TASK PLAN

PROJECT: OFON 2 DATE: 29.May.14

WORKSITE: OFON 2/ Rockwater 2 SHEET: 2 OF 5

TASK TITLE: Metrology with Saturation Divers PLAN NO: TP001

Step TASK DESCRIPTION Resp* Check+

Status

RA has been conducted and approved

Toolbox talk (stage 3 RA) has been conducted with all personnel involved in the operation
 The Rockwater 2 has been mobilized in accordance with mobilization procedure and has
completed DP trials in accordance with Rockwater 2 standard operating procedure.
 Saturation Divers are ready to perform the job.
 Vessel is in DP at correct position for transponder stand deployment.
 All required survey data is displayed on the ship Navigation screen.
 A beacon is attached to the crane wire.
Sub – Task #1 Divers Deployment
1. Position vessel at work location BR
2. Bell to be deployed at location. DS
Diver to go out of the bell and look at the work location, using nav DS
3.
data and mini beacon
Sub – Task #2 Temporary frame preparatory work on deck
Insert a transponder fitted with a centralizing collar in frame
4. DF
receptacle. Secure transponder with rope.
5. Connect tag lines to the transponder frame as required DF
6. Attach light stick and strobe to the rigging. DF
Sub – Task #2 Temporary frame deployment

Access to the deck is to be restricted to essential personnel only during temporary


frames deployment.

Remove cargo lashing off the frame as required. DF/CO


7.
Connect the pre-rigged transponder frame to the crane.
Lift and deploy the stand with the crane DF/CO
Note: - Control of the load must be kept with tag-lines
8.
Note: Make sure that the divers are under the bell during the stand
lowering.
9. Lower the transponder frame 10m from the sea bed. DF/CO
Sub – Task #3 Transponder frame positioning on seabed
TASK PLAN
PROJECT: OFON 2 DATE: 29.May.14

WORKSITE: OFON 2/ Rockwater 2 SHEET: 3 OF 5

TASK TITLE: Metrology with Saturation Divers PLAN NO: TP001

Step TASK DESCRIPTION Resp* Check+

Diver to locate and assist transponder frame final positioning by DS


10. means of tag lines. Communicate with Bridge /surveyor for the final
positioning.
11. Crane operator to slowly pay-out to the seabed. DS
12. Surveyor to confirm position prior to disconnect rigging. DS/SR
Sub – Task #4 Transponder frame rigging disconnection
Disconnect the frame rigging /crane wire. ROV to monitor wire SS/SR
13.
recovery until clear from frame.
14. Performed the USBL fixing, as required. SR
15. Diver to move location. DS
Repeat steps step 4 to 13 for next transponder frames SR/DS
16.
deployments.
END OF TASKS
DSV Rockwater 2 – Survey and Positioning Document Identification Number
Procedure NG-018-XX-GLO-203012
Revision: 00 Status: IFR
Document Type: PRC System/Subsystem: 00 Discipline: PLR Rev. Date: 14-April-2014

Contractor document number Page 61 of 94

13.17 OFP2 SOUTH METROLOGY ARRAY

Figure 40: OFP2 South Metrology Array Layout

Location Easting (m) Northing (m)


Riser 1 – 12” GE 732,523.2 456,506.0
Riser 2 – 10” WI 732,534.1 456,501.4
Riser 3 – 6” GL 732,538.6 456,499.6
Riser 4 – 16” MP 732,544.4 456,497.1
Flange 1 - 12” GE 732,495.0 456,484.1
Flange 2 - 10” WI 732,520.8 456,457.9
Flange 3 - 6” GL 732,529.9 456,458.8
Flange 4 - 16” MP 732,568.9 456,459.6
Pipeline 12” GE 732,476.9 456,468.3
Pipeline -10” WI 732,520.9 456,433.9
Pipeline – 6” GL 732,534.4 456,435.2
Pipeline – 16” MP 732,572.0 456,441.0

“This document is the property of TEPNG. It must not be reproduced or transmitted to others without written authorization from
the Company”
DSV Rockwater 2 – Survey and Positioning Document Identification Number
Procedure NG-018-XX-GLO-203012
Revision: 00 Status: IFR
Document Type: PRC System/Subsystem: 00 Discipline: PLR Rev. Date: 14-April-2014

Contractor document number Page 62 of 94

Seabed 1 732,491.9 456,508.4


Seabed 2 732,448.2 456,473.2
Seabed 3 732,491.9 456,449.1
Seabed 4 732,519.8 456,488.1
Seabed 5 732,547.5 456,468.0
Seabed 6 732,583.2 456,479.0
Seabed 7 732,593.7 456,448.8
Seabed 8 732,546.4 456,446.6

13.18 OFP2 NORTH METROLOGY ARRAY

Figure 41: OFP2 North Metrology Array Layout

Easting (m) Northing (m)


R1 – 4” GL (OFD2) Riser 732,573.6 456,546.0
R2 – 12” MP Riser 732,576.0 456,545.0
R3 – 4” GL Riser 732,578.3 456,544.1
R4 – 8” WI Riser 732,580.6 456,543.1
F1 - 4” GL (OFD2) Pipeline Flange 732,553.1 456,631.2

“This document is the property of TEPNG. It must not be reproduced or transmitted to others without written authorization from
the Company”
TRANSPONDER TEMPORARY STRUCTURE TYPE.2

RI-01
11.6T WLL MASTER LINK

RI-04 RI-04
4T WLL 2m EWL FIBER SOFT SLING 4T WLL 2m EWL FIBER SOFT SLING

RI-03
4.75T WLL SHACKLE RI-03
4.75T WLL SHACKLE

PIPELINE FLANGE
SUPPORT BRACKET

MTO (RIGGING PER STRUCTURE)


ITEM QTY DESIGNATION
RI-01 1 11.6T WLL MASTER LINK
RI-04 2 4T WLL 2m EWL FIBER SOFT SLING
RI-03 2 4.75T WLL SHACKLE

OFON PHASE 2 PROJECT

FORMAT/
NG-018-SK-00001-02 SCALE REV.AA 21/05/12
TRANSPONDER TEMPORARY STRUCTURE TYPE.3

RI-01
11.6T WLL MASTER LINK

RI-04 RI-04
4T WLL 2m EWL FIBER SOFT SLING 4T WLL 2m EWL FIBER SOFT SLING

RI-03
4.75T WLL SHACKLE RI-03
4.75T WLL SHACKLE

PIPELINE FLANGE
SADDLE BRACKET

MTO (RIGGING PER STRUCTURE)


ITEM QTY DESIGNATION
RI-01 1 11.6T WLL MASTER LINK
RI-04 2 4T WLL 2m EWL FIBER SOFT SLING
RI-03 2 4.75T WLL SHACKLE

OFON PHASE 2 PROJECT

FORMAT/
NG-018-SK-00001-03 SCALE REV.AA 21/05/12
TRANSPONDER TEMPORARY STRUCTURE TYPE.1
RI-01
11.6T WLL MASTER LINK

RI-02 RI-02
10T MBL 2m EWL WIRE ROPE SLING 10T MBL 2m EWL WIRE ROPE SLING

RI-03
4.75T WLL SHACKLE RI-03
4.75T WLL SHACKLE

SEABED FRAME
ASSEMBLY

MTO (RIGGING PER STRUCTURE)


ITEM QTY DESIGNATION
RI-01 1 11.6T WLL MASTER LINK
RI-02 2 10T MBL 2m EWL WIRE ROPE SLING
RI-03 2 4.75T WLL SHACKLE

OFON PHASE 2 PROJECT

FORMAT/
NG-018-SK-00001-01 SCALE REV.AA 21/05/12
Figure 1: Metrology female receptacle on riser side.

Figure 2: Metrology female receptacle on riser side.


HSE Risk Assessment 30/05/2014

Level 3: Task Risk Assessment

DETAILS

Originator MSV_Rockwater2 Diving Superintendent Status Awaiting Approval

Approver MSV_Rockwater2 OCM Reference Procedures/Task IMCA 010 Diving from a DP vessel
Plans Metrology Procedure
Reference No R028669
Local Reference
Project Total - OFON Phase 2
Operation Diving
Location Rockwater 2
Description of Activity Deploying Transponders for metrology
Area on Site Vessel - Dive Control

MEETING DETAILS

Meeting Location Dive control Meeting Date 29/05/2014

SUBSEA 7 ATTENDEES EXTERNAL ATTENDEES

Name Role Name Role Company

Nathan Barnes Supt

Scott Oliverman Dive Supv

Jean -Claude Lerebvre Total Client REP

Monday Ekarika Client HSE

Rohin Vadera Party Chief

Daniel Hall Project Engineer

Page 1 of 3
HSE Risk Assessment 30/05/2014

TASKS

Task Hazard Safety, Health, Environmental Consequence Severity/ RPC


Probability
Prep for Over boarding of Transponders 1. Slips trips personnel injury III - Moderate
2. Pinch points Damage to equipment /assets D - Unlikely 3
3. Rigging

Corrective Measure Severity/ Resid


Probability RPC
1.1 CSB Eyes on path III - Moderate
2.1 CSB Awareness E - Very Unlikely 3
3.1 Certified in date rigging

Task Hazard Safety, Health, Environmental Consequence Severity/ RPC


Probability
Over boarding Transponders 1. Dropped object personnel injury III - Moderate
2. Equipment/asset clash Damage to equipment /assets C - Possible 2
3. Rigging

Corrective Measure Severity/ Resid


Probability RPC
1.1 Clear of subsea assets/ Structures/ Overhang III - Moderate
1.2 Personnel clear of swing path D - Unlikely 3
2.1 Suitable weather conditions
2.2 Optimal vessel heading
2.3 Tag lines if needed
2.3 clear repeated communications to crane driver
3.1 Certified in date rigging

Task Hazard Safety, Health, Environmental Consequence Severity/ RPC


Probability
Land out Transponders 1. pinch point personnel injury IV - Slight
2. Equipment/ asset clash Damage to equipment /assets D - Unlikely 3
3. poor /no Visibility

Corrective Measure Severity/ Resid


Probability RPC
1.1 CSB eyes on path IV - Slight
1.2 Diver wearing PPE gloves D - Unlikely 3
1.3 Clear repeated communications to crane driver.
2.1 Awareness of surrounding assets
3.1 CSB Diver Awareness good umbilical management
3.2 Diver transponders
3.3 Survey screen dump of vessel set up and location of task
3.4 bellman to monitor divers umbilical

Page 2 of 3
HSE Risk Assessment 30/05/2014

Task Hazard Safety, Health, Environmental Consequence Severity/ RPC


Probability
Recover transponders 1. Diver umbilical entanglement personnel injury III - Moderate
2. Transponder rigging entanglement Damage to equipment /assets C - Possible 2
3. Poor /no Visibility
4. Dropped object
Corrective Measure Severity/ Resid
Probability RPC
1.1 Diver awareness good umbilical management III - Moderate
1.2 Bellman to monitor divers umbilical D - Unlikely 3
2.1 Diver to check rigging when rigging is standing
3.1 Diver transponders
3.2 Survey screen dump of vessel set up and location of task
3.3 Diver Awareness
4.1 Personnel clear of swing path
4.2 clear of Subsea Assets/ Structures / Overhang

Page 3 of 3