
discusses the importance The load corresponding to pre-load in the
Affect Expansion Anchors of torque on the installa-
n anchor, and clamping between the fixture and
i
R
tion and performance of the concrete, is designated Ntorque. Torquing causes
z
T
torque-controlled expan- the anchor to undergo a positive (i.e. tension)

g a
sion anchors installed into concrete. displacement, which is offset by a negative (i.e.

S
By Richard T. Morgan, P.E. compression) displacement in the concrete. The
a
Why Torque Expansion Anchors? amount of pre-load, clamping, and displacement
m
Figure 1 illustrates the components of a torque-
are dependent on the parameters listed above.
Application of external tension load to the
controlled expansion anchor. Applying a torque to fixture reduces the clamping load between the
the nut activates a mechanism whereby displace- fixture and concrete while adding some tension
ment (movement) causes the wedges to expand load to the anchor. Since concrete is typically
into the concrete. This mechanism consists of stiffer in compression compared to the tension
a tapered mandrel that moves up through the stiffness of an anchor, the additional tension
wedges. The tapered mandrel can be a part of load on the anchor resulting from the external
Richard T. Morgan is the the bolt shank (Figure 1a), or it can be a sepa- tension load is minimized as long as any clamp-
Manager for software and rate assembly that threads onto the bolt shank ing load remains.
literature in the Technical (Figure 1b). When the wedges are expanded, a Once the clamping load between the fixture
Marketing Department of Hilti tension pre-load develops in the anchor along and concrete is completely removed, any external
North America. He is responsible with a compression clamping load between the tension load applied to the fixture acts directly
for PROFIS Anchor and PROFIS fixture and the concrete. Pre-loading reduces the on the anchor. Figure 3 illustrates the effect an
Rebar software and can be reached amount of displacement the anchor undergoes external tension load has on a torque-controlled
at richard.morgan@hilti.com. when subjected to external tension load. Pre- expansion anchor after the clamping load between
loading also reduces anchor fatigue under cyclic the fixture and concrete has been removed.
loads. Clamping eliminates gaps between the It is necessary to make a distinction between
fixture and concrete. anchor performance in uncracked concrete versus
cracked concrete. When a torque controlled
expansion anchor is installed in uncracked con-
What Results from Torquing? crete, the anchor pre-load created by torquing will
Torquing creates a tension pre-load in the anchor decrease over time. Relaxation within the interface
and a commensurate clamping load between the between the nut and bolt threads and relaxation
fixture and the concrete. Tension pre-load and of the stressed concrete in the areas adjacent to
clamping load depend on several parameters: the expansion wedges contribute to this decrease.
• the amount of torque applied to the anchor The anchor pre-load decrease occurs rapidly at
• the friction that develops between the nut first, sometimes within minutes after the initial
and bolt threads torque has been applied. The decrease continues
• the friction between the nut and washer over several hours, then days, eventually reaching

8 April 2017
tension

tension
load

load
All tension load
increase in tension load on resulting from
the anchor resulting from Nexternal Nexternal acts on

external applied
Ntorque the anchor.

tension load

external applied
(Nexternal)

tension load
(Nexternal)
created by torqueing

created by torqueing
pre-load/clamping

pre-load/clamping
loss of clamping load
resulting from Nexternal
(Ntorque)

(Ntorque)
loss of all clamping
load resulting from
remaining clamping load Nexternal
anchor pre-load clamping anchor pre-load clamping
resulting from Nexternal
displacement displacement

anchor concrete anchor concrete


(tension) (compression) (tension) (compression)

Figure 2. Effects of external tension load with clamping. Figure 3. Effects of external tension load without
® clamping.

a plateau (e.g. 100+ days). The amount of


anchor pre-load lost over this time can range
can lose all of the anchor pre-load when
a crack propagates to the anchor. The size

R E
follow-up expansion capability. Therefore, it
is important to select an anchor specifically

U
between 50-60% of the initial anchor pre- of the drilled hole ht is effectively increased, qualified for use in cracked concrete.
yrig

T
load. Re-torquing permits some of this anchor Cop additional wedge expan-
which requires Whether cracked or uncracked concrete
pre-load loss to be regained. However, a loss sion, via additional anchor displacement, conditions exist, pre-load and the com-

C
of anchor pre-load due to relaxation will con- to accommodate the crack. This additional mensurate clamping load will decrease.

e
U
tinue to occur, albeit to a lesser extent than wedge expansion resulting from the addi- Once these loads are removed, any addi-
the original loss. Re-torquing is discussed tional anchor displacement is referred to
i n tional external tension load applied to

R
later in this article. as follow-up expansion. Torque-controlled the fixture will cause additional anchor
z
T
With respect to cracked concrete condi- expansion anchor design for cracked con- displacement and “lift-off” of the fixture,
tions, torque-controlled expansion anchors a
crete conditions requires the anchor to have
g
whereby a space develops between the

S m
a
ADVERTISEMENT–For Advertiser Information, visit www.STRUCTUREmag.org

www.buysuperstud.com/DeflectionClips
or call 800.477.7883
US Patent 6213679; other patents pending

STRUCTURE magazine 9 April 2017


fixture and concrete surface. The tension requirements for testing in ACI 355.2 includes anchor in an under-sized drilled hole can
load is now acting directly on the anchor(s). provisions for checking the effects of under- damage the wedges and inhibit wedge
Anchoring-to-concrete strength design pro- torquing. These provisions are given in expansion during torquing. Installing an
visions for tension assume the loads acting Section 5.2.3.2.1, and are as follows: anchor in an oversized drilled hole results
on an anchorage act directly on the anchor “For the reliability tests performed with in the wedges not able to fully engage the
elements, i.e., no pre-load/clamping load reduced installation effort (Table 4.1, Test concrete, thereby preventing them from
remains. Anchoring-to-concrete strength 3 and Table 4.2, Test 5), install and set the properly expanding when the anchor is
design provisions for shear likewise assume anchor with a setting torque of 0.5Tinst. Do torqued or externally loaded.
the loads act directly on the anchor ele- not reduce the torque from this amount.”
ments, i.e., no clamping load remains. The parameter Tinst is defined in ACI 355.2 How is Inspection
Furthermore, the clamping load that does Section 2.2 – Notation as the “specified or
develop from torquing an expansion anchor maximum setting torque for expansion or
Accomplished?
is not considered sufficient to design an pre-stressing of an anchor.” Tinst corresponds The MPII for an anchor provides specified
anchorage as a slip-critical connection for to the recommended torque value given torque values. These torque values must
resisting shear load. in the MPII. Setting a torque-controlled be used when installing the anchor. The
expansion anchor with Tinst causes anchor IBC requires special
® inspection for “materi-

E
What is the Result displacement/wedge expansion and pre- als and systems required to be installed in
load/clamping load to develop. Referencing accordance with additional manufacturer’s
of Improper Torquing?

R
the ACI 355.2 Commentary Sections R5.2.3 instructions” (e.g. reference Section 1705,
Expansion anchors must be torqued per and R.5.2.3.1, the test provisions given Required Special Inspections and Tests, and

U
the values provided in the Manufacturer’s in Section 5.2.3.2.1 ht are intended to sim- specifically Section 1705.1.1 Special cases
yrig

T
Printed Installation Instructions (MPII) to Cop
ulate “installation error on the job site” in the 2015 IBC). Special inspection is
properly expand the wedges and clamp the (i.e. under-torquing) and to determine “if intended to be an independent evaluation

C
fixture. Under-torquing results in under- the anchor will still properly function if of the work that has been performed. The

e
U
expansion of the wedges, which reduces set with a torque substantially below the special inspector is employed by, and acts on
the amount of clamping developed. Once recommended torque.” An under-torqued
i n behalf of, the owner or through the archi-

R
pre-load/clamping is removed from an expansion anchor will have under-expanded tect/engineer of record who represents the
z
T
under-torqued expansion anchor subjected wedges. Testing per ACI 355.2 Section owner. The special inspector should not
to tensile loading, the anchor will displace, a
5.2.3.2.1 assesses if a torque-controlled
g
be employed by the contractor since this

S
resulting in follow-up wedge expansion and expansion anchor set with a torque less would be considered a conflict of interest.
lift-off of the fixture. a
than Tinst , and after removal of any pre- Therefore, special inspection with respect
An anchor group consisting of anchors
that are torqued unequally during installa- m
load/clamping load, can undergo sufficient
follow-up expansion to function in an
to a torque-controlled expansion anchor is
a means to verify, among other things, that
tion can have an unequal load distribution acceptable manner. the anchor has been properly installed using
on the anchors. For example, Section 5.2.2 Over-torquing a torque-controlled expan- the manufacturer’s specified torque value.
– Drill bit requirements in the American sion anchor could result in the occurrence The ESR will note special inspection
Concrete Institute (ACI) Standard ACI of various failure modes. One possible fail- requirements unique to an anchor. These
355.2 (Qualification of Post-Installed ure mode is concrete splitting. The ACI special inspection requirements can include
Mechanical Anchors in Concrete) permits 355.2 test 9.3 – Service-condition test at verification of the “tightening torque” used
anchor installation at an angle up to 6 minimum edge distance and minimum spac- to install the anchor. Torquing must be
degrees from perpendicular. Anchors in a ing “is performed to check that the concrete performed with a properly calibrated torque
group that are installed at an excessive angle will not experience splitting failure during wrench. This assures that the manufactur-
(with respect to perpendicular) will have anchor installation.” The test consists of er’s specified setting torque is used, and it
a different tension pre-load compared to installing two anchors in uncracked con- also helps avoid under-torquing or over-
anchors in the group installed perpendicular crete at a minimum edge distance (c min) torquing of the anchor. Since the interface
to the surface. If this unequal load distri- and minimum spacing (smin) established between the nut and bolt threads is integral
bution on the anchors is not considered, by the anchor manufacturer. Each anchor to developing pre-load in the anchor, these
the calculated anchorage capacity may be is installed with a setting torque that is threads should be inspected for damage or
unconservative. A non-uniform clamping greater than the smaller of (1.7Tinst) and fouling before torquing, and should never
load will also develop between the fixture (Tinst + 100 ft-lb). The smallest values for be lubricated.
and concrete. cmin and smin that can be achieved without Verifying a torque value brings up the sub-
Torque-controlled expansion anchors splitting failure represent the minimum ject of re-torquing. As previously noted, even
must be qualified per the International edge distance and minimum spacing for without any external load being applied to an
Code Council Evaluation Service (ICC- the anchor in both cracked and uncracked expansion anchor installed in uncracked con-
ES) acceptance criteria AC193 (Acceptance concrete. Over-torquing can also result crete, the pre-load resulting from torquing
Criteria for Mechanical Anchors in Concrete in steel failure of the anchor, the anchor tends to decrease over time due to relaxation.
Elements) in order to receive recognition pulling through the wedges, or the entire Expansion anchor pre-load loss in cracked
under the International Building Code anchor pulling out of the concrete. concrete occurs when a crack propagates to
(IBC). Recognition is given in an ICC-ES Torque-controlled expansion anchors the anchor.
evaluation report (ESR). AC193 also refer- must be installed in holes drilled with Re-torquing an expansion anchor is used
ences ACI 355.2; Section 5.2.3 – Setting matched-tolerance bits. Installing an to reintroduce a higher preload or clamping

STRUCTURE magazine 10 April 2017


load. Re-torquing can also be used to re-set a clamping load between the fixture and The MPII and ESR provide specified instal-
the anchor when the location of a fixture concrete. A properly qualified, designed, lation torque values for an anchor. The ESR
must be adjusted. The nut threads, anchor and installed expansion anchor set with the notes if the anchor is qualified for use in
threads, and area under the washer should manufacturer’s specified installation torque cracked concrete and the special inspection
be cleaned before re-torquing if the nut is will function as designed. Under-torquing requirements. Special inspection of torque-
loosened or removed. When re-torquing an causes under-expansion of the wedges, controlled expansion anchors, conducted by
anchor, the re-torque value should never which results in lower-than-intended an approved agency acting on behalf of the
exceed the torque value given in the MPII. clamping of the fixture and increased owner or owner’s representative, is required by
A rule of thumb is to limit the number of anchor displacement when external tension the IBC. Calibrated torque wrenches or power
times an expansion anchor can be re-torqued loads are applied. Over-torquing can lead to tools specifically designed for setting a torque-
to three times. Consult with the anchor concrete failure, steel failure of the anchor, controlled expansion anchor should be used
manufacturer for guidance with respect to or some form of anchor pullout failure. for installation and inspection of the anchor.▪
a particular product.
ACI 355.2 Section 5.2.3.1.1 includes
provisions for testing the relaxation
effects on a torque-controlled expan- ®

E
sion anchor. The recommended torque
value (Tinst) given in the MPII is applied

R
using a calibrated torque wrench. After
10 minutes, the nut is loosened and
GEOPIER GROUND IMPROVEMENT

U
a torque of 0.5Tinst is re-applied using CONTROLS
righ
t STRUCTURE SETTLEMENT

T
the calibrated torque wrench. This test opy
C
simulates the loss of pre-load over the

C
service life of the anchor and assesses if

e
U
the anchor can function in an acceptable
manner after relaxation has occurred.
i n
R
Torquing is sometimes used as a crude
z
T
means of proof loading an expansion
anchor to verify some level of perfor-
g a
S
mance and rule out gross installation
errors. The use of torque to proof- a

ADVERTISEMENT–For Advertiser Information, visit www.STRUCTUREmag.org


load an anchor is not precise because
the torque-tension relationship can m
be highly variable from one anchor
to another.
A manually operated torque wrench is
commonly used to install and proof-load
torque-controlled expansion anchors.
The published torque values of a power
tool such as an impact wrench do not
coincide with a manually applied torque
value, and standard impact wrenches
do not have the required calibration
accuracy. Therefore, an impact wrench
should not, as a rule-of-thumb, be
used to set a torque-controlled expan-
sion anchor. That said, technological
GIVE YOUR STRUCTURE STABILIT Y
advances by some manufacturers now
permit torque-controlled expansion
anchors to be set with an “adaptive Work with Geopier’s geotechnical engineers to solve your ground
torque tool” specially calibrated for improvement challenges. Submit your project specifications to
setting this type of anchor.
receive a customized feasibility assessment and preliminary cost
estimate at geopier.com/feasibilityrequest.
Summary
This article discussed the importance of 800-371-7470
torquing with respect to the installation geopier.com
and functioning of torque-controlled info@geopier.com
expansion anchors installed into con-
crete. Installation torque creates a
tension pre-load in the anchor and

STRUCTURE magazine 11 April 2017

You might also like