PROJECT: VIJAY RAJA EXURB Date :

Batching Slip for concrete QTY Pour Start Time :

QUALITY MANAGEMENT SYSTEM Pour End Time :

CHECKLIST FOR MIXER MACHINE


Document No: ,001 Location / Structure
Building: Grade of Concrete M30
Poured Concrete Qty (Bag):
Area / Grid Line: 1.83cum
(Actual)
No.of Batch (1/2 Bag): 15.00

No of Cube taken = nos Total Consumption

S.No Description Unit Qty/Bag Material Consumption (Kg) Remarks

1 Cement (kg) Kg 25.00 375

2 Fly Ash (Kg) Kg 25.00 375

3 Sand Cft 2.34 35.10

4 20mm Metal Cft 1.89 28.35

5 12mm Metal Cft 1.33 19.95

6 Admixtures litre 0.15 2.25

7 Water litre 21.46 322