For more information Build the hierarchy After you set up an EPS, you can define
about security profiles, see
the Administrator’s Guide.
additional data about each EPS node, such as anticipated dates, budgets,
and spending plans. Use the Project Details to specify this information,
as described later in this chapter. Or, you can begin adding projects
under the applicable nodes in the structure if you have access rights to
these functions. Access rights are set by your network or database
administrator.
While resources typically work on several projects, each project has its
own resource assignments. Similarly, while calendars, reports, and
activity codes may span all projects, they may also be project specific.
You can also use the Use the Projects window to add a project to the EPS hierarchy. Define
Project Architect wizard to
general information such as the project’s ID and name, planned start and
create new projects. See
“Using Project Architect” must finish by dates, and the responsible manager.
on page 79.
Click Add. The Create a New Project Wizard guides you through the
steps required to add a project, including selecting the node in which to
place the project in the EPS, naming the project, and identifying the
responsible manager for the project.
For more information Import projects You may want to build your EPS using projects
about importing and
previously created in an earlier version of the Project Management
converting projects, see
the Administrator’s Guide. module, Microsoft Project, or Primavera Project Planner 3.0 (P3). The
Import Wizard prompts you to specify the information to be imported
and where the project should be placed in the current EPS hierarchy.
For more information on In addition to providing access to methodologies, Project Architect also
using methodologies, see
contains a bottom-up estimation feature that allows you to estimate
the Methodology
Management Reference resource units and costs for your methodology selections. Project
Manual. Architect bases this estimate on the project complexity value that you
specify during the architect process. This enables you to estimate work
effort and cost before adding a project.
You can also access the Start Project Architect Wizard Choose File, New to start the
Project Architect wizard Create a New Project wizard. Select the EPS level in which to place the
from the File menu. Use new project. Name the project and specify a start date.
this option to incorporate
methodologies into the Select a responsible manager. Depending on the choices you make when
current project.
you run the Project Architect, the OBS element you select here will
appear at the top of the new project’s OBS.
Choose the default rate type. Then choose Yes and run the Project
Architect.
The options that you select Select methodologies and estimate project complexity Click
in Project Architect for the Select Base Methodology or Plug-in Methodology to select the
Responsible Manager and methodology you want to import. Click Next to select the Base or Plug-
default rate may override in Methodology you want to import. Click Next and type a value for the
the selections you choose project complexity, or click the Size and Complexity Wizard button to
in the New Project wizard.
calculate a value for the project complexity. The module uses the project
complexity percentage to calculate a value between the low and high
estimated values defined for the labor and nonlabor units, material costs,
and expense costs defined for each activity in the project.
The project complexity value can be between 0 and 100 percent. If the
project complexity value equals 0, the module uses the low estimate for
each activity. If the project complexity value equals 100, the module
uses the high estimate for each activity. For project complexity values
between 0 and 100, the module calculates an intermediate value
between the low and high estimates for each activity. The value
calculated using the project complexity value is then copied into the
planned labor/nonlabor units, material costs, and expense costs for each
activity.
Tailor the WBS elements You can modify the Work Breakdown
Structure (WBS) elements associated with the selected methodology.
Click Tailor to view the details and activities of each WBS element.
Tailor the WPs and Docs You can view the work products and
documents associated with the selected methodology. Click Tailor to
view the details of each work product or document and to select which
documents to include in the project plan.
Choose Assignment Rate Type You can use the rate type that has
been set for the project. Alternatively, you can copy the price/unit rate
type from the methodology.
The Modify Import Configuration dialog box lists the data types for
which you can set options. Select one of the following in the Action
field to indicate how you want to update the data type:
■ Keep Existing Retains data in the existing database and does not
overwrite them with the updated methodology data; adds new data
if the record does not exist.
■ Update Existing Overwrites data in the existing database with the
updated methodology data; adds new data if the record does not
exist.
■ Insert New Retains data in the existing database and adds any new
data items. For example, if a new role was added in the
Methodology Management module, but you don’t want to change
the existing roles, choose Insert New to add the new role to the
project management database.
■ Do Not Import Retains data in the existing database and does not
import the methodology data.
Use status for filtering projects in the EPS You can change an
open (Active) project to closed (Inactive) when the project is completed.
You can also assign a What-If status to a copied project that you want to
use for analysis. Project status can be used to organize and summarize
information, and to filter projects.
Choose File, Open. Select the EPS node or project whose status you
want to change and click Open. Then, click Projects in the Home
workspace.
To view only those projects with a specific status, choose View, Filter
By, Status, then choose the status you want to use. You can also choose
View, Filter By, Customize. In the Filters dialog box, mark the
applicable Select checkboxes for the statuses of the projects you want to
see.
Status filters
When you open the Projects window, include the node/project you want
to copy as well as the node to which you want to copy it. Select the
node/project you want to copy, then click Copy from the command bar.
Select the node to which you want to copy the node/project, then click
Paste in the command bar. When you copy a project to another location
in the EPS, you can also choose to copy the links to the WBS,
documents, OBS, and other related elements. Mark the applicable
checkboxes in the dialog boxes that are displayed when you click Paste.
Click OK in each dialog box to proceed with the copy.
Mark the
checkboxes for
the elements
you want to
copy.
You can only delete Delete an EPS node or project When you delete a node, all
projects that are opened in projects in that branch of the hierarchy will also be removed. If you
Exclusive mode. don’t want to delete these projects, you must copy and paste them to
another area of the hierarchy before you delete the higher-level EPS
node.
To include/exclude tabs,
right-click in the Details
area, and choose
Customize Project Details.
Open each tab to view and edit that type of information for the selected
node or project.
General information The General tab enables you to view and edit
general information about the selected node or project. This information
includes the ID, name, responsible manager, leveling priority, and risk
level. You can also view or edit the project’s Web site address, if
applicable.
Leveling Priority
You can include assignments from closed projects during leveling. Mark
the Consider Assignments in Other Projects with Priority Equal/Higher
Than checkbox in the Level Resources dialog box and indicate a Project
Leveling Priority for those projects on the General tab in the Projects
window. You can enter a value from 1 to 100, with 1 being the highest
priority. To use the priority level as a tie breaker during leveling, include
Project Leveling Priority under Leveling Priorities in the Level
Resources dialog box.
Dates The Dates tab enables you to edit schedule information for the
selected project. This information includes the current data date,
planned start date, and the scheduled finish date. If you have an EPS
node selected, you can also enter the dates you anticipate the node will
start and finish.
The latest early finish date calculated A date constraint The user-defined date
when the project was last scheduled placed on the the project is expected
project end date to start or finish
Anticipated Dates
Anticipated start and finish dates are used during the project planning
stage, and can be set at the EPS, project, or WBS level. If the selected
project has no activities, or the activities have not started, the Start date
or Finish date (in columns) is set equal to the Anticipated Start or
Anticipated Finish. Click the Browse button to select a new date.
Project codes The Codes tab enables you to assign project code
values to the selected project. You must first add project codes and
values (choose Enterprise, Project Codes).
Default values The Defaults tab enables you to specify the default
settings for the selected project. This information includes the default
cost account for resource assignments to activities, the defaults for
automatic activity numbering, and the default activity calendar, duration
type, and percent complete type.
If you change the default calendar, The default cost account
the module applies the default for resource assignments
calendar only to new activities. to activities and project
The default duration, expenses in the project
percent complete, and
activity types for
activities in the project.
Changing these
settings does not affect
existing activities.
Mark to automatically
number new activities
one increment greater
than the selected
activity, when adding
manually. New activity IDs are numbered
according to this increment.
This setting is used to calculate the cost for Choose to determine the true At
activities that have labor/nonlabor/material Complete units/costs.
units with no assigned resources/roles or
resources/roles that do not have prices. Choose to track the amount
remaining before you exceed the
budget.
Mark to base percent
complete on activity steps
when using the physical
percent complete type.
Refer to the Help for further Mark the Recalculate Actual Units and Cost when Duration% Complete
information about the Changes checkbox to automatically update the actual units and costs
calculation settings. when the Duration% complete is updated. If this checkbox is cleared,
the module does not estimate actuals, and the actual fields remain blank
unless you specify values.