You are on page 1of 1

- C1 Submitted Dakin as alternative FCU on 24 Dec 21 and replied by consultant on 4 Jan 21.

- C1 Submitted the shop drawings for HVAC layouts on 30 Dec 21.


- Consultant requested to update the load calculations on 04 Jan 21.
- C1 requested for base build HAP files with related zoning layouts on 05 Jan 21.
- Received Base build HAP files from consultant on 10 Jan 21 and zoning layouts on 14 th Jan 21.
- HAP Calculations and Zoning layouts approved for all floors by 08 Mar 21.
- C1 Submitted Petra as alternative FCU on 15 Feb 21.
- R00 : Submission rejected. Kindly provide compliance to original specification/reason for
change etc. 15 Feb 21.
- R01 : Chapman replied on correct submittal on 21 Feb 21. “ The Proposed brand is not in
vendor list and does not comply with some of the specification requirements. C1 replied to
clarify there comment as the compliance was already attached.
- R02 : Chapman provided with comments on compliance sheet on 28 Mar 21.
- R03 : Approved on 09 Mar 21.
- After Revisions and factory visit accompanied by HCO, Petra as a brand have been approved by
chapman on 09 March 21.
- C1 Submitted FCU Selection and static pressure calculations on 20 March 21.
- After revisions FCU selection and static pressure calculations approved on 31 March 21.
- HVAC Air conditioning layouts approved by 15 April 21 for all floors.

You might also like