Professional Documents
Culture Documents
3D Finite Element Analysis of Pile Responses To Adjacent Excavation in Soft (2018)
3D Finite Element Analysis of Pile Responses To Adjacent Excavation in Soft (2018)
A R T I C LE I N FO A B S T R A C T
Keywords: To gain new insights into single pile responses to adjacent excavations in soft ground, three dimensional nu-
Finite element analysis merical parametric studies are carried out. An advanced hypoplastic (clay) constitutive model which takes ac-
Excavation depths systems count of small-strain stiffness is adopted. The effects of excavation depths (He) relative to pile (Lp) were in-
Soft clay vestigated by simulating the excavation near the pile shaft (i.e., He/Lp = 0.67), next to (He/Lp = 1.00) and below
Single pile
the pile toe (He/Lp = 1.33). In addition, the effect of pile head boundary conditions and different working loads
with FOS = 3.0 and 1.5 were also studied. The model parameters are calibrated and validated against measured
results in centrifuge reported in literature. It is found that the pile responses to excavation depend upon for-
mation level of the excavation as well as the embedded depth of the wall. With different wall depth in each case,
the induced settlement, lateral displacement and bending moment in the pile at the same stage of the excavation
was different in the three cases. Among the three cases, the excavation in case of He/Lp = 1.33 resulted in the
largest pile settlement (i.e., 7.6% pile diameter). On the other hand, the largest pile deflection was induced in
case of He/Lp = 0.67. On contrary, insignificant bending moment and changes in axial load distribution induced
in the pile on completion of the excavation in each case. However, significant bending moment (60% of pile BM
capacity of 800 kNm) induced in the pile with fixed head condition. The different working loads (with FOS = 3.0
and 1.5) influence induced pile settlement but have relatively minor effect on induced bending moment.
1. Introduction Finno et al. (1991) and Goh et al. (2003) reported case studies in
granular soil and Alluvium residual soil respectively. They demon-
It is well recognised that a pile foundation transfers the load of strated that lateral soil movements due to excavation can be detri-
superstructure to surrounding soil which is adjacent to pile shaft as well mental to adjacent piles. In both the reported case studies, piles toe
as underneath the piled foundation. Consequently, the high effective level was much deeper than the excavation level and they reported only
stress regime (stress bulb) is generated surrounding of the pile. On the the lateral behaviour of piles. Apart from field monitoring, a number of
other hand, the excavation in the ground inevitably results in the centrifuge tests were also conducted to investigate the response of
ground movement due to effective stress release. To cope with trans- single pile (Ong et al., 2006) and pile group in soft Kaolin clay (Ong
portation problems in congested cities in the world like Hong Kong, et al., 2006). They concluded that the induced bending moment and
Shanghai, London etc, underground transportation systems (involving lateral deflection of piles were highly influenced by distance from wall
tunnels for metros, excavations of metro stations and basement to fa- and pile head condition. In studies, lateral response of end bearing piles
cilitate inhabitants in the buildings for parking) have been developed. without initial applied load was reported. In reality, piled foundation in
These excavations are sometimes inevitable to be constructed adjacent soft clay behave as floating pile group and subjected to initial applied
to existing piled foundations. This condition leads to a big challenge for load from superstructure. In the presence of initial applied load, soil
a geotechnical engineer to assess and protect the integrity of piled surrounding the pile foundation experience higher effective stress level
foundation. before the commencement of adjacent excavation. Leung et al. (2000,
⁎
Corresponding author.
E-mail addresses: eng.soomro@gmail.com (M.A. Soomro), dildarali72@gmail.com (D.A. Mangnejo), riaz@quest.edu.pk (R. Bhanbhro),
nahmedmemon@gmail.com (N.A. Memon), engr.muneebmemon@gmail.com (M.A. Memon).
1
Formerly The Hong Kong University of Science and Technology, Clear Water Bay, Kowloon, HKSAR.
https://doi.org/10.1016/j.tust.2019.01.012
Received 9 March 2018; Received in revised form 7 January 2019; Accepted 13 January 2019
0886-7798/ © 2019 Elsevier Ltd. All rights reserved.
M.A. Soomro et al. Tunnelling and Underground Space Technology 86 (2019) 138–155
2003; 2006) conducted centrifuge tests to investigate the effects of an Working load
un-propped excavation on the behaviours of nearby single piles and pile Prop 1 (1.0 m)
groups in dry dense Toyoura sand. It was found that the distance from Prop 2 (4.0 m) 3.0 m
the pile to the retaining wall and pile head conditions had a large in-
Existing single pile Clay
Embedded length = 18.0 m
fluence on the induced pile bending moment and lateral deflection. Ng Prop 3 (7.0 m) Diameter = 0.8 m
et al. (2017) reported the results of three centrifuge tests which were Prop 4 (10.0 m)
carried out to study the effects of a multi-propped deep excavation in- Formation level Diaphragm wall
flight on the behaviour of single piles in dry Toyoura sand. Piles were Thickness = 0.6 m
Depth = 18.0 m
laterally restrained in terms of rotation and deflection right at or above
ground surface in the three different tests. It was concluded that lateral
restraints imposed on the pile head have a significant influence on in-
Excavation depth (He) = 12 m
duced pile bending moment. Induced bending moment due to excava-
Wall penetration ratio = 0.5
tion can exceed the pile bending capacity. Poulos and Chen (1997)
developed design charts to compute the lateral behaviour of a single
pile adjacent to deep excavation in soft ground. They performed two
staged analysis considering plane strain conditions and linear elastic
soil model. Similar work was conducted by Liyanapathirana and
Nishanthan (2016) using finite element method. In both these studies
lateral response of single pile was investigated. The settlement beha- z
viour of pile and development of excess pore water pressure and con- Working load
solidation settlement were not investigated. Korff et al. (2016) devel- Prop 1 (1.0 m)
oped an analytical model relating axial pile deformation to the vertical
Prop 2 (4.0 m) 3.0 m
soil displacement resulting from the deep excavation and also suggests Existing single pile Clay
ways to determine the pile response to lateral displacements. In their Embedded length = 18.0 m
Prop 3 (7.0 m) Diameter = 0.8 m
approach nonlinear load transfer mechanisms depending on relative Prop 4 (10.0 m)
soil pile displacements as well as pile axial deformations /strains were Diaphragm wall
Prop 5 (13.0 m)
modelled. They concluded that the settlement of piles with a large Thickness = 0.6 m
Prop 6 (16.0 m) Depth = 24.0 m
component of shaft friction is determined mainly by the actual load on
the pile relative to the pile ultimate capacity. The lateral pile response is Formation level
governed mainly by the relative stiffness of the pile to the soil. Shakeel
and Ng (2018) carried out three-dimensional coupled consolidation Excavation depth (He) = 18 m
analysis is conducted to gain insight into the response of a (2 × 2) Wall penetration ratio = 0.5
floating pile group adjacent to deep excavation in soft clay. By using a
validated finite element model, the influence of the excavation depth,
pile length, pile group location from excavation, the supporting system
stiffness, soil state and permeability, and working load are system-
atically studied. The analysis revealed that the maximum settlement
occurs when the pile group is founded at the excavation level and at a
distance of 0.75 times the excavation depth, although the induced
bending moment is insignificant. In contrast to pile group settlement, Prop 1 (1.0 m)
tilting is significant when it gets closer to the wall and minimum at a Prop 2 (4.0 m) 3.0 m Existing single pile Clay
distance of 0.75 times the excavation depth. Li et al. (2014) analysed Embedded length = 18.0 m
Prop 3 (7.0 m) Diameter = 0.8 m
the pile deflection, bending moment and lateral soil pressure in con-
sideration of factors including the excavation depth, distance from the Prop 4 (10.0 m)
excavation, the retaining wall stiffness, the pile stiffness, the pile-head Diaphragm wall
Prop 5 (13.0 m)
Thickness = 0.6 m
condition, the length of pile and axial load on the pile with the Mod- Depth = 27.0 m
Prop 6 (16.0 m)
ified-Cam Clay (MCC) model. Zhang et al. (2018) carried out the finite
element analyses considering soil of the hardening small strain (HSS) Prop 7 (19.0 m)
constitutive model to establish the excavation-induced pile behaviours Prop 8 (22.0 m)
by varying the depth of excavation, pile diameter, pile length, pile Formation level
distance away from the excavation, pile-head fixity, unsupported depth Excavation depth (He) = 24 m
of excavation and axial loadings exerted on the pile head. It is well Wall penetration ratio = 0.5
understood that the stress-strain relationship of soils is highly nonlinear
even at very small strain. The stiffness of most soils decreases as strain
increases and depends on the recent stress or strain history of the soil
(Atkinson et al., 1990; Atkinson & Sällfors, 1991). Owing to non-linear
soil behaviour, an excavation can cause reduction in the stiffness of the
ground. To obtain a satisfactory numerical model of single pile re- (a)
sponses to excavation-induced effective stress relief, the analysis needs
to take account of the small strain non-linearity of soil. Fig. 1. Configuration of numerical simulation of cases of He/Lp = 0.67; He/
Lp = 1.00; He/Lp = 1.33 (a) elevation views (b) plan view.
This study aims at systematically investigating the effects of ex-
cavation depth systems of different formation level on a loaded single
floating pile. In addition, the effect of pile head boundary conditions
and working load were also studied. Settlement, axial load distribution
pile deflections and internal bending moments along the pile, effective
stress changes and excessive pore pressure generation during
139
M.A. Soomro et al. Tunnelling and Underground Space Technology 86 (2019) 138–155
140
M.A. Soomro et al. Tunnelling and Underground Space Technology 86 (2019) 138–155
Table 1
Summary of numerical simulations.
Variable Excavation depth (m) Diaphragm wall depth Pile head Working load Objective
(m) condition (kN)
Table 2
Model parameters of kaolin clay adopted in the parametric study.
Description Parameter Reference
Effective angle of shearing resistance at critical state: ϕ′ 22° Bolton and Powrie (1986)
Parameter controlling the slope of the isotropic normal compression line in the ln(1 + e) versus lnp plane, λ* 0.11 Deduced from Al-Tabbaa (1987)
Parameter controlling the slope of the isotropic normal compression line in the ln(1 + e) versus lnp plane, κ* 0.026 Deduced from Al-Tabbaa (1987)
Parameter controlling the position of the isotropic normal compression line in the ln(1 + e)–lnp plane, N 1.36 Deduced from Al-Tabbaa (1987)
Parameter controlling the shear stiffness at medium- to large- strain levels, r 0.65 Calibrated based on Parry and Nadarajah (1974)
Parameter controlling initial shear modulus upon 180° strain path reversal, mR 14 Calibrated based on Benz (2007)
Parameter controlling initial shear modulus upon 90° strain path reversal, mT 11 Calibrated based on Benz (2007)
Size of elastic range, R 1 × 10−5 Calibrated based on Benz (2007)
Parameter controlling the rate of degradation of the stiffness with strain, βr 0.1 Calibrated based on Benz (2007)
Parameter controlling degradation rate of stiffness with strain, χ 0.7 Calibrated based on Benz (2007)
Initial void ratio, e 1.05 Deduced from measured water content
Dry density (kg/m3) 1136 Deduced from measured void ratio
Coefficient of permeability, k (m/s) 1 × 10−9 Al-Tabbaa (1987)
141
M.A. Soomro et al. Tunnelling and Underground Space Technology 86 (2019) 138–155
Table 3 prototype) thick sandy layer. The sandy layer serves as a drainage
Concrete parameters adopted in finite element analysis. boundary at the bottom of the box. The strongbox was then placed in a
Description Parameter consolidation frame to achieve a soft clay layer of 130 mm (6.5 m in
prototype).
Young's modulus, E 35 GPa After installation of model pile and wall at 1g, a portion of the clay
Poisson's ratio, ν 0.3
was then removed and replaced by a latex bag containing ZnCl2 solu-
Density, ρ 2400 kg/m3
tion. After assembling the centrifuge model package the whole package
was mounted on the swinging platform of the centrifuge and the cen-
2.3. Numerical modelling procedure trifuge was spun to 50g. On completion of reconsolidation (i.e., the
degree of the consolidation > 90%), in-flight excavation was simulated
The numerical analysis modelling procedure for a typical case (i.e., by draining away zinc chloride fluid from the latex bag.
He/Lp = 0.67) is summarized as follows:
3.2. Back-analysis of centrifuge test and modelling procedure
(a) Step 1: Set up the initial boundary and initial effective stress con-
ditions (i.e., static effective stress conditions with varying Fig. 3(b) shows an isometric view of a typical finite element mesh
K0 = 0.63). for back-analyzing centrifuge test by Ong et al. (2006). To facilitate
(b) Step2: Activate the brick elements representing single pile (mod- direct comparison between the measured and computed results, all
elled as “wished-in-place”). dimensions of the finite-element mesh were in model scale and were
(c) Step 3: Apply the working load (determined from numerical pile identical to those in the centrifuge tests. Displacements perpendicular
load test) on the pile. to the outer boundaries of the mesh were restrained. The soil and the
(d) Step 4: Allow excess pore pressure, which generated in result of deadweight were modelled with eight-node brick elements while the
application of working load on the pile, to dissipate. pile was modelled with four-node shell elements. The Kaolin clay
(e) Step 5: Activate the brick elements representing the diaphragm parameters are summarized in Table 2. The sand in the centrifuge
wall. model test that underlies the Kaolin clay was modelled using the Mohr-
(f) Step 6: Staged multi-propped excavation is simulated as described Coulomb soil model. The sand used was Toyoura sand and its properties
in Section 2.1. After excavating to 3 m depth, the first level of props are given in Leung et al. (2000). Under a confining pressure of between
is installed at 1 m below the ground surface. 50 and 100 kPa, the internal friction angle is about 43°. The unit weight
(g) Step 6: Repeat step 6 to excavate the next stages and install props and relative density of the sand were measured to be 15.78 kN/m3 and
until the last stage of excavation (i.e., He = 12 m) is completed. 90%, respectively. Based on sand type (quartz sand) and relative den-
sity, the calculated angel of dilation is 12° (Bolton and Powrie, 1986).
In back-analysis, the numerical modelling procedure is the same as
3. Validation of numerical modelling against centrifuge test those modelled in the centrifuge tests. Details are summarised as fol-
results lows:
As discussed in Section 2.1, the constitutive (hypoplastic clay) 1. Set up the initial boundary and initial effective stress conditions
model parameters were calibrated with laboratory test results. To jus- with Ko = 0.5) at 1 g;
tify the calibration of soil model and its parameters, a back-analysis of a 2. Activate pile and diaphragm wall modelled as “wished-in-place”;
centrifuge test (performed by Ong et al., 2006) were carried out. The 3. Apply hydrostatic pressure due to ZnCl2 solution on the wall and
computed results from the back-analysis have been validated against formation level.
measured results in the centrifuge test. 4. Increase stress level of the entire mesh (including soil, pile and
diaphragm wall) by raising its gravitational acceleration from 1g to
3.1. Configuration and procedure of centrifuge test 50g;
5. Excavation was modelled by releasing ZnCl2 solution pressure.
Ong et al. (2006) carried out a centrifuge test to investigate the
responses of a single pile to adjacent excavation with stable wall in 3.3. Comparison of computed and measured results
Kaolin clay. The test was carried out at a centrifugal acceleration of 50g
on the National University of Singapore geotechnical centrifuge. Fig. 4(a) shows the comparison between measured and computed
Fig. 3(a) shows the configuration of the centrifuge model test. An ex- ground surface settlement trough developed on completion of the ex-
cavation of 1.2 m in the prototype was carried out adjacent to 600 mm cavation. The ground surface settlements are taken at an offset of 0.2dp
diameter (in prototype) concrete bored pile of Grade 35. The embedded from the pile (see inset of the figure). Both the ground surface settle-
depth of the pile was 12.5 m (in prototype) and rested on the bottom of ment (S) and the distance behind the wall in the transverse direction are
the box. The model wall was a single sheet of aluminium alloy with normalised by final excavation depth (He). It can be observed from the
thickness of 3 mm (having bending rigidity of 24 × 103 kN-m2/m). It is figure that the measured and computed settlement trough show rea-
approximately equivalent to an FSP-IIA sheet pile wall with dimension sonable agreement. A spandrel type of settlement trough was formed
of 400 mm × 120 mm × 9.2 mm (w × h × t) in prototype scale with behind the wall. This type of settlement trough is commonly observed
embedded depth of 8 m in terms of flexural rigidity by assuming that in non-propped excavation (Hsieh and Ou, 1998). The maximum set-
the Young’s modulus values of steel is 210 GPa. The excavation rate was tlement was computed as s/He = 8.0% at d/He = 0.67 (i.e., 0.8 m) be-
0.55 m/day. The excavation was simulated in-flight by darning away hind the wall. Owing to excavation release, the pile deflected towards
the ZnCl2 solution (having same unit weight as the clay) from latex the excavation.
membrane. The model was prepared and tested in plane strain Fig. 4(b) compares the measured and computed lateral displace-
strongbox. The strongbox was made of aluminium and had an internal ment along the pile length. The results from centrifuge and numerical
plane area of 540 mm by 200 mm (27 m by 10 m in prototype) and modelling revealed that the maximum pile deflection occurred at the
internal height of 470 mm (23.5 m in prototype). The clay layer was pile head. The magnitude of the maximum measured and computed pile
modelled using Kaolin powder. The Kaolin slurry was prepared at an deflection were 12.6 mm (2.1dp%) and 11.4 mm (11.4dp%), respec-
initial water content of 120% (about twice that of the liquid limit of tively. This is because of free head condition of the pile in the centrifuge
Kaolin). The slurry was placed in strongbox over a 120 mm (6 m in test. However, negligible pile deflection was observed at lower part (Z/
142
M.A. Soomro et al. Tunnelling and Underground Space Technology 86 (2019) 138–155
200 mm 340 mm
Excavation 24 mm
130 mm
Kaolin clay
470 mm
Single pile
Toyoura sand
120 mm
Retaining wall
540 mm
(a)
Diaphragm
Single pile
Fluid pressure wall
200 mm
250 mm
Fig. 3. Details of centrifuge test reported by Ong et al. (2006) (a) Elevation view (b) Finite element mesh.
Lp > 0.7) of the pile. The computed deflection profile showed good portion of the pile (0.6 < Z/Lp < 1.0). Comparing the computed
agreement with that of measured in centrifuge test. bending moment profile with measured; the computed bending mo-
Fig. 4(c) illustrates the comparison between measured and com- ment shows reasonably good agreement.
puted bending moment profile along the pile length due to excavation. These agreements in the surface settlement troughs pile deflection
Since the pile head was not constrained in centrifuge and numerical and bending moment profiles validate the hypoplastic model and model
modelling, zero bending moment was induced in the pile due to ex- parameters adopted in this study and gives confidence that the finite
cavation. However, the bending moment increases along the pile length element analyse has ability to predict reasonable accurate excavation-
with maximum bending moment of 87 kNm at Z/Lp = 0.6. With ex- induced effective stress and strain changes which resulted in ground
cavation depth of only 1.2 m, the bending moment decreases at lower movements and pile deflection.
143
M.A. Soomro et al. Tunnelling and Underground Space Technology 86 (2019) 138–155
Fig. 4. Measured and computed ground and pile response (a) surface settlement (b) pile deflection (c) induced bending moment in pile.
3.4. Determination of working load for the pile 24 h. Fig. 5 shows the computed load-settlement curve. A displacement-
based failure criterion (as given in Eq. (5)) given by Nget al. (2001) was
This parametric study aims at investigating the loaded single pile used to determine ultimate capacity of the pile.
responses to adjacent excavations with different formation level re-
lative to the pile length in soft clay. A numerical pile load test was 1 Ph Lp
δph,max ≅ 0.045d p +
carried out to compute bearing capacity of the pile. The load of 3 MN 2 Ap Ep (5)
(with increment of 0.27 MN) was applied on the pile over period of
where δph, max is the maximum pile head movement which defines the
144
M.A. Soomro et al. Tunnelling and Underground Space Technology 86 (2019) 138–155
3
Kaolin clay
5
He/Lp = 0.67
7
He/Lp = 1.00 He/Lp = 1.33
8
145
M.A. Soomro et al. Tunnelling and Underground Space Technology 86 (2019) 138–155
When the first stage was excavated, the upper part of the pile de-
flected more than the lower part of the pile. As excavation proceeds,
significant lateral displacement was induced in lower part of the pile. In
contrast, the upper part of the pile (i.e., near the head) displaced away
from the excavation. The substantial lateral displacement of the lower
part of the pile is due to further effective stress-release and soil move-
ment during excavation. On completion of excavation in case of He/
Lp = 0.67, the maximum deflection of 40 mm (5.0%dp) was induced at
the pile toe. Furthermore, the excavation-induced deflection results
reveal that the pile has rotated counter-clockwise about an axis per-
pendicular to the plane of the paper. The pivot point is approximately at
Z/Lp = 0.25. Similarly, the pile deflected towards the excavation due to
effective stress-release and soil flow in case of He/Lp = 1.00. By com-
paring the deflection due to third stage of the excavation (i.e., h = 9 m)
in case of He/Lp = 0.67 and He/Lp = 1.00, it is found that induced-de-
flection in later case is smaller (18%) than that of in former case. This is
because of the embedded depth of that wall which provides stiffness
effect in the clay. Similar to the pile responses in case of He/Lp = 0.67,
the pile rotated about the axis perpendicular to the plane of the paper in
case of He/Lp = 1.00. However, the pivot point shifted downward (i.e.,
Z/Lp = 0.34) in this case. A similar pile deflection profile during an
adjacent excavation of the pile was observed by Liyanapathirana and
Nishanthan (2016). The maximum deflection of the pile after the
Fig. 8. Pile settlement and sub surface settlements along the pile axis in cases
completion of the excavation was computed as 32 mm (4.0% dp) in case
(i.e. He/Lp = 0.67; He/Lp = 1.00 and He/Lp = 1.33). of He/Lp = 1.00.
The pile deflection induced due to excavation in case of He/
Lp = 1.33 was observed similar to that of in cases of He/Lp = 0.67 and
4.1.3. Excavation-induced pile settlement and free-field subsurface profile
He/Lp = 1.00 qualitatively. The magnitude of the maximum pile lateral
Fig. 8 shows the normalised pile and sub surface vertical settlement
displacement induced at the pile toe was 36 mm (4.5% dp). Moreover,
(Sp/dp) profile along the pile length after excavation in all three cases
the pivot point of the rotation about the axis perpendicular to the plane
(i.e., He/Lp = 0.67, He/Lp = 1.00 and He/Lp = 1.33).
of the paper shifted in downward direction ((i.e., Z/Lp = 0.4) as com-
It can be seen from the figure that sub surface settlement soil
pared to those of in cases of He/Lp = 0.67 and He/Lp = 1.00.
slightly decrease along the pile axis due to excavation in all the three
cases. Because of the uniform settlement due to excavation, the changes
4.1.5. Excavation-induced bending moment in the pile
in axial load distribution along the pile are insignificant (discussed in
Fig. 10 illustrates bending moment profile in pile on completion of
Section 4.1.7). However, the significant pile settlement induced during
excavation in all three cases (i.e., He/Lp = 0.67, He/Lp = 1.00 and He/
excavation in each case (discussed earlier). Korff et al. (2016) devel-
Lp = 1.33). The induced-bending moment is taken as positive if tensile
oped an analytical model relating axial pile deformation to the vertical
stress was induced along the pile shaft facing the excavation. Since
soil displacement resulting from the deep excavation and also suggests
there was no rigid constraint at the pile head (pile head was free to
ways to determine the pile response to lateral displacements. In their
move and rotate), no bending moment was induced at/near pile head in
approach nonlinear load transfer mechanisms depending on relative
all the three cases.
soil pile displacements as well as pile axial deformations/strains were
On completion of excavation with formation level at mid-depth of
modelled. It can be seen from the computed results that pile settlement
the pile (i.e., He/Lp = 0.67), negative bending moments were induced
is similar to the greenfield case at smaller working load. Thus Korff’s
along the entire pile. It implies that the tensile fibre is located on the
framework may be an efficient approach to assess the interaction of
face of pile opposite to excavation. The bending moment increased
deep excavations with isolated pile with a free head and a constant
linearly along the pile length with the maximum magnitude of 127 kNm
smaller head load. However, this could not be applicable for larger
at Z/Lp = 0.8 (i.e. above formation level). This is because the pile was
working loads (explained in Section 4.3.1). The surface settlement in-
subjected to lateral soil displacements towards the excavation due to
creases with increase of excavation depth. The maximum settlement of
total stress release.
3.3dp%, 5.0dp% and 6.34%dp% in case of He/Lp = 0.67, He/Lp = 1.00
In contrast to induced bending moment in case of He/Lp = 0.67,
and He/Lp = 1.33, respectively. On the other hand, the pile settlement
negative bending moment profile (i.e. tensile fibre in the pile shaft fa-
profile is uniform along its depth. This is because of higher stiffness of
cing the excavation) was established on completion of excavation in
concrete as comparative to soft soil.
cases of He/Lp = 1.00 and 1.33. The reason for this bending profile can
be attributed to the embedded depth of the wall which makes soil
4.1.4. Excavation-induced lateral pile displacement displacement milder than that of in case of He/Lp = 0.67. The maximum
Fig. 9(a), (b) and (c) show lateral pile displacement induced during bending moment of 42 kNm and 13 kNm at Z/Lp = 0.7 were induced in
different excavation stages in case of He/Lp = 0.67, He/Lp = 1.00 and the pile in case of He/Lp = 1.00 and 1.33, respectively.
He/Lp = 1.33, respectively. The excavation stages (h = 6, 9 and 12 m), It can be seen that the maximum induced bending moment at the
(h = 9, 12 and 18 m) and (h = 12, 18 and 24 m) are chosen for dis- end of excavation in all the three cases is much less than the pile
cussion and comparison in case of He/Lp = 0.67, He/Lp = 1.00 and He/ bending moment capacity (i.e., 800 kNm). Therefore, the most critical
Lp = 1.33, respectively. The positive values mean that pile deflected issue to be considered in excavation-soil-pile problem is relatively large
towards excavation. settlement and lateral displacement of the pile. However, lateral pile
It can be seen from the figure that as excavation was carried out, the movement is dependent on the pile head boundary conditions (dis-
pile deflected towards excavation in all the three cases. This is because cussed in Section 4.2). This conclusion may not be applicable to sce-
of excavation-induced effective stress release and soil displacement narios in which the ground conditions or stiffness of excavation system
towards excavation. (i.e., wall and prop stiffness) are different from those adopted in this
146
M.A. Soomro et al. Tunnelling and Underground Space Technology 86 (2019) 138–155
Fig. 9. Lateral pile displacement at different excavation stages (a) He/Lp = 0.67; (b) He/Lp = 1.00 and (c) He/Lp = 1.33.
study. (before excavation) is included. Before the excavation in each case, the
pile shaft and pile toe shared 65% and 35% of the working load (i.e.,
4.1.6. Changes in axial load distribution 720 kN), respectively. It can be seen from the figure that on the com-
Fig. 11 shows the axial load distribution along the normalised pile pletion of the excavation, no any significant changes in axial load dis-
length (i.e., Z/Lp) below the ground surface after excavation in the three tribution was computed along the entire pile length in each case. This is
cases (i.e., He/Lp = 0.67, He/Lp = 1.00 and He/Lp = 1.33). For re- because of uniform soil displacement along the entire pile length (see
ference, axial load distribution after application of the working load Fig. 8) and insignificant changes in normal effective stresses to the pile
147
M.A. Soomro et al. Tunnelling and Underground Space Technology 86 (2019) 138–155
Fig. 10. Induced bending moment due to excavation. Fig. 12. Relative pile-soil displacement before and after the excavation all the
three cases.
Fig. 11. Axial load distribution along the pile length before and after the ex-
cavation in all the three cases. Fig. 13. Changes in normal effective stress on the pile due to excavation in all
the three cases.
148
M.A. Soomro et al. Tunnelling and Underground Space Technology 86 (2019) 138–155
Fig. 14. Computed evolution of stress paths of elements near the pile shaft and underneath the pile toe during excavation in all the three cases.
In contrast to the case of He/Lp = 0.67, the axial load increased lower part of the pile. Consequently, the mobilised shaft resistance
along the entire pile length due to excavation-induced ground move- decreased along the upper part and increased at the lower part of the
ments due to total stress release in both cases of He/Lp = 1.00 and 1.33. pile as discussed in pervious section. Among the three cases, the de-
This led to reduction in the mobilised shaft resistance (suggested by veloped relative pile-soil shear displacement in cases He/Lp = 1.00 and
increased slope of axial load distribution) along the pile length. As a 1.33 is smaller than that of in case of He/Lp = 0.67. This is because of
result, the load borne by shaft resistance transferred to the pile toe. the soil displacements behind the wall (i.e., surrounding the pile) in-
Consequently, the pile settled to further mobilise end-bearing to duced due to excavation in case of He/Lp = 1.00 and He/Lp = 1.33 are
maintain equilibrium. The end-bearing to increased because of the larger than that in case of He/Lp = 0.67. Due to this reason, the mobi-
linearly decreasing distribution of free-field ground movements. The lised shaft resistance along the lower part of the pile is higher is case of
increase in end-bearings of the pile were 4% and 2% of the pre-ex- He/Lp = 0.67 as compared to that in cases He/Lp = 1.00 and 1.33.
cavation value in cases of He/Lp = 1.00 and 1.33, respectively.
4.1.8. Changes in normal effective stresses to the pile shaft after excavation
4.1.7. Development of relative pile-soil displacement due to excavation It is well recognised that the mobilised shaft resistance depends
To understand the load, transfer mechanism (as discussed in per- upon coefficient of friction (i.e., tangent of friction angle between pile
vious section) caused by excavation in all the three cases (i.e., He/ and soil at interface), the normal effective stresses to the pile shaft and
Lp = 0.67, He/Lp = 1.00 and He/Lp = 1.33), relative pile-soil displace- relative pile-soil displacement. To substantiate the discussion in per-
ment at the piles-soil interface along the pile length is illustrated in vious section, the normal effective stresses to the pile shaft was ex-
Fig. 12. The relative shear displacement before excavation (due to tracted from the numerical analysis of all the three cases (i.e., He/
working load) is also included for reference. A positive value of pile-soil Lp = 0.67, He/Lp = 1.00 and He/Lp = 1.33) as shown Fig. 13. Three
relative displacement indicated that the soil is supporting the pile and references lines (i.e., earth pressure at rest (Ko), Rankine active (Ka) and
vice versa. As expected, the positive relative pile-soil displacement was passive (Kp) pressures) are included in the figure for comparison. Before
developed along the entire pile length after the application of the excavation (after application of working load) the effective stress dis-
working load (i.e., before excavation). This implies that positive shaft tribution along the pile shaft is was approximately equal to earth
resistance was mobilised at the interface (see Fig. 11). Nevertheless, the pressure distribution at Ko condition.
excavation-induced effective stress release led to changes in the relative It can be seen from the figure that the normal effective stresses to
shear displacement (of insignificant magnitude) in each case. The soil the pile shaft decreased along the pile length except near the pile toe
displacement along the entire pile length is almost uniform which led to (Z/Lp > 0.87) on completion of the excavation in case of He/Lp = 0.67.
substantial pile settlement (see Fig. 7) in all the three cases. Conse- Consequently, shaft resistance reduced at the upper part of the pile (as
quently, insignificant relative pile-soil shear displacement was devel- discussed in Section 4.1.6). As a result, pile settled with respect to the
oped due to excavation in each case. free-field case to further mobilise shaft resistance. These computed re-
Owing to soil displacement due to excavation in each case, the shear sults are consistent with the centrifuge tests results reported by Lee and
displacement decreased along the upper part of the pile (i.e., Z/ Chiang (2007), Franza and Marshall (2018) and Franza and Marshall
Lp < 0.35). Conversely, the relative displacement increased at the (2017). They discussed the impact of excavation induced effective stress
149
M.A. Soomro et al. Tunnelling and Underground Space Technology 86 (2019) 138–155
4.1.9. Stress path evolution of elements underneath the pile toe and at the
mid-depth of the pile shaft
To further understand the load transfer mechanism in the pile due to
excavation, two elements (one underneath the pile toe and the other at
the mid-depth of the pile shaft) were selected for comparing the evo-
lution of stress path during excavation in case of He/Lp = 0.67, He/
Lp = 1.00 and He/Lp = 1.33 as illustrated in Fig. 14. For reference, at-
rest earth pressure coefficient (i.e., Ko) line and critical state line (i.e., M
line) are also included in the figure. It can be seen that the initial stress
states of selected elements are on Ko line which means the element is
subjected to Ko stress condition in each of cases. After application of
working load in each case, the mean effective stress (p') and deviatoric
stress (q) of the elements underneath the pile toe increased. The p' and q
further increased after consolidation in each cases. It can be observed
from the figure that the p' and q increased due to first two excavation
stages (i.e., E1 and E2) in case of He/Lp = 0.67. This implies that load
transferred to the pile toe. This is because of reduction in shaft re-
sistance of the pile during the excavation stages. However, both the p'
and q decreased at the end of excavation, suggesting that end-bearing
reduced (see Fig. 11) and pile had to mobilise its shaft resistance to
carry constant applied working load.
In contrast to the stress path in case of He/Lp = 0.67, the p' and q
keep increasing during entire excavation process in both the cases of
He/Lp = 1.00 and 1.33. This is because of embedded depth of the wall
which providing support to soil element underneath the pile toe.
Consequently, the end-bearing of the pile increased (see Fig. 11) in both
the cases. At the end of the excavation in each case the stress state of the
selected element remained above and below the Ko line and M line,
respectively.
The p' and q of element at the mid-depth of the pile shaft decreased
after application working load and consolidation. Owing to excavation-
induced stress release the mean effective stress (p') of the element de-
creased in each case. However, the deviatoric stress (q) increased
during excavation. This can be because of mobilisation of shaft re-
sistance to carry constant applied working load.
150
M.A. Soomro et al. Tunnelling and Underground Space Technology 86 (2019) 138–155
Fig. 16. Effect of pile head fixity on lateral pile displacement (a) He/Lp = 0.67; (b) He/Lp = 1.00 and (c) He/Lp = 1.33.
4.2. Effect of pile head fixity case of pinned and fixed head conditions was observed to zero at the
ground surface in all the three cases as expected. Moreover, the in-
Fig. 16(a) (b) and (c) compare induced lateral displacement of the duced-pile deflection profile along the pile length in cases of pinned and
pile with different head conditions (i.e. free, pinned and fixed) in case fixed head conditions are similar in all the three cases. During the ex-
of He/Lp = 0.67, He/Lp = 1.00 and He/Lp = 1.33, respectively. The ex- cavation, the pile deflection increased along the depth with maximum
cavation stages (h = 6 and 12 m), (h = 9 and 18 m) and (h = 12 and value at pile toe. Compared to the lateral pile displacement in case of
24 m) are selected for discussion and comparison in case of He/ free head condition, the deflection at the upper portion of pile is smaller
Lp = 0.67, He/Lp = 1.00 and He/Lp = 1.33, respectively. The pile de- in case of pinned and fixed condition.
flection toward the excavation is regarded as positive. Fig. 17(a) (b) and (c) illustrate the comparison between induced
It can be seen from the figure that the pile lateral displacement in bending moment profile in the pile with different pile head conditions
151
M.A. Soomro et al. Tunnelling and Underground Space Technology 86 (2019) 138–155
Fig. 17. Induced bending moment at different excavation depth (a) He/Lp = 0.67; (b) He/Lp = 1.00 and (c) He/Lp = 1.33.
on completion of excavation in all three cases (i.e., He/Lp = 0.67, He/ portion of the pile in constraint head conditions. In contrast only po-
Lp = 1.00 and He/Lp = 1.33). The induced-bending moment is taken as sitive bending moment is induced in the free head pile. The negative
positive if tensile fibre faces towards excavation. bending moment at pile head in constrained conditions increases as
It can be seen that the induced bending moment profiles in the pile excavation depth increases. Among the three cases reported, the ex-
with retrained head conditions are quite different from that in free pile cavation in case He/Lp = 1.33 induced the largest bending moment of
head condition in all the cases. Due to head constraint higher negative 480 kNm at the pile head which is 60% of the pile bending moment
bending moment was induced at pile head in all the three cases. As capacity (i.e., 800 kNm, as discussed in Section 2) with corresponding
excavation depth increase positive bending moment is induced at lower flexural rigidity. The maximum negative bending moment of 375 and
152
M.A. Soomro et al. Tunnelling and Underground Space Technology 86 (2019) 138–155
Fig. 20. Effect of different working loads on axial load distribution along the
pile length before and after the excavation in case of He/Lp = 1.33.
Fig. 19. Effect of different working loads on induced bending moment along
the pile length. Fig. 21. Pile settlement in case of FOS = 1.5 and sub surface settlements along
the pile axis in all the cases (i.e. He/Lp = 0.67; He/Lp = 1.00 and He/Lp = 1.33).
480 kNm at the pile head was induced in case of He/Lp = 0.67 and He/
Lp = 1.00, respectively. along the pile shaft and underneath the pile toe due to higher working
load (i.e. low factor of safety). As Korff et al., (2016) method analyti-
cally suggests, the greater the pile head settlements, the lower the
4.3. Effect of working load tangent soil stiffness at the shaft and pile tip for further relative pile-soil
displacements. Therefore, in undrained conditions a pile with a lower
4.3.1. Excavation-induced settlement of the pile safety factor before the excavation has a very low stiffness for further
Fig. 18 shows the normalised incremental settlement of the pile (Sp/ variation of load applied at its head for shaft. This is the reason for a
dp) at different working load (i.e. 720 kN and 1440 kN) in all three cases pile with low safety factor pile can settle significantly more than the
(i.e., He/Lp = 0.67, He/Lp = 1.00 and He/Lp = 1.33). The long-term pile greenfield ground movement (explained in Section 4.3.4) as the pile
settlement (i.e., 10 years after completion of excavation) is also in- soil-stiffness is low. From a soil mechanisms perspective, the deep ex-
cluded in the figure. cavation induced pile settlement in undrained conditions is not due to a
It can be seen from the figure that higher the working load on the “bulb stress” rather the shear stresses/strains at the pile-soil interface
pile, the larger is the induced settlement in the pile at same excavation (i.e. refer to shear stiffness degradation curves from the G0 level).
depth. This can be attributed to degradation of the tangent soil stiffness It can be seen that settlement of the pile increased in the long term
153
M.A. Soomro et al. Tunnelling and Underground Space Technology 86 (2019) 138–155
Fig. 22. Evolution of stress paths of elements near the shaft and underneath the toe of the pile subjected to different working loads during excavation.
(i.e., 10 years after completion the excavation) in all cases. This addi- displacement along the pile length.
tional pile settlement is attributed to the dissipation of excessive pore
pressure generated around the pile due to excavation. The maximum 4.3.4. Excavation-induced pile settlement and free-field subsurface profile
increment in the pile settlement (35% of the settlement after excava- Fig. 21 shows the normalised pile (subjected working load with
tion) was observed in the case of He/Lp = 1.33 with factor of safety 1.5. FOS = 1.5) and sub surface vertical settlement (Sp/dp) profile along the
pile length after excavation in all three cases (i.e., He/Lp = 0.67, He/
4.3.2. Excavation-induced bending moment Lp = 1.00 and He/Lp = 1.33).
Fig. 19 illustrates bending moment profile in pile at different It can be seen from the figure that sub surface settlement soil
working loads after excavation in all three cases (i.e., He/Lp = 0.67, He/ slightly decrease along the pile axis due to excavation in all the three
Lp = 1.00 and He/Lp = 1.33). The induced-bending moment is taken as cases. Because of the uniform settlement due to excavation, the changes
positive if tensile stress was induced along the pile shaft facing the in axial load distribution along the pile are insignificant (discussed in
excavation. Since there was no rigid constraint at the pile head (pile Section 4.3.3). However, the significant pile settlement induced during
head was free to move and rotate), no bending moment was induced at/ excavation in each case (discussed earlier). Moreover, the settlement of
near pile head in all the three cases. It can be seen that minor influence the pile subjected to working load with FOS = 1.5 is significantly
on excavation-induced bending moment profile in the pile was ob- higher than the subsurface settlement in free-field case. Thus Korff’s
served due to different working load (i.e. FOS = 3.0 and 1.5). The si- framework may be an efficient approach to assess the interaction of
milar observation was made by Zhang et al. (2011), Liyanapathirana deep excavations with isolated pile with a free head and a constant
and Nishanthan (2016) and Zhang et al. (2018). smaller head load (see Fig. 8). However, this could not be applicable for
larger working loads.
4.3.3. Changes in axial load distribution
Fig. 20 compares the axial load distribution along the pile length for 4.3.5. Stress path evolution of elements at the mid-depth of the pile shaft
different working load (720 kN with FOS = 3.0 and 1440 with and underneath the pile toe
FOS = 1.5) in case of He/Lp = 1.33. For reference, axial load distribu- Fig. 22 compares the stress path evolution of the two elements (one
tion after application of the working load (before excavation) is in- underneath the pile toe and the other at the mid-depth of the pile shaft)
cluded. Before the excavation in each case, the working load was car- around the pile loaded with working load 720 (FOS = 3.0) and 1440 kN
ried by the pile by mobilising shaft and end-bearing resistance. The pile (FOS = 1.5) during excavation in case of He/Lp = 1.33. Comparing the
with working load of 1440 kN mobilised higher shaft and end-bearing stress path of element underneath the pile toe in case of FOS = 1.5, the
resistance than that with working load of 720 kN. increment in the p' and q is higher in case of FOS = 3.0. This is because
Similar to changes in load distribution along the pile subjected to of large load transferred (see Fig. 20) to the pile toe after application of
working load of 720 kN after the excavation, no any significant changes the working load and during excavation.
in axial load distribution was computed along the entire pile length in Qualitatively, the stress path evolution of the element at the mid-
each case. This is because of uniform soil displacement along the entire depth of the pile shaft during excavation is similar in both case of
pile length (see Fig. 21). This led to negligible relative pile-soil FOS = 3.0 and 1.5. The increment in deviatoric stress (q) in case of
154
M.A. Soomro et al. Tunnelling and Underground Space Technology 86 (2019) 138–155
FOS = 1.5 is higher than that in case of FOS = 3.0. This is because of Atkinson, J.H., Richardson, D., Stallebrass, S.E., 1990. Effect of recent stress history on
large excavation-induced settlement (see Fig. 18) to mobilise shaft re- the stiffness of overconsolidated soil. Géotechnique 40 (4), 531–540.
Atkinson, J.H., Sällfors, G., 1991. Experimental determination of stress-strain-time
sistance to carry constant applied working load in case of FOS = 1.5. characteristics in laboratory and in-situ tests. General report. In: Proceedings of 10th
European Conference on Soil Mechanics and Foundation Engineering, Florence, Italy,
5. Summary and conclusion Vol. 3, pp. 915–56.
Benz, T., 2007. Small-Strain Stiffness and Its Numerical Consequences. Ph.D. thesis.
UniversitatStuttgart.
This study compares the responses of a floating pile due to different Bolton, M.D., Powrie, W., 1987. The collapse of diaphragm walls retaining clay.
excavation depths systems in saturated soft Kaolin clay using 3D cou- Géotechnique 37 (3), 335–353.
Finno, R.J., Lawrence, S.A., Allawh, N.F., Harahap, I.S., 1991. Analysis of performance of
pled consolidation analysis. The effects of excavation depths relative to pile groups adjacent to deep excavation. J. Geotech. Geoenviron. Eng., ASCE 6 (117),
pile were investigated by simulating the excavation near the pile shaft 934–955.
(i.e., He/Lp = 0.67), next to (He/Lp = 1.00) and below the pile toe (He/ Franza, A., Marshall, A.M., 2017. Centrifuge modelling of tunnelling beneath axially
loaded displacement and non-displacement piles in sand. In: Brandon, T.L.,
Lp = 1.33). Based on ground conditions, different configurations and
Valentine, R.J. (Eds.) Proc. Geotech. Front. 2017. GSP 277 Transp. Facil. Struct. site
method of excavation modelled, the following conclusions can be Investig. Orlando, Florida, pp 576–586.
drawn Franza, A., Marshall, A.M., 2018. Centrifuge modeling study of the response of piled
structures to tunneling. J. Geotech. Geoenviron. Eng. 144, 04017109. https://doi.
org/10.1061/(ASCE)GT.1943-5606.0001751.
(a) Owing to different embedded depth of the wall in each of three Goh, A.T.C., Wong, K.S., Teh, C.I., Wen, D., 2003. Pile response adjacent to braced ex-
cases, the induced settlement (Sp), lateral displacement and bending cavation. J. Geotech. Geoenviron. Eng., ASCE. 4 (129), 383–386.
moment in the pile at the same stage of the excavation was different Gudehus, G., Amorosi, A., Gens, A., Herle, I., Kolymbas, D., Mašín, D., Wood, M., Nova,
R., Niemunis, A., Pastor, M., Tamagnini, C., Viggiani, G., 2008. The soilmodels.info
in the three cases. project. Int. J. Num. Anal. Methods Geomech. 32(12), 1571–1572.
(b) Significant effect of wall embedded depth was observed. For a given Hsieh, P.-G., Ou, C.-Y., 1998. Shape of ground surface settlement profiles caused by ex-
excavation depth, induced pile settlement in case of larger em- cavation. Can. Geotech. J. 35 (6), 1004–1017.
Hsiung, B.C.B., 2009. A case study on the behaviour of a deep excavation in sand.
bedded was smaller than that in cases of smaller embedded depth of Comput. Geotech. 36 (4), 665–675.
the wall. Owing to the dissipation of excess pore pressure after Jáky, J., 1944. The coefficient of earth pressure at rest. J. Soc. Hungarian Architects Eng.
10 years of completions of excavations, induced pile settlement 355–358 [In Hungarian].
Korff, M., Mair, R.J., Van Tol, F.A.F., 2016. Pile-soil interaction and settlement effects
increases in all cases. induced by deep excavations. J. Geotech. Geoenviron. Eng. 142 (8), 04016034.
(c) Owing to excavation, the bending moment was induced along the Lee, C.J., Ng, C.W.W., 2004. Development of downdrag on piles and pile groups in
pile length. At the end of excavation in each case, the maximum consolidating soil. J. Geotech. Geoenviron. Eng., ASCE 130 (2), 905–914.
Lee, C.J., Chiang, K.H., 2007. Responses of single piles to tunneling-induced soil move-
induced bending moment in all the three cases is much less than the
ments in sandy ground. Can. Geotech. J. 44, 1224–1241. https://doi.org/10.1139/
pile bending moment capacity (i.e., 800 kNm). T07-050.
(d) The pile head boundary conditions had significant effects on Leung, C.F., Chow, Y.K., Shen, R.F., 2000. Behavior of pile subject to excavation-induced
bending movement profile of the pile while impact on settlements soil movement. J. Geotech. Geoenviron. Eng., ASCE 126 (11), 947–954.
Leung, C.F., Lim, J.K., Shen, R.F., Chow, Y.K., 2003. Behavior of pile groups subject to
was minor. In particular, fixed pile head conditions led to very large excavation-induced soil movement. J. Geotech. Geoenviron. Eng., ASCE. 129 (1),
bending moments (60% of pile bending moment capacity). 58–65.
(e) On the contrary, the different working loads (with FOS = 3.0 and Leung, C.F., Ong, D.E.L., Shen, R.F., Chow, Y.K., 2006. Pile behavior due to excavation-
induced soil movement in clay II: collapsed wall. J. Geotech. Geoenviron. Eng., ASCE
1.5) influenced induced pile settlement significantly but have re- 132 (1), 45–53.
latively minor effect on induced bending moment. Liyanapathirana, D., Nishanthan, R., 2016. Influence of deep excavation induced ground
(f) The computed results have revealed that, the settlement of the pile movements on adjacent piles. Tunn. Undergr. Space Technol. 52, 168–181.
Li, L., Hu, X.X., Dong, G.H., Liu, J., 2014. Three-dimensional numerical analyses of pile
subjected to working load with FOS = 1.5 is significantly higher response due to braced excavation-induced lateral soil movement. Appl. Mech.
than the subsurface settlement in free-field case after excavation in Mater. 580–583, 524–531.
each case. Thus Korff’s framework may be an efficient approach to Mašín, D., Herle, I., 2005. State boundary surface of a hypoplastic model for clays.
Comput. Geotech. 32 (6), 400–410.
assess the interaction of deep excavations with isolated pile with a
Mašín, D., 2009. 3D modeling of an NATM tunnel in high K0 clay using two different
free head and a constant smaller head load. However, Korff ap- constitutive models. J. Geotech. Geoenviron. Eng. 135 (9), 1326–1335.
proach may provide unconservative estimation of pile settlements Ng, C.W.W., Simpson, B., Lings, M.L., Nash, D.F.T., 1998. Numerical analysis of a mul-
tipropped excavation in stiff clay. Can. Geotech. J. 35, 115–130.
for low pile safety factor.
Ng, C.W.W., Yau, T.L.Y., Li, J.H.M., Tang, W.H., 2001. New failure load criterion for large
(g) On the completion of the excavation, no any significant changes in diameter bored piles in weathered geomaterials. J. Geotech. Geoenviron. Eng., ASCE
axial load distribution and relative pile-soil displacement were 127 (6), 488–498.
computed along the entire pile length in each case. This is because Ng, C.W.W., Hong, Y., Liu, G., Liu, T., 2012. Ground deformations and soil structure
interaction of a multi-propped excavation in Shanghai soft clays. Géotechnique 62
of uniform soil displacement along the entire pile length and minor (10), 907–921.
changes in normal effective stresses to the pile shaft. Ng, C.W.W., Wei, J., Poulos, H.G., Liu, H., 2017. Effects of multipropped excavation on an
adjacent floating pile. J. Geotech. Geoenviron. Eng. 143 (7), 04017021.
Niemunis, A., Herle, I., 1997. Hypoplastic model for cohesionless soils with elastic strain
Readers should be reminded that the above conclusions are drawn range. Mech. Cohesive-Frict. Mater 2, 279–299.
from this parametric study in one soft layer of clay. Any extrapolation Ong, D.E.L., Leung, C.F., Chow, Y.K., 2006. Pile behavior due to excavation-induced soil
from these results should be treated with caution. movement in clay. I: Stable Wall. J. Geotech. Geoenviron. Eng., ASCE 132 (1), 36–44.
Parry, R.H.G., Nadarajah, V., 1974. Observations on laboratory prepared, lightly over-
consolidated specimens of kaolin. Géotechnique. 24 (3), 345–358.
Acknowledgements Poulos, H.G., Chen, L.T., 1997. Pileresponse due to excavation-induced lateral soil
movement. J. Geotech. Geoenviron. Eng. 123 (2), 94–99.
Shakeel, M., Ng, C.W.W., 2018. Settlement and load transfer mechanism of a pile group
The authors would like to acknowledge the financial support pro-
adjacent to a deep excavation in soft clay. Comput. Geotech. 96, 55–72.
vided by Quaid-e-Awam University of Engineering, Science & Wang, L.Z., Chen, K.X., Hong, Y., Ng, C.W.W., 2015. Effect of consolidation on responses
Technology, Sindh and Pakistan. of a single pile subjected to lateral soil movement. Can. Geotech. J. 52 (6), 769–782.
Zhang, R., Zheng, J., Pu, H., Zhang, L., 2011. Analysis of excavation-induced responses of
loaded pile foundations considering unloading effect. Tunn. Undergr. Space Technol.
References 26 (2), 320–335.
Zhang, R., Zhang, W., Goh, A.T.C., 2018. Numerical investigation of pile responses caused
Al-Tabbaa, A., 1987. Permeability and stress–strain response of Speswhite Kaolin. Ph.D. by adjacent braced excavation in soft clays. Int. J. Geotech. Eng. 10 (5), 856–864.
thesis. University of Cambridge, U.K.
155