You are on page 1of 7

PAPER

Stakeholder Engagement in PPP Projects Stakeholder Engagement in PPP Projects

Precast Segmental Bridge Failures –


An Introspection

V N Heggade
CEO
STUP Consultants Pvt Ltd

Introduction Some of the commonalities of these failures are:


There has been an alarming number of failures of precast • Belong to the category of pre cast segmental
segmental construction in the country with seven of construction using span-by-span method of
them reported since November 2018 (Figure-1). Of erection.
these three of them belong to the category of spine and
wing construction. • Compression failure due to crushing of concrete
during construction.
The latest failure on 28th March 2021, the expressway • Only one stage of prestressing, inducing complete
flyover at Dwarka, New Delhi was dramatically prestressing force into the section when only around
captured on CCTV camera without which it would not 50% of the load was there on the structure.
have been possible to assess that the trigger for collapse
originated from already installed back span. A synthesis of the probable causes of failure has been
attempted and some recommendations given.

Figure-1: Precast Segmental superstructure failures during construction

40 MARCH 2021
PAPER

Synthesis of probable design & • Thermal stresses not considered during construction
construction causes and recommended stage (expansion or contraction),
remedies • Effect of thermal gradient effect during construction
stage not considered.
Cracking normally triggers the mishap in post tensioned
segmental construction. Cracking in segmental box • Over or under estimation of initial prestress resulting
girders may occur due to the inadequacies arising in the from optimistic or conservative coefficients of
design for construction stage, construction techniques friction and wobble.
adopted and quality and workmanship of construction. • Under or over estimating relaxation loss in
prestressing.
Design for construction stage • Tendon profiling where a large variation of prestress
Inadequacies during the design stage may initiate eccentricity occurs and not checking the stresses at
cracking, consequently resulting in mishaps. critical locations.
• Forces of Bridge Deck Equipment (BDE) due to
• Inappropriate consideration of stresses due to
the coupling of BDE with the permanent structure
moment redistribution,
not considered.

Figure-2: A stage of Kinemetics of launching

MARCH 2021 41
PAPER

• Wind action on BDE and its effect on permanent problem of one stage prestressing for less than 50% of
structure during construction stage not considered. the service is further aggravated in the spine and wing
construction. The higher widths warrant twin celled
It has been widely reported that there is a conservatism
box whether it is spine and wing construction or single
in assuming the wobble and friction coefficients leading
transverse box segment.
to more prestressing in reality than actually assumed in
design calculations.
At around 1/3rd or 1/4th the span, the prestressing
cables are profiled vertically thereby inducing a
In the span by span method of precast segmental
vertical component of prestressing. The distribution
construction, invariably one stage prestressing is
of shear stresses for such vertical component is made
adopted thus stretching the section to its limits when
conventionally with the assumption that the rigid cross
only around 50% of the load is allied on the section, but
section is transversely not deformable (Figure-3 Left).
much of its time dependent prestressing losses are yet
However, depending upon the stiffness of component
to occur. Further, during the launching of the segments,
parts of the cross section this assumption may not be
as can be seen from the Figure-2, the coupled actions
correct (Figure-3 Right). The rigid un-deformable
between launching girder can induce unscheduled
cross section in transverse direction, assumes that
forces in the girder which is under erection during the
a centered vertical component of the prestressing is
load transfer and also on the already installed back
evenly distributed among the webs. In fact, a center
span.
vertical component of the prestressing may induce a
While the segments are being erected in the span Pn+1 transverse deformation in the top and bottom flanges
to Pn+2, the launching girder may induce restraints with a displacement of the center web larger than that
on the already installed deck by virtue of its fixity at of the external webs, leading to cracks in the flanges.
‘middle support’ location and friction by ‘counter
weighted trolley’ at the rear end. That may induce
additional compression in the back span.The lauching
girder is supported on the middle support and the rear
trolley by portal frame action in the transverse direction.
For any reasons, if the middle support and rear trolley
are not exactly on top of diaphragm segments, there is
a possibility of torsion being induced due to the wind
action on the 2 to 3 m deep launching girder.

Uniform temperature variation during day and night


and thermal gradient acoss the depth would also induce
further stresses in the girder.

The spine and wing construction in the country started


with JJ Hospital fly in which the deck width was only
Figure- 3: Transverse stiffness of wide two celled box
16.20m. Nowadays, the spine and wing constructions
is being adopted for much larger widths even up to Thus there is a very likely possibility of additional
36m with very large cantilever wings. In that kind prestress being induced in to the cross section for a
of construction, only the spine cross section has to variety of reasons explained above. Taking this into
accommodate the entire prestressing force as wing cognizance, IRC: 112 not only specifies ULS checks for
cross sections do not contribute to the property of the construction stage but also SLS checks in its Annexure:
section but act as superimposed Dead Load. Thus, the A-6 which is reproduced below.

42 MARCH 2021
PAPER

A6- 3.3 Serviceability limit states • Inadequate Geometric control during matchcasting.

(1) Serviceability criteria for the completed structure • Non uniform temporary prestressing between the
need not be applied to intermediate construction segments.
stages, provided that durability and final appearance • Lower strength of materials.
of the completed structure are not affected (e.g.,
• Over or Under prestressing
crack width and deformations) and comply with
applicable provisions of the Code. • Unscheduled forces on permanent structure due to
faulty operation of Bridge Deck Equipment (BDE).
(2) The idea of frequent combination does not exist
during construction and also limit states related to Most important distinction between full span precast
durability are not pertinent for short term-phases construction to that of segmental construction are the
as such limiting stresses in concrete to 0.48 fck(t) joints between the segments that have to be perfectly
and steel to 0.8 fyk under rare combination during fitted with each other.These joints have to transfer
construction is adequate. the compression through 100% contact area which is
ensured by match casting, either by long line method or
(3) For bridges or element of bridges in which limit
by shortline method.
state of decompression is checked on the completed
structure, tensile stresses less than fctm(t) under the Guidelines for design and construction of segmental
quasi-permanent combination during construction bridges, IRC:SP:65 covers in detail the design and
is permitted. construction requirement for precast segmental
(4) Prestressing effects may be taken as γsup= γinf= 1.0 bridges. Despite the elaborate guideline, there seem
during the construction. to be perennial issues regarding the quality of match
casting of the segments leading to mishaps during the
Taking in to consideration all the uncertainties as
construction due to following reasons.
explained above, it is recommended that the clause (2)
of A6-3.3 be modified to read as follows: • Concrete not properly reaching the bottom slab and
also honeycombing at the edges of the segments
(2) The idea of frequent combination does not exist
near the end stopper.
during construction and also limit states related to
durability are not pertinent for short term-phases • The epoxy formulation for wet joints not properly
as such limiting stresses in concrete to 0.48 fck(t) applied and temporary prestressing not done within
and steel to 0.8 fyk under rare combination during the pot life leading to less than 100% contact area
construction is adequate. However, for span-by- between the match cast surfaces.
span precast segmental construction for one stage • The shearkeys being broken while deshuttering or
prestressing under the rare combination, stresses in handling the segments leading to imperfect fitting
concrete shall be limited to 0.36 fck(t). of the segments.
During Construction stage • Less than 100% contact area between the
Inadequacies, as listed below, during the construction compression joints leading to longitudinal cracks
stage also may initiate cracking, resulting in mishaps. after final prestressing.

• Fabrication defects in pre-casting yard. There are some specialities which make the match
casting of precast segments sensitive to certain types
• Inappropriate and timely (within pot life of epoxy of defects. Due to the short pouring cycle between
polymerisation) epoxy jointing of segments. segments (usually a day) the whole process of segment
• Breaking of shear keys during handling of segments. construction can lead to different type of construction

MARCH 2021 43
PAPER

defects if specific inspection and adequate quality before the hardening of epoxy glue. The delay in
measures are not taken. Some of the most common the process or the non-uniform pressure across the
defects during the fabrication and erection of segments depth of the segment would result in an undulated
are: surface.
The segments should be repaired prior to their erection
• The continuous reuse of movable parts of the
as long as the defects do not affect the contact faces
formwork might affect its water tightness after
between segments that are match cast. The contact faces
several reuse cycles. This can lead to a leak of the
should not be repaired prior to erection and prestressing
grout component of the concrete mix.
of the segment since there is risk of damaging them
• The segment pour sequence, particularly if a further. Conventional concrete repairing techniques
self-compacting concrete mix is not used, is very such as the use of micro concrete or grout mixes with
sensitive to workmanship skills. The compaction low shrinkage, after cleaning the affected area, are
and pouring sequence within each segment, common repairing strategies.
honeycombs, voids or cold joints due to improper
spacer fixing are common problems that might Additional precauations are called for to control the
arise. ‘bow effect’. For the segments whose width to length
ratio is more than 6, segment casting mock ups have to
• In match casting of very wide segments there can
carried out with special concrete mix designs producing
be ‘bow effect’. The segment cast first which acts as
low heat of hydration, appropriate cooling and curing
a shutter face may undergo curving at the joint face
method of concrete in the regions of high ambient
due to thermal gradient and induce that curvature
temperature and measurements recorded of the heat of
permanently in the newly cast segment. The
hydration to predict the thermal gradients.
segment cast first would come back to its original
shape after cooling to ambient temperature. This In many of the bridge failures refereed to above, it
effect is particularly severe when the ratio of width has been reported that the epoxy glue application was
to length of the segments is more than 6. found to be inappropriate. The external prestressing
• The placing of the preassembled segment with dry joints could be a solution to avoid epoxy glued
reinforcement within the formwork and the difficult wet joints.
access for inspection and location of spacers can
lead to lack of cover in some locations. Quality control during design and
construction
• During the segment movement to storage or erection,
damages can arise from improper handling of the In comparison to other conventional prestressed
segment, such as chipping or breaking of shear concrete bridges, for precast segmental bridges, the
keys and local cracking if temporary lifting points influence of construction method, construction sequence
and support points are not adequately designed or and construction accuracy are significant. Therefore,
detailed. it is imperative that qualified engineer(s) with good
knowledge, experience and demonstarted capability are
• The ‘glue joints’ with epoxy resin is provided from constantly involved in the design scrutiny and Bridge
durability considerations to ensure water tightness construction engineers are stationed at the construction
in the joints to avoid any ingress of water into site to provide appropriate construction management.
internally post tensioned tendons. Normally, the
preparation, application and temporary prestressing The design and construction of precast segmental
of epoxy glue to induce uniform pressure across the bridges require a tight integration between several
jointed surface should be completed with in an hour interfaces as part of an industrialised process, and

44 MARCH 2021
PAPER

requires specific measures to be taken into account system is a very important part in precast segmental
in the quality control of the geometry, materials and construction. There are instances where the design
erection and also specialised workmanship in different consultant and the supplier of BDE are the same.
areas. Even when inhouse design is done by a contractor,
the BDE is also supplied by the contractor in some
Detailed documents including method statements, cases. There is a strong conflict of interest here and this
fabrication and erection procedures and testing practice of design consultant and BDE supplier to be
requirements need to be detailed in the contract the same agency should be discontinued from a safe
documents to assist the relevant teams involved in the construction point of view. Presently, there is no system
project to reduce the risks during construction. of proofchecking the launching system or BDE and that
needs to be introduced with immediate effect.
The current organisation structure for managing the
EPC contract consist of a design consultant to the In the present Authority Engineer (AE) contract, there
contractor, proofchecking consultant to approve the is no provision of structural engineer with necessary
design of the contractor’s designer, safety consultant qualification, experience and demonstarted capability
to approve the project highway safety and finally as a key personnel. This needs to be introduced with
Authority Engineer (AE) representing Authority acting immediate effect.
as a supervision consultant including final design
approval and quality control at the site. The contractor Conclusions
engages the prestressing system supplier and Bridge The bridge failures of precast segmental construction
Deck equipment supplier. Some times contractor has during construction are continuing to occur and that is
his own BDEs. a matter of great concern to the engineering fraternity.
The recent collapse in Dwarka, New Delhi is one too
As the proof consultant and safety engineers are
many and that too when the best of the designers and
engaged and paid by the contractor, invariably choice
contractors were involved. As per the adage ‘Those
is made on low cost criteria, not on the qualification
who ignore the history will be condemned to relive
and experience in precast segmental construction. The
it’, as such it is a time for serious introspection for the
expectation from proofchecking and safety consultants
engineering fraternity.
is that the design has to be approved immediately after
being submitted by the contractor’s designer. There is After due analysis of the probable causes of failures,
a strong need to look in to the prequalification of proof some recommendations are given below to prevent
checking and safety consultants. such occurences.
The EPC contract specifies that the entire design with • Even for construction stage, SLS check for rare
approvals and the 10 % of the work has to be completed combination involving wind and thermal loads
within 180 days of the award of the work including has to be carried out as per IRC:112. However, for
geotechnical investigations, surveying, etc. In many span-by-span precast segmental construction for
cases, this is impractical and the haste leads to designs one stage prestressing, stresses in concrete should
that are incorrect, quick approvals and bad quality of be limited to 0.36 fck(t).
construction, which all are the causes of the mishaps.
This criteria has to be reviewed going forward for safe • There are certain aspects which make the match
construction and the bridge to perform as reuquired for casting of precast segments sensitive to certain
its design life, albeit with regular maintenance. defects. The segments should be repaired prior to
their erection as long as the defects do not affect
The Bridge Deck equipment design including launching the contact faces between segments that are to be

MARCH 2021 45
PAPER

match cast. These faces consequently should not 180 days of the award of the work including
be repaired prior to erection and prestressing of geotechnical investigations, surveying, etc. needs
the segment to avoid the risk of causing further to be reviewed and modified.
damage.
• The designer for the EPC contractor and supplier of
• Incase of segments with width to length ratio higher BDE or launching system should not be same.
than 6, the mock ups for match casting of segments
• The design of launching system or BDE must also
to arrive at optimum mix design of concrete should
be proof checked and also load tested.
be made mandatory.
• A qualified, experienced structural engineer with
• For the time being wet joints should be prohibited
demonstrated capability has to be introduced as key
and dry joints with external prestressing should be
personnel in Authority Engineer (AE) contract.
encouraged for span-by-span method of precast
segmental construction. Acknowledgement
• There is a strong need to look in to the Author wishes to record the grave concern of CEAI at
prequalification criteria of the proof checking and the unabated bridge failures in the recent past and their
safety consultants. drive to help the authorities to find a solution to the
same.
• The criteria in EPC contract to complete design
with approvals and the 10 % of the work within

46 MARCH 2021

You might also like