Activity Network Model

1 5
2 4 9
4

1 1 7
8

3 5 6
6 4

Solution

Activity Normal Earliest Time Latest Time Total


Activity
Name Time Start Finish Start Finish Float
1 to 2 A 4 0 4 5 9 5
1 to 3 B 1 0 1 0 1 0
2 to 4 C 1 4 5 9 10 5
3 to 4 D 1 1 2 9 10 8
3 to 5 E 6 1 7 1 7 0
4 to 9 F 5 5 10 10 15 5
5 to 6 G 4 7 11 12 16 5
5 to 7 H 8 7 15 7 15 0
6 to 8 I 1 11 12 16 17 5
7 to 8 J 2 15 17 15 17 0
8 to 10 K 5 17 22 19 22 0
9 to 10 L 7 10 17 15 22 5

Critical Path
TF = 5
4 C 5 5
TF = 5 9 1 10 10
0 A 4
2 4
0 4 9

TF = 8
1 D 2
9 1 10 TF = 0
1
7 H 15
7 8 15

TF = 0
0 B 1
3 5
0 1 1
TF = 0
1 E 7 7
1 6 7 12

The Critical Path is 1-3, 3-5, 5-7, 7-8, 8-10.


Completion time is 22 days.
7

10

2
5
8

TF = 5 TF = 5
F 10 10 L 17
5 15 15 7 22
9

TF = 0
10
15 J 17
7 15 2 17

TF = 0
8
17 K 22
17 5 22
6
TF = 5
TF = 5 11 I 12
G 11 16 1 17
4 16