MONTHLY REPORT - APRIL 2021

Status of Civil Engineering Head Office Activities and Task

Activities and Task Status at the end of Remarks


April 2021
Certification of Rekomtek Pengusahaan SDA: Completed Received on 01 March 2021

Certification of SIPA:
Documents Preparation & Submission Completed Submitted on 15 March 2021 and verified
SIPA Issuance
Subdit Wilayah 1 Verification 1. TNKS area is verified
2. IUPTL document submitted
3. Project S-Curve submitted
Subdit Perencanaan Teknis & Kelembagaan Not started Waiting for Subdit Wilayah 1
Bagian Hukum dan Komunikasi Publik Not started Waiting for Subdit Perencanaan Teknis & Kelembagaan
Direktorat Bina Operasi dan Pemeliharaan Not started Waiting for Bagian Hukum dan Komunikasi Publik
Sekretariat Direktorat Jenderal SDA Not started Waiting for Direktorat Bina Operasi dan Pemeliharaan
Direktorat Jenderal SDA Not started Waiting for Sekretariat Direktorat Jenderal SDA
Certification of Dam Design/Construction:
Diskusi Teknis 1 Completed
Diskusi Teknis 2 Completed
Documents Preparation & Submission Completed
Sidang Teknis 1 Completed
Followup Report Preparation & Submission
General Completed
Dam Design On progress 1. Dynamic analysis with SEE 10.000 years is COMPLETED.
2. Dam Break Analysis is COMPLETED.
3. Secant pile wall selection due to geological condition is
COMPLETED.
4. Comparison of secant pile wall with other structures is
COMPLETED.
5. Thermal analysis is waiting for curing box test. the data result
from first trial is received but has some errors on temperature
reading.

5/1/2021 | Page 1 of 7
MONTHLY REPORT - APRIL 2021
Status of Civil Engineering Head Office Activities and Task

Activities and Task Status at the end of Remarks


April 2021
Hydrology On progress 1. Technical discussion on 3-4 May in Bandung with Bu Wanny,
included:
a. Verification of Flood analysis using TRMM data.
b. Calculation hourly rainfall distribution pattern.
c. Calibration of flood data design compare to AWLR data.
d. Calibration of TRMM & AWLR data for low flow analysis.
e. Calibration fluctuation inflow 1977-1989 using Baseflow to
generate fluctuation inflow 1999-2017
2. The 8 m3/s duty flow should be approved by the DLH.
Environment team to get the approval.
Geology & Geology Technic On progress 1. Site investigation & document preparation is on progress.
2. Updating geological drawings is on progress.
3. Due to social issues, bore hole investigation at RW is on HOLD,
The investigation is replace with Geolistrik.
Diversion Tunnel On progress 1. As built drawings received.
2. Back analysis on 350mm lining thickness is COMPLETED.
3. Primary cofferdam design is COMPLETED.
4. Upstream cofferdam design is COMPLETED.
5. Downstream cofferdam design is COMPLETED.
Cofferdam (Primary Cofferdam, Upstream Cofferdam, Downstream On progress 1. Calculation is COMPLETED.
Cofferdam) 2. Drawings is COMPLETED.
3. Additional site investigation is on progress.
Construction Material Completed
Instrumentation On progress NC to update instrumentation drawings
Hydromechanical Completed Technical discussion was held on 22 April 2021 with Pak Ketut
Suryata.
Sidang Teknis Lanjutan Not started
Sidang Pleno Not started

5/1/2021 | Page 2 of 7
MONTHLY REPORT - APRIL 2021
Status of Civil Engineering Head Office Activities and Task

Activities and Task Status at the end of Remarks


April 2021
Permit of Road Relocation
Design Approval
Diskusi Teknis 1 Completed
Diskusi Teknis 2 Completed
Join Survey Completed
Diskusi Teknis 3 Completed 16 Oktober 2020
Diskusi Teknis 4 Completed 23 Oktober 2020
Diskusi Teknis 5 Completed 26 Oktober 2020
Design Expose Completed 20 November 2020
Document Preparation & Submisson for Design Aoproval Completed Design approved on 27 November 2020
Uji Laik Fungsi Jalan Not started Waiting for construction to complete
Serah Terima Aset Not started
Detail Design of Diversion Tunnel:
Calculation & Design Report
Drawings
Diversion Tunnel Concrete Lining Completed - IFC The fabrication drawings to be prepared by site engineer
Inlet Structure Diversion Tunnel Excavation Completed - IFC
Inlet Structure Diversion Tunnel Concrete Arrangement Completed - IFC
Inlet Structure Diversion Tunnel Embedded Part Completed - IFC
Inlet Structure Diversion Tunnel Reinforcement Arrangement Completed - IFC
Inlet Structure Diversion Tunnel Bar Bending Schedule The fabrication drawings to be prepared by site engineer
Outlet Structure Diversion Tunnel Excavation Not started
Outlet Structure Diversion Tunnel Concrete Outline Arrangement Completed - IFC
Outlet Structure Diversion Tunnel Reinforcement Arrangement Completed - IFC
Outlet Structure Diversion Tunnel Bar Bending Schedule The fabrication drawings to be prepared by site engineer
Plugging Grout Curtain Completed - IFC
Plugging Concrete Outline Issued for Approval Rev B
Plugging Reinforcement Not started
Plugging Bar Bending Schedule Not started

5/1/2021 | Page 3 of 7
MONTHLY REPORT - APRIL 2021
Status of Civil Engineering Head Office Activities and Task

Activities and Task Status at the end of Remarks


April 2021
Detail Design of Intake Dam :
Calculation & Design Report
Main Report Issued for Approval
Detail Design Criteria Issued for Approval
Excavation Slope Stability Design Issued for Approval
Secant Pile Wall Geotechnical Excavation Issued for Approval
Secant Pile Wall Structural Calculation Issued for Approval
Hydraulic Calculation Issued for Approval
CFD Simulation Report Issued for Approval
Stability and Stress Analysis Dam Issued for Approval
Power Intake Stability Analysis Issued for Approval
Drawings
Dam 3D Visualization Issued for Approval
Dam General Arrangement Plan & Elevation Issued for Approval
Dam Spillway General Arrangement Plan and Section Issued for Approval
Dam Low Level Outlet General Arrangement Plan and Section Issued for Approval
Dam Debris Flushing General Arrangement Plan and Section Issued for Approval
Dam Environmental Flow & Fish Trap Facility GA Plan and Section Issued for Approval
Dam Instrumentation General Arrangement Plan and Section Issued for Approval
Dam Geological Investigation Drawings Issued for Approval
Dam and Intake Setting Out Main Axis Completed - IFC
Dam and Intake Excavation Plan, Section & Support Detail Completed - IFC
Intake General Arrangement Plan and Section Issued for Approval
Intake Concrete Outline On progress
Intake Reinforcement & BBS On progress
Specification Issued for Approval
Bill of Quantity Issued for Approval

5/1/2021 | Page 4 of 7
MONTHLY REPORT - APRIL 2021
Status of Civil Engineering Head Office Activities and Task

Activities and Task Status at the end of Remarks


April 2021
Detail Design of Waterway:
Calculation & Design Report
Tunnel Rock Support Design Completed - IFU
Waterway Components & ACSC Completed - IFU
Additional Site Investigation Completed - IFU
Headrace Tunnel Concrete Lining Structural Design Completed - IFU
Adit 1 Concrete Plug, Structural Calculation Issued for Approval
Adit 2 Concrete Plug, Structural Calculation Issued for Approval
Transition from Concrete Line to Steel Lined Design Issued for Comment
Drawings
Headrace Tunnel Typical Rock Support Completed - IFC
Headrace Tunnel Concrete Lining Various Thickness - Cross Section Completed - IFC
Headrace Tunnel from Intake to CH+435 - Concrete Lining Completed - IFC
Headrace Tunnel from Intake to CH+435 - Reinfrocement & BBS Completed - IFC
Headrace Tunnel Grout Curtain at CH+435 On Progress Awaiting for Wall Pore Pressure Investigation Result at :
CH+455, CH+615
Headrace Tunnel from CH+435 to Adit 1 (CH+537) - Concrete Lining, On Progress Awaiting for Wall Pore Pressure Investigation Result at :
Reinforcement & BBS CH+455, CH+615
Headrace Tunnel from Adit 1 (CH+537) to CH+2100 - Concrete Lining, On Progress Awaiting for Wall Pore Pressure Investigation Result at :
Reinforcement & BBS CH+775, CH+1215, CH+1915
Detail design of Steel Penstock Adit-3 to End Portal Not started Planned date on 24-09-2021
Detail design of Bifurcation Not started Planned date on 12-01-2022
Detail Design of ACSC (Riser, elbow, manifold and ACSC) Not started Air cushion steel pipe assembly drawing planned date 19-05-2021
Vertical Shaft Assembly drawing planned date 30-07-2021
Vertical Bend/Transition section & Manifold assembly drawing
planned date 30-09-2021

5/1/2021 | Page 5 of 7
MONTHLY REPORT - APRIL 2021
Status of Civil Engineering Head Office Activities and Task

Activities and Task Status at the end of Remarks


April 2021
Detail Design of Anchor Block of Penstock Bifurcation:
Calculation & Design Report
Drawings
Anchor block design Not started the design will be submitted 3 weeks once the information from ME
is received
Bored pile layout Not started the design will be submitted 3 weeks once the information from ME
is received
Detail Design of Powerhouse:
Calculation & Design Report
Drawings
Excavation Drawing of hill side:
Excavation Stage 1 - Powerhouse/Tailrace above El.336 (Soil Nailling) Completed - IFC
Excavation Stage 2 - Powerhouse/Tailrace below El.336 (Anchored Secant On progress Anchored secant pile wall calculation needs to be reviewed by
Pile Wall) senior geotechnical engineer.
Excavation Stage 3 - Manifold Bifurcation Not started
Secant pile layout of river side Not started
Curtain grouting of river side Not started
Power house civil outline Issued for Approval
Power house steel roof structure Issued for Approval
Power house concrete structure Issued for Approval
Power house concrete reinforcement Not started
Power house inspection bridge Not started
Power house gantry Not started
Power house control room Not started
Detail Design of Tail Race:
Calculation & Design Report
Tailrace structural calculation Completed - IFU
Recommendation for handling landslide on the excavation slope of the Completed - IFU Responding site request
tailrace
Dissipation chamber structural calculation Issued for Approval Rev A

5/1/2021 | Page 6 of 7
MONTHLY REPORT - APRIL 2021
Status of Civil Engineering Head Office Activities and Task

Activities and Task Status at the end of Remarks


April 2021
Drawings
Tailrace concrete outline & reinforcement Completed - IFC
Dissipation Chamber concrete outline & reinforcement On progress