Professional Documents
Culture Documents
OFFSHORE
WIND FARM
DEVELOPMENT
IN TAMIL NADU
MARCH 2018
This report is co-funded
by the European Union
In 1957, the signature of the Treaties of Rome It has also become much easier to live and work
THE EUROPEAN UNION marked the will of the six founding countries
to create a common economic space. Since
then, first the Community and then the European
in another EU country.
8 OUTLINE WIND FARM DESIGN............................................................................................................................66 15 FIRST OFFSHORE WINDFARM PROJECT IN INDIA (FOWPI)........................................................................ 136
8.1 INTRODUCTION............................................................................................................................................................ 66 15.1 DESIGN BASIS OF FOWPI...........................................................................................................................................137
8.2 ENERGY PRODUCTION............................................................................................................................................... 66 15.2 DESIGN FOR FOWPI.................................................................................................................................................... 138
8.3 ELECTRICAL OUTLINE DESIGN.................................................................................................................................70
8.4 PRELIMINARY FOUNDATION COMPARISON.......................................................................................................... 76 16 REFERENCES....................................................................................................................................................... 142
APPENDICES.............................................................................................................................................................. 144
Since the FOWIND project began at the end of We now have 8MW turbines in commercial
2013, there have been dramatic changes in the operation, with rotor diameters of 164 meters.
offshore wind business: These will soon be surpassed by machines up
to 9.5 MW, and a number of manufacturers will
Four years ago, offshore wind was largely a breach the 10MW barrier soon. According to a
European affair, costly and difficult. However, 2011 EU-funded study, with current materials
due to strong public-private partnerships in machines of up to 20 MW can be built; and with
the key countries surrounding the North, Irish advances in materials science and engineering
and Baltic Seas, the industry is now booming experience, there is no telling what the upward
with a strong supply chain, a new generation of limit might be.
turbines, and ever-decreasing costs. As a result
of this, interest in offshore outside of Europe is All of this is to say that the current rapid rate
on the rise, with plans for massive expansion of of change is likely to continue, with improved
the industry in Asia and North America. China’s technology, even larger and more cost-effective
offshore industry installed more than 1,000 turbines, and increasingly efficient operation and
MW in 2017, and the first commercial wind farm maintenance practices.
is now operational off the US East Coast, with
very ambitious plans for rolling out gigawatts For the moment, however, we are faced with the
over the next 5-10 years. challenge of enabling the spread of the technology
beyond European waters to India without taking
In 2015 the Indian government dramatically 25 years to get to competitive prices! Every
upscaled its ambition for renewable energy, national circumstance is different, but there are
setting very aggressive targets for 2022, lessons to be learned from each of them. Chief
including 60 GW of onshore wind. While among them is the need for long-term and well-
offshore will not play a major role in meeting planned public-private partnerships that are
that target, it indicates a political direction for necessary to create a competitive and sustainable
the future of the Indian energy sector in which offshore wind industry.
offshore wind could play a significant role in
the medium and longer term. Our thanks to all our partners, and a special
thanks to ReNew Power and the FOWPI project
for their contributions to the report. We trust
you will find the results instructive as the
sector moves ahead.
The National Institute of Wind Energy (NIWE), an autonomous R&D institution under
the Ministry of New and Renewable Energy, Government of India, is a knowledge
partner to the project since June 2015. Renew Power Ventures Private Limited,
a leading Independent Power Producer in India joined as an industry partner
to the project in June 2016.
This report has been developed as part of Work Package 5 on feasibility studies of
offshore wind in Tamil Nadu. The aim of this report is to provide a concept design for
a demonstration project of 150 to 504 MW in Tamil Nadu’s most promising offshore
wind development area, “zone A” identified in the Pre-feasibility Study [1]. This
provides companies and government institutions with a starting point for future
detailed offshore Front End Engineering Design (FEED) studies and assists with the
identification of key project risks in Tamil Nadu. A parallel study has been conducted
for the state of Gujarat.
1. INTRODUCTION
capacities are representative of established potential demonstration project configurations
(4 MW), current (6 MW) and near future (10 MW) using DNV GL’s Turbine.Architect design tool
offshore wind turbine designs. (also used for foundation type comparison).
The preliminary risk assessment from the
Based on these wind farm capacities and turbine Pre-feasibility Study has been updated to identify
The FOWIND consortium’s, Tamil Nadu Feasibility Study Report, is a key milestone sizes, a high level Annual Energy Production (AEP) areas which require more detailed assessments.
deliverable from the project’s final year of work and is the consecutive step following assessment has been carried out for the potential
demonstration project and indicative Capacity Beside technical considerations; high level
the Tamil Nadu Pre-feasibility Study delivered in 2015 [4]. This report is supported
Utilisation Factors (CUF) have been estimated. social and environmental factors have been
by FOWIND’s Supply Chain, Port Infrastructure and Logistics Study [2] and the Grid touched upon in this study.
Integration Study [3] delivered in 2016 and 2017 respectively. Concept demonstration project designs have
been conducted for each combination of Detailed descriptions for the applied methodology
project capacity, wind turbine, foundation type of the individual studies are provided with in each
The objective of this report is to provide a concept this updated analysis. There is currently no installed (monopiles, jackets and gravity base) and the section of the report.
design for a demonstration project of 150 to 504 LIDAR in Tamil Nadu, however NIWE have plans to
MW in Tamil Nadu’s most promising offshore wind commission a LIDAR in the Gulf of Mannar and have
development area, “zone A” identified in the Pre- recently issued a tender (Jan 2018) for offshore
feasibility Study [4]. This provides companies and geotechnical investigations. This investigation is
government institutions with a starting point for aimed to support the design of the offshore LIDAR
future detailed offshore Front End Engineering platform. Once 12 months of on-site Lidar data
Design (FEED) studies and assists with the becomes from the NIWE LIDAR the MNRE may wish
identification of key project risks in Tamil Nadu. to conduct a full energy assessment in support of
A parallel study has been conducted for the state this Full Feasibility Study.
of Gujarat.
A preliminary metocean and geotechnical study
The study builds on the FOWIND Pre-feasibility has been conducted for the Tamil Nadu region,
Study, which identified eight offshore wind this was in direct response to key risks identified
development zones. Zones A to H range from 810 during the Pre-feasibility Study (e.g. lack of and
to 2,116 km2 in area and each zone could feasibly uncertainty within the available data for offshore
accommodate multiple numbers of multi-MW wind resource, metocean climate and geotechnical
offshore wind farms. Zone A with the lowest conditions). The metocean study provides wave
identified cost of energy has been sub-divided and current parameters suitable for concept
into 10 “sub-zones” to identify an optimal location feasibility design and the geotechnical study
for a future demonstration project. Any further provides a lower and upper bound soil profile
known constraint parameters (e.g. technological envelope for preliminary design.
barriers and spatial conflicts) were considered in
TIME-DOMAIN
LOADS LOADS DATABASE SITE SUITABILITY LOADS ANALYSIS
AUTOMATED
DESIGN DETAIL / FEA DESIGN
TURBINE DESIGN
COMPONENT
TURBINE-PRICE COST MODELS
SUB-STRUCT AUTOMATED
DESIGN & PRICING SUP-STRUCT DESIGN
FARM
FINANCIAL POWER CURVE DYNAMIC POWER
CALCULATIONS POWER CURVE CALCULATION CURVE CALCULATION
(CoE/NPV/IRR)
WIND FARM
identified, the sub-zone selection methodology
is presented and discussed in Section 4.3. on the Pre-Feasibility assessment and the features
of these eight zones are described in Table 4-1.
LOCATION
These 10 sub-zones are subsequently modelled
using DNV GL’s system design and cost modelling FIGURE 4-1: HEAT MAP SHOWING
tool Turbine.Architect and evaluated against PRELIMINARY SITE SELECTION
their normalised levelised cost of energy (LCOE)
to establish the optimum demonstration project
locations within zone A. The Turbine.Architect
methodology and results are presented in
Section 4.4.
TABLE 4-1: POTENTIAL ZONES FOR DEVELOPMENT OF OFFSHORE WIND POWER PROJECT FIGURE 4-2: TAMIL NADU ZONE A SUB-ZONE
100 m and 120 m AGL1
Indicative Mean WS at
to existing substation
Mean Percentage WS
change between
change between
Gulf of Mannar
depth (mLAT)
lowest score)
Indicative
Indicative
zone D
Notes
(km2)
Area
(km)
Tuticorin A3
A4
A5
A1
Manappad A9
the zone;
*C 7.9 0.7% 1.5% -37 24 810 Bathymetry at higher resolution is
recommended (i.e. Tcarta);
Closest ports: Valinokkam, Rameswaram,
Tuticorin
Shallow water: a few sand bars are located
within the zone;
*D 8.1 1.2% 2.2% -30 36 1,015 Bathymetry at higher resolution is FIGURE 4-3: TAMIL NADU SHIPPING DENSITY TRAFFIC
recommended (i.e. Tcarta);
Closest port: Manappad
A9
A7
A10
A8
1. Only wind speed at 120 m AGL have been used in the zone identification. 2. Only wind speed at 120 m AGL have been used in the zone identification.
Wind speeds at 100 m are stated for reference ONLY. Stated wind speeds Wind speeds at 80 m are stated for reference ONLY. Stated wind speeds
are indicative and require validation. are indicative and require validation.
Distance to
Distance to
Area (km2)
coast (km)
depth (m)
WS 100m
port (km)
WS 120m
Sub-zone
Distance
WS 80m
onshore
to grid
Water
(m/s)
(m/s)
(m/s)
(km)
A1 7.58 7.81 8.01 -14.42 11.53 11.57 12.90 79.4
A2 7.82 7.94 8.01 -19.22 16.83 6.99 18.69 79
A3 7.68 7.90 8.01 -18.07 12.35 6.99 14.22 105
A4 7.82 7.93 7.98 -25.53 19.48 6.99 21.54 80
A5 7.78 7.93 7.98 -29.24 20.39 6.99 22.37 70.5
A6 7.80 7.99 8.07 -27.50 20.83 12.72 22.65 86.9
A7 7.80 8.03 8.22 -16.51 14.87 26.90 21.15 98
A8 7.76 7.98 8.17 -18.44 17.90 32.17 23.16 91.3
A9 7.92 8.13 8.22 -22.90 22.35 26.51 26.60 82.1
A10 7.94 8.16 8.30 -18.77 23.96 30.14 31.18 80.4
Epsilon 50 [-]
strength from
Friction angle
Depth to [m]
Depth from [m]
unit weight
4.4.1 Introduction
Submerged
Tidal level HAT 0.8 m
Soil type
strength
to [kPa]
[kN/m3]
50-year maximum
11.0 m
Shear
Shear
[kPa]
An analysis has been undertaken to identify
[deg]
wave height
the most suitable sub-zone for wind farm 50-year storm
development in the Tamil Nadu region. 1.4 m
surge elevation
The analysis was completed using DNV GL’s 0.0 3.8 Sand 7.0 - - - 20
Annual mean
system design and cost modelling design 1.24 m
significant wave height 3.8 10.8 Sand 8.5 - - - 25
tool Turbine.Architect.
Energy availability 92.8 %
10.8 21.2 Sand 8.5 - - - 20
4.4.2 Methodology Annual operational
4.30 mINR (million INR)
3
21.2 100 Sand 8.5 - - - 25
expenditure
The goal of the spatial analysis is to form Wind climate Weibull
2.0
a quantitative ranking of cost of energy for shape factor
each sub-zone in zone A to determine suitability Hub height 105 m
TABLE 4-5: SPATIAL ANALYSIS INPUTS FOR SUB-ZONES WITHIN TAMIL NADU REGION
for wind farm development. Wind shear
Roughness wind shear
calculation method
Cost of energy will be calculated using DNV GL’s
Annual mean
at 100 mLAT
construction
Roughness height 0.001 m
onshore grid
Water depth
Distance to
Distance to
wind speed
connection
to LAT [m]
Turbine.Architect tool. The tool is capable of
port [km]
Sub-zone
forming detailed cost estimates for the majority The maximum wave height, storm surge and
[m/s]
of components of the wind farm and is sensitive
[km]
tidal parameters are used for producing offshore
to the parameters listed in Section 4.4.3, and many support structure estimates. The significant wave
more. For further information on the Turbine. height, availability and annual OPEX parameters
Architect cost modelling tool refer to Section 3.
A1 14.42 7.81 11.53 12.90
are used in the wind farm cost modelling
calculations. A2 19.22 7.94 16.83 18.69
4.4.3 Inputs
A3 18.07 7.9 12.35 14.22
A constant soil profile has been assumed
Inputs relevant to the cost modelling and systems across the region. Soil parameters are used A4 25.53 7.93 19.48 21.54
design undertaken during the spatial analysis are in the definition of support structure and are
presented in this section.
A5 29.24 7.93 20.39 22.37
as presented in Table 4-4.
A6 27.5 7.99 20.83 22.65
4.4.3.1 Regional Conditions 4.4.3.2 Site Conditions A7 16.51 8.03 14.87 21.15
Conditions constant across all of the subzones Conditions which vary between sub-zone are
A8 18.44 7.98 17.90 23.16
modelled during the spatial analysis are presented presented for each sub-zone in Table 4-5. A9 22.9 8.13 22.35 26.60
in Table 4-3.
A10 18.77 8.16 23.96 31.18
3. 1 mINR = 1 million INR = 1,000,000 INR. 1 Crore INR = 10 mINR = 10,000,000 INR. 1 Lakh INR = 0.1 mINR = 100,000 INR.
A1
A2
A7
A3
A8
A5
A10
A9
A6
A4
Rotor diameter 154 m 96%
In Table 4-7 each sub-zone has been placed in
RNA mass 365 tonnes 94% order of rank for the three parameters mentioned
4.4.4.4 Operational Expenditure Costs
Capex (% of max)
Drive train configuration Direct drive 92% above – annual mean wind speed , water depth
Wind speed and turbulence class 1B and distance to grid connection. It can be seen
90% At this stage of analysis operational expenditure that A3 is in the top three sub-zones in terms of
Cut-in wind speed 3 m/s has been assumed to be constant across the
88% water depth and distance to grid. This is reflected
A1
A2
A7
A3
A8
A5
A10
A9
A6
A4
Cut-out wind speed 25 m/s region and so the same value is used for each in the CAPEX results, Figure 4-5, which show A3
sub-zone. In reality, the costs will vary between as having the second lowest capital expenditure,
the sub-zones due to the changes in distance with sub-zone A1 having the lowest. A3 ranks
A breakdown of CAPEX for the major components
4.4.3.4 Support Structure from shore. However, this variation will be above A1 in terms of energy yield, however, as
is shown in Figure 4-6. The major components are:
negligible in comparison to the total OPEX cost. shown in Figure 4-7 the overall trend for the
Electrical infrastructure;
For the purposes of the spatial analysis a monopile Turbines; Tamil Nadu zone is that lower CAPEX drives lower
support structure has been modelled as the Foundations; 4.4.5 Conclusions cost of energy, however of the sub-zones with low
foundation type. Preliminary analyses have shown Project development (feasibility studies, CAPEX (A1, A2 & A3) it is the site with the higher
that the spatial trends are the same regardless of consenting, package management etc.). The sub-zone showing the lowest cost of energy annual energy yield – A3 – which has the lowest
support structure type and so the spatial analysis is A3 (see Figure 4-4. This is a result of A3 being cost of energy overall.
has been restricted to one type. FIGURE 4-6: SPATIAL ANALYSIS RESULTS:
CAPEX BREAKDOWN
4.4.4 Results
4.4.4.1 Cost of Energy
TABLE 4-7: RANKING OF SUB-ZONES FOR GEOSPATIAL PROPERTIES
Results in terms of cost of energy are shown
connection
to onshore
mean wind
Project CapEx
in Figure 4-4.
Distance
Annual
Water
speed
depth
Rank
grid
FIGURE 4-4: SPATIAL ANALYSIS RESULTS:
COST OF ENERGY RELATIVE TO MAXIMUM
A1
A2
A7
A3
A8
A5
A10
A9
A6
A4
OF SUB-ZONES
Turbines Electrical Foundations Project Development
1 8.16 A10 14.42 A1 11.53 A1
100.0%
2 8.13 A9 16.51 A7 12.35 A3
3 8.03 A7 18.07 A3 14.87 A7
98.0%
4.4.4.3 Annual Energy Yield 4 7.99 A6 18.44 A8 16.83 A2
Relative CoE (% of maximum)
96.0%
5 7.98 A8 18.77 A10 17.9 A8
Variation in annual energy yield across the Tamil
94.0% 6 7.94 A2 19.22 A2 19.48 A4
Nadu sub-zones, expressed to the maximum of
92.0% the sub-zones, is shown in, is shown in Figure 4-7. 7 7.93 A4 22.9 A9 20.39 A5
90.0%
8 7.93 A5 25.53 A4 20.83 A6
9 7.90 A3 27.5 A6 22.35 A9
88.0%
10 7.81 A1 29.24 A5 23.96 A10
A1
A2
A7
A8
A3
A5
A10
A9
A6
A4
Shear strength
Shear strength
Epsilon 50 [-]
Friction angle
parameters and stratification in the region, and
Depth to [m]
5.4.3 Tamil Nadu southern zone
Depth from
unit weight
Submerged
from [kPa]
geotechnical description for any future projects, a detailed site-specific
Soil type
[kN/m3]
to [kPa]
offshore geophysical and geotechnical survey
[deg]
campaign should be conducted and combined
[m]
The stratigraphy within southern zones is believed
with a comprehensive ground model to capture
to generally comprise of a sand and cemented
sands with occasional stiff clay seams to depths
spatial variability and geohazards across the site 0.0 3.8 Sand 7.0 - - - 20
(see recommendations in Section 5.5).
of around 45m, with relative density of the sands 3.8 10.8 Sand 8.5 - - - 25
ranging from loose to very dense.
5.5 FUTURE SURVEY 10.8 21.2 Sand 8.5 - - - 20
RECOMMENDATIONS
5.4.4 Tamil Nadu southern zones
21.2 To depth Sand 8.5 - - - 25
In order to conduct FEED, detailed design and
concept design soil profile deliver a bankable offshore wind project a range of
comprehensive site-specific surveys are required
Table 5-5 and Table 5-6 provide estimated lower upfront; these include wind measurement,
and upper bound soil profiles for Tamil Nadu’s oceanographic surveys, geological surveys TABLE 5-6: TAMIL NADU SOUTHERN ZONE INDICATIVE UPPER BOUND “CEMENTED”
southern zones. As stated these profiles are (geophysical & geotechnical) and any relevant SOIL PROFILE
indicative and experience based ONLY and shall hazard identification surveys such as unexploded
be considered to broadly apply across the zone A ordinance (UXO) in some areas. The Supply Chain,
Shear strength
Shear strength
sub-zones. Port Infrastructure and Logistics Study [2] Section
Epsilon 50 [-]
Friction angle
Depth to [m]
Depth from
unit weight
Submerged
2.1.1 and the Pre-feasibility Study [4] Section
from [kPa]
Soil type
[kN/m3]
A lower and upper bound has been provided to
to [kPa]
6.1.5.5 provides preliminary guidance for offshore
estimate a “Rochdale Envelope” of soil conditions
[deg]
surveys.
[m]
for the zone and as such provide a range of
possible conditions for foundation concept design.
0.0 To depth Sand 9.0 - - - 45
6.2 SUMMARY OF
COMMERCIALLY AVAILABLE
WIND TURBINES
Table 6-1 presents the characteristics of wind
turbines that should be commercially available
assuming a procurement date target between
2020 and 2025. Only wind turbines greater than
4.0 MW in rated capacity have been identified.
Rated Power1
Rated Power1
diameter (m)
diameter (m)
Commercial
Commercial
IEC Class
IEC Class
Timeline2
Timeline2
Turbine
Turbine
Model
Model
Rotor
Rotor
(MW)
(MW)
2-b Energy 2B6 6 IEC 1 140.6 2015 Mingyang SCD 6MW 6 IEC 2B 140 2014
Adwen AD 8-180 8 IEC 1B 180 2018 Mingyang SCD 6.5MW 6.5 IEC 1 140 2013
Adwen AD 5-116 5 - 116 2012 Nautica Advance floating turbine 7 - N/A Concept
Adwen AD 5-132 5 IEC S 132 2014 Wind Lens 5 - 100 Concept
Adwen AD 5-135 5 IEC 1B 135 2013 Samsung heavy industries S7.0-171 7 IEC 1A 171 2015
Aerodyn Engineering aM 5.0/139 5 IEC 2B 139 2015 Seatwirl 10MW 10 - N/A Concept
Aerodyn SCD 6MW 6 IEC 2B 140 2014 Seawind 6 6.2 IEC 1 126 2015
AMSC SeaTitan 10MW 10 IEC 1B 190 Concept Senvion 6.2M152 6.2 IEC S 152 2014
H127-5MW (CSIC Haizhuang) 5 - 127 2015 Senvion 6.2M126 6.2 IEC 1B 126 2014
H151-5MW (CSIC Haizhuang) 5 IEC 3B 151 2015 Senvion 6.3M152 6.2 IEC S 152 2017
HQ5500/140 (Hyundai Heavy Industries) 5.5 IEC 1B 140 2015 Siemens SWT4.0-120 4 IEC 1A 120 2010
Envision EN-4.0-136 4 IEC S 136 2016 Siemens SWT4.0-130 4 IEC 1B 130 2015
Gamesa Azimut project 15 - N/A Concept Siemens SWT-6.0-154 6 IEC 1 154 2014
GE 4.1-113 4.1 IEC 1B 113 2013 Siemens SWT-7.0-154 6 IEC 1B 154 2016
GE Haliade 6MW 6 IEC 1B 150.8 2016 Siemens Gamesa SWT-8.0-167 8 IEC 1B 167 2016
Goldwind GW154/6.7MW 6.7 - 154 2018 Siemens Gamesa D1x 10 - N/A Concept
Goldwind GW164/6.45MW 6.45 - 164 2018 Sinovel SL6000/155 6 IEC S 155 2017
Goldwind GW171/6.45MW 6.45 - 171 2018 Sinovel SL5000 5 IEC 1A 126 2012
Guodian power UP6000-136 6 IEC 1B 136 2012 Prototype in
Sway turbine ST10 10 IEC 1B 164 development
Hitachi HTW5.0-126 5 IEC S 126 2016 Taiyuan heavy industry TZ5000-153 5 - 153 2017
Hitachi HTW5.2-136 5.2 IEC 3A 136 2016 SUPRAPOWER project 10 - N/A Concept
Hitachi HTW5.2-127 5.2 IEC 1A 127 2016 Aerogenerator X 10 IEC 1 270 Concept
MHI Vestas V117-4.2MW 4.2 IEC 1B 117 2010 XEMC - Darwind XD115-5MW 5 IEC 1C 115 2006
MHI Vestas V164-9.5MW 9.5 IEC S 164 2020 XEMC - Darwind XD128-5MW 5 IEC 2B 128 2014
MHI Vestas V164-8.0MW 8 IEC S 164 2014
Notes.
1. This value is based on the nameplate rated power rather than the peak power of the power curve.
2. Estimated full commercial availability on the basis of public domain information.
3. This is the rotor productivity at rated power of the turbine.
4. TBC refers to a turbine characteristic that is “To Be Confirmed” and not yet publically reported by the wind turbine
manufacture
Goa
Punjab 30
30°N Chandigarh
Uttaranchal
Karnataka
Applying method 1, using results for extreme wind The Standard Method is used, employing the FIGURE 6-2: CYCLONE HAZARD ZONEDelhi
& THE BASIC WIND SPEED IN TAMIL NADU
speeds including cyclones from the metocean following definitions:
14°N Source: (Building Materials & Technology Promotopn Council (BMTPC); India.) Uttar Pradesh Sikkim
study presented in Table 5-2 (Section 5.3.4), the The basic wind speed, Vb, is obtained from
Rajasthan Assam Nagaland
26
estimated 50-year return 10-minute annual mean a supplied map of maximum gust (3-second 26°N
ARABIAN SEA
wind speed at 10 m above MSL is 33 m/s (Uref). average) wind speeds, independent of Bihar Meghalaya
Manipur
Applying the power law for normal wind speed direction, at a height of 10 m above level
presented in IEC 61400-3 [42] the 10 mMSL value terrain, with a probability of 0.02 being Tripura
Jharkhand Mizoram
can be extrapolated to hub-height as follows: exceeded in any one year. West Bengal
Gujarat 22
22°N
Madhya Pradesh
z_hub α
For the identified zones A, B, C, D, E and G, the
U(ref(hub)) = U(ref(10m)) basic wind speed of the coast of Tamil Nadu is Chattisgarh
z_10m
somewhere in the region of 33 m/s to 39 m/s. Daman & Diu Orissa
Dadra & Nagar
For zones F & H, the basic wind speed is in the
Pondicherry
Haveli
where: Maharashtra
region of 44 m/s to 47 m/s;
18
18°N
α = power law exponent, estimated as 0.14 for
The site wind speed, Vs, is estimated by
normal conditions offshore [42].
applying factors to account to variation in Andhra Pradesh BAY OF BENGAL
z = elevation above MSL (either 10m reference
Lakshadweep
height and exposure of the site. Extrapolating
Tamil Nadu
Kerala
96
or hub-height) 10°N to 100 m MSL and off the coast relies Goa
on estimated factors of 1.272 and 1.284 Karnataka
14
14°N
Hence the extrapolated 50-year return 10-minute respectively, resulting in an estimated
ARABIAN SEA
annual mean wind speed are estimated as 45.6 site gust wind speed of 49.6 m/s for zones A,
Andaman & Nicobar
m/s and 46.7 m/s for hub-heights of 100 mMSL and B, C, D, E and G and 60.3 m/s for zones F & H.
120mMSL respectively. These magnitudes exceed
Pondicherry
the IEC Class II requirement of 42.5 m/s (Table Examination of Table 6-2 indicates that these Very High Damage Risk Zone −A (Vb=55 m/s)
Very High Damage Risk Zone −B (Vb=50 m/s)
6-2) and indicates a IEC Class I turbine should be conditions require IEC Class I classification for all Lakshadweep Tamil Nadu 10
10°N Kerala High Damage Risk Zone (Vb=47 m/s)
sufficient. Similar requirements for IEC Class I zones. Moderate Damage Risk Zone − A (Vb=44 m/s)
Moderate Damage Risk Zone − B (Vb=39 m/s)
can be seen when estimating the 3 second 50-year
Low Damage Risk Zone (Vb=33 m/s)
return gust (Ue50 = 1.4 x Uref), where Ue50 In summary for zone A (including sub-zone A3)
is calculated as 63.8 m/s and 65.468°E
m/s for hub- both method 1 and method 2 indicate IEC Class I 68°E
Note :
heights of 100 mMSL and 120mMSL respectively. turbines could be sufficient. More detailed extreme 1. Probable maximum surge heights are shown in Flood Hazard Map of India
2°N
area from which the turbine can capture the and Rated Rotor Productivity, considering both In Northern Europe, an offshore gross capacity Table 6-3 presents the shortlisted wind turbines
lowest and highest mean wind speed estimates factor of 55% would be expected in order to for the identified Tamil Nadu zones, following
FIGURE 6-3: WIND TURBINE GROSS CAPACITY FACTOR AGAINST RATED ROTOR PRODUCTIVITY FIGURE 6-4: WIND TURBINE GROSS CAPACITY FACTOR AGAINST RATED ROTOR PRODUCTIVITY.
(7.9 M/S MEAN ANNUAL WIND SPEED AT 100 M MSL) (7.8 M/S MEAN ANNUAL WIND SPEED AT 80 M MSL)
0.50
0.50
TYPE G
0.45
0.45
T YP E G
Rated Rotor Productivity [kW/m^2]
T Y PE R
0.30
T YP E R
0.30
0.25
25% 27% 29% 31% 33% 35% 37% 39% 41% 0.25
20% 22% 24% 26% 28% 30% 32% 34% 36%
Gross Capacity Factor
Gross Capacity Factor
Notes: Wake losses and losses in the wind farm electrical systems have not been taken into account. Notes: Wake losses and losses in the wind farm electrical systems have not been taken into account.
0
30%
330 30
25%
20%
0.50
300 15% 60
56 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 57
10%
0.45
TYPE G
5%
TABLE 6-3: TYPE R SHORTLISTED WIND TURBINES FOR THE TAMIL NADU ZONES TABLE 6-3: TYPE R SHORTLISTED WIND TURBINES FOR THE TAMIL NADU ZONES CONT.
Rated Power1
Productivity3
Productivity3
diameter (m)
Power1 (MW)
diameter (m)
Rated Rotor
Commercial
Rated Rotor
Commercial
IEC Class
Timeline2
IEC Class
Timeline2
(kW/m2)
(kW/m2)
Turbine
Turbine
Rated
Rotor
Rotor
(MW)
2-b Energy 2B6 6 IEC 1 140.6 2015 0.39 Nautica Advance floating turbine 7 - - Concept -
Adwen AD 8-180 8 IEC 1B 180 2018 0.31 Wind Lens 5 - 100 Concept 0.64
Adwen AD 5-116 5 - 116 2012 0.47 Samsung heavy industries
S7.0-171
7 IEC 1A 171 2015 0.30
Adwen AD 5-132 5 IEC S 132 2014 0.37
Seatwirl 10MW 10 - N/A Concept -
Adwen AD 5-135 5 IEC 1B 135 2013 0.35
Seawind 6 6.2 IEC 1 126 2015 0.50
Aerodyn Engineering aM
5.0/139
5 IEC 2B 139 2015 0.33 Senvion 6.2M152 6.2 IEC S 152 2014 0.34
Aerodyn SCD 6MW 6 IEC 2B 140 2014 0.39 Senvion 6.2M126 6.2 IEC 1B 126 2014 0.50
AMSC SeaTitan 10MW 10 IEC 1B 190 Concept 0.35 Siemens SWT4.0-120 4 IEC 1A 120 2010 0.35
H127-5MW (CSIC Haizhuang) 5 - 127 2015 0.39 Siemens SWT4.0-130 4 IEC 1B 130 2015 0.30
H151-5MW (CSIC Haizhuang) 5 IEC 3B 151 2015 0.28 Siemens SWT-6.0-154 6 IEC 1 154 2014 0.32
HQ5500/140 (Hyundai Heavy
5.5 IEC 1B 140 2015 0.36 Siemens Gamesa SWT-7.0-154 7 IEC 1B 154 2016 0.38
Industries)
Envision EN-4.0-136 4 IEC S 136 2016 0.28
Siemens Gamesa SWT-8.0-154 8 IEC 1B 154 2016 0.43
Gamesa Azimut project 15 - - Concept -
Siemens Gamesa D1x 10 - N/A Concept -
4.1 IEC 1B 113 2013 0.41
Sinovel SL6000/155 6 IEC S 155 2017 0.32
GE Haliade 6MW 6 IEC 1B 150.8 2016 0.34
Sinovel SL5000 5 IEC 1A 126 2012 0.40
Protoype in
Goldwind GW154/6.7MW 6.7 - 154 2018 0.36 Sway turbine ST10 10 IEC 1B 164 development 0.47
Taiyuan heavy industry
Goldwind GW164/6.45MW 6.45 - 164 2018 0.31 5 - 153 2017 0.27
TZ5000-153
Goldwind GW171/6.45MW 6.45 - 171 2018 0.28 SUPRAPOWER project 10 - N/A Concept -
Guodian power UP6000-136 6 IEC 1B 136 2012 0.41 Aerogenerator X 10 IEC 1 270 Concept 0.17
Hitachi HTW5.0-126 5 IEC S 126 2016 0.40 XEMC - Darwind XD115-5MW 5 IEC 1C 115 2006 0.48
Hitachi HTW5.2-127 5.2 IEC 1A 127 2016 0.41 XEMC - Darwind XD128-5MW 5 IEC 2B 128 2014 0.39
MHI Vestas V117-4.2MW 4.2 IEC 1B 117 2010 0.39 Generic 4MW 4.0 - 120.0 - 0.35
MHI Vestas V164-9.5MW 9.5 IEC S 164 TBC 0.45 Generic 6MW 6.0 - 154.0 - 0.32
MHI Vestas V164-8.0MW 8 IEC S 164 2014 0.38 Generic 10MW 10.0 - 190.0 - 0.35
Mingyang SCD 6MW 6 IEC 2B 140 2014 0.39
Notes.
Mingyang SCD 6.5MW 6.5 IEC 1 140 2013 0.42 1 This value is based on the nameplate rated power rather than the peak power of the power curve.
2 Estimated commercial availability on the basis of public domain information.
3 This is the rotor productivity at rated power of the turbine.
60,000
Onshore Best
Lower Bound
Upper Bound
50,000
(EUR / MW)
(EUR / MW)
Estimate
Offshore
Offshore
Supply
40,000
Siemens SWT-6-154 Prototype
Vestas V112-3.3MW Prototype
Alstom Haliade Prototype
SWT-3.6-107 Prototype Siemens SWT-3.6-120 Prototype Siemens SWT-4.0-120 Prototype European 950,000 1,000,000 1,400,000
Vestas V112-3.0MW Prototype
10,000
Difference -28% -20% -20%
0
Jan-07 Jan-08 Jan-09 Jan-10 Jan-11 Jan-12 Jan-13 Jan-14 Jan-15 Jan-16 Jan-17
Only WTG orders where contracts have been supplier. With the consolidation of the big players, require significantly larger loads to be resisted If local turbine suppliers in India diversify further
signed to date are included in Figure 6-5 and this narrows the number of WTG OEMs with during operation. However, WTG OEMs have into developing offshore platforms it might be
WTG models with no orders are not depicted. significant offshore operational track record. already developed large offshore wind turbines assumed similar cost savings could be achieved.
It should be noted that prototypes are not included For projects constructed between 2012 and 2018 that are “smarter” using technologies such as As such based-on experience and research
in the analysis; however, they are inserted into the offshore turbine supply market is dominated advanced control strategies, tower dampers and FOWIND has provided indicative turbine supply
Figure 6-5 as milestones. by the Siemens Gamesa group and MHI Vestas, advanced condition monitoring systems. costs per MW for both European WTG OEM supply
with a combined share between 80-90% [45]. and for future localised WTG OEM supply in India.
Since 2013 the number of offshore turbine Furthermore, with the successful offshore cost 6.6 OFFSHORE TURBINE PRICING
suppliers in the market has contracted significantly reductions recently seen in Europe and with For the purposes of this feasibility study (see
through joint ventures, mergers and acquisitions subsidy-free offshore wind bids (excluding grid Wind turbine pricing is inherently site specific and Section 10) overseas supply has been assumed.
with the big players. On the 27th September connection costs) already received in Germany and dependent on a wide variety of costs including This is also in line with findings presented in the
2013 Vestas Wind Systems and Mitsubishi Heavy the Netherlands, the next round of bids in Europe materials, manufacturing, transport and profit Supply Chain, Port Infrastructure and Logistics
Industries formed the MHI Vestas joint-venture, are predicted to feature much larger “1x MW” margin. For the purposes of this study, FOWIND Study [2] where it was anticipated that the first
this was followed on the 2nd November 2015 turbine platforms with MW capacities exceeding has performed a basic bottom up cost modelling projects in India might utilise overseas turbines.
when GE completed the acquisition of Alstom. 10 MW and with rotor diameters more than 200 m. exercise using known information and assumptions
about the supply of turbines in both India and Predicting future cost trends is extremely difficult
Most recently on the 3rd April 2017 Siemens and These larger turbines are critical to meet the Europe. The final price estimates will vary and will depend on a number of drivers of price.
Gamesa completed their merger, and subsequently LCOE targets and as such developers will need substantially and it is essential to directly engage On the whole though FOWIND believes that
on the 26th July 2017 the newly formed Siemens to accept “1x MW” platforms with limited with turbine suppliers to acquire accurate turbine prices are significantly more likely to fall per MW,
Gamesa announced they would integrate Adwen operational hours, but likely from suppliers prices and the costs given here are indicative only. particularly if the global supply picture improves
(originally an JV between Gamesa and Areva) with extensive experience of the design and and a number of new entrants begin offering
within the group’s broader offshore operations, operation of established smaller platforms. With regards to onshore wind, local turbine turbines into the market.
these events have consolidated the groups These larger turbines present challenges with manufacturers in India can supply turbines at
position as the leading offshore wind turbine design, manufacture, construction and will a lower cost than their European counterparts.
Rated Rotor P
0.30
0.45
TYPE G 0.25
20% 22% 24% 26% 28% 30% 32% 34% 36%
Gross Capacity Factor
7. WINDFARM LAYOUT
25%
TYPE C 20%
300 60
0.35 1 5%
10%
5%
TYPE R 270 0% 90
0.30
return, a project in the Tamil Nadu Region will has been assumed for the proposed layout.
have to consider a Type R wind turbine with This layout would be broadly similar for other
a large rotor to a small generator ratio. Based project configurations and wind turbine capacities. 0
on the reasons discussed in section 6.4, the 30%
330 30 A2
FOWIND consortium has only considered wind It should be noted that the proposed layout 25%
turbines that have a Rated Rotor Productivity is preliminary in nature and should be revised 20% 1 2 3 4
lower than or equal to 0.35 kW/m2 and which further based on the onsite measured wind 300 1 5% 60 9 8 7 6 5
10 11 12 13 14
fall under the Type R category. resource and detailed grid studies specific 10% 20 19 18 17 16 15
26 A4
to sub zone A3. An elliptical exclusion zone 5%
21 22 23 24 25
28 27
Three generic offshore wind turbines models around the turbines was generated using DNV GL’s 32 31 30 29
270 0% 90 34 35 36 37 38
of 4MW, 6MW, 10MW have been taken forward WindFarmer software. The ellipse is defined by 33
44 43 42 A 3 41 40 39
for further analysis in this report. These models three parameters:
45 46 47 48 49 50
have been developed using DNV GL’s Turbine.
56 55 54 53 52 51
Architect software, industry trends and input Length of the long axis, in rotor diameters; A1
240 1 20 57 58 59 60 61 62
from DNV GL’s turbine engineering experience. A5
Direction of long axis; 67 66 65 64 63
68
Minimum separation distance (short axis), 73
69 70 71 72
in rotor diameters. 210 150
7.2 S
UB ZONE A3 PRELIMINARY 180
79 78 77 76 75 74
WIND FARM LAYOUT During the wind farm layout design (see Figure 80 81 82 83 84
7-2), the long axis of the ellipse has been aligned
An offshore wind farm layout using the 6MW with the assumed prevailing wind direction (see
and a 154m rotor diameter generic offshore Figure 7-1) in order to minimise both losses due
wind turbine with a 504MW project capacity to wake effects and loads on downwind turbines.
A2
FIGURE 7-3: TAMIL NADU SUB ZONE A3 504MW 6MW OFFSHORE WINDFARM 3D LAYOUT
1 2 3 4
9 8 7 6 5
10 11 12 13 14
20 19 18 17 16 15
21 23 24 25 26 A4
22
31 30 29 28 27
32
34 35 36 37 38
33
44 43 42 A3 41 40 39
45 46 47 48 49 50
56 55 54 53 52 51
A1
57 58 59 60 61 62
A5
68 67 66 65 64 63
69 70 71 72 73
79 78 77 76 75 74
64 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 65
80 81 82 83 84
8. CONCEPT WIND FARM
8.2.2 Wind farm availability responsibility is placed on the transmission system
operator to provide on offshore connection point
This factor represents the expected energy-based to wind farms developed in German Federal waters.
also accounts for delays in the project coming Hub height 83 100 118 83 100 118 (m) MSL
back to full operation following a grid outage. Mean Annual Wind Speed 7.76 7.8 7.84 7.76 7.8 7.84 (m/s)
A typical assumption for generic projects in Gross energy output 587.7 656.6 660.9 1948.6 2206.3 2246.9 GWh/annum
Europe is 99.5 %, however, grid availability Array efficiency1 88.4% 91.3% 92.3% 78.4% 82.3% 81.8% DNV GL estimate
in India could have different behaviours and Wind farm availability2 91.9% 91.6% 91.6% 92.2% 92.9% 94.1% DNV GL estimate
therefore this value should be regarded with Electrical efficiency3 97.1% 97.1% 97.1% 97.1% 97.1% 97.1% DNV GL estimate
caution.
Wind farm performance4 98.0% 98.0% 98.0% 98.0% 98.0% 98.0% DNV GL assumption
Net Energy Output 471 508 498 1502 1661 1627 GWh/annum
High wind hysteresis losses: Wind turbines
Project Net Capacity Factor 35.3% 38.1% 37.9% 30.0% 37.6% 37.1%
will shut down when the wind speed exceeds
a certain limit. High wind speed shut down Notes:
1 Internal wake losses
events can cause significant fatigue loading. 2 Includes assumed Balance of Plant (BoP) availability
Therefore, to prevent repeated start up and 3 Includes array and export cable losses
4 Includes sub-optimal efficiencies (power curve compliance, blade degradation, power consumption, grid availability, etc.
shut down of the turbine when winds are
close to the shutdown threshold, hysteresis is
commonly introduced into the turbine control
algorithm. Where a detailed description of the
8.2.5 Energy production summary given the input data and methods employed.
wind turbine cut-in and cut-out parameters In particular, errors in the long-term wind
are available, this is used to estimate the loss rose will affect layout optimisation, given
The projected energy production for each of the
of production due to high wind hysteresis by the uni-directional nature of the wind rose;
proposed project configurations are is summarised
repeating the analysis using a power curve
in Table 8-1. These results represent an estimate
with a reduced cut-out wind speed. Due to the
of the annual production expected over the Further to the estimated losses, DNV GL has
low wind conditions expected at all sites, the
lifetime of the project assumed to be 20 years. made several generic or typical assumptions
FOWIND consortium has assumed these losses
to be able to perform the present analysis;
to be negligible.
The table includes potential sources of energy therefore, these values must be taken as
loss that have been estimated or assumed. indicative and subject to changes according
Power curve compliance: Wind turbines
to the final plant configuration;
will have some sub-optimal efficiencies when
The methods used to calculate losses, the losses
considering the power curves provided by
for which assumptions have been necessary and The prediction of wake losses for large
the manufacturer. These inefficiencies are
those losses which have not been considered have offshore wind farms is an area of significant
due to different factors such as pitch/yaw
been discussed in this section. It is recommended uncertainty and although a correction has
misalignment, controller performance, etc.
that the various loss factors are reviewed and been applied to the analysis to take account
For this reason, DNV GL typically assumes
considered carefully. of recent operational evidence, it should be
a power curve compliance efficiency
noted that wake models used in this analysis
of 99.5 %.
8.2.6 Energy production estimate may be updated in the future, in light of new
uncertainties analytical developments or empirical data.
After consideration of all the factors mentioned
above, DNV GL has assumed an overall Wind
The following uncertainties have been identified For the purpose of this study, it has been assumed
Farm Performance availability of 98.0% for all
as important to the analysis of the wind farm that there are no planned wind farms in the
different scenarios.
layouts undertaken: immediate vicinity of any of the identified sites.
Given the immaturity of the market it is not
The wind climate predicted by DNV GL in this considered appropriate to account for reduction
study is subject to significant uncertainties in yield due to the presence of other wind farms.
This section provides the outcomes of a preliminary DNV GL has prepared a preliminary schematic
investigation into the electrical layouts of the electrical diagram showing the electrical system for
onshore substation and offshore cabling. It also the onshore substation. This is shown in Figure 8-2.
provides indicative costing and sizing for the
electrical equipment. This conceptual design represents a typical
solution for an onshore substation based on
It is assumed that the Tamil Nadu offshore wind farm the use of standard components. Both active
development will not include an offshore substation. power and reactive power requirements should
The onshore substation will be the central location be considered during detailed design so that
for the collection of energy from the Wind Turbine grid code requirements can be met at the point
Generators (WTGs) located offshore. of connection. Compensation equipment will be
required at the different operating voltages to
For the purpose of the electrical concept design address the capacitive effects of the cabling as
the following configuration has been considered, well as to satisfy the requirements of the grid code.
84 WTGs each of 6 MW capacity. The overall
The normal running arrangement is with all FIGURE 8-2: OFFSHORE SUBSTATION PRELIMINARY SCHEMATIC
installation capacity is therefore calculated as
504 MW. For the remaining project configurations onshore transformers in service. The following
Turbine.Architect has been used to validate and main equipment has been assessed and To 220 kV Tamilnadu Grid (TG)
scale the results from this concept design study. determined as being suitable for the onshore
66 kV array cables have been assumed for all substation configuration: TG1 TG2
in Tamil Nadu, 220 kV is utilised as the operating are recommendations as a preliminary design: BC1
BB2 BB4
BC2
Figure 8-1 illustrates the assumed location of Circuit breaker with a capacity of 3150 Amps
the 504 MW Tamil Nadu offshore wind farm on 220 kV winding
Shunt Reactor-1 Shunt Reactor-2 Shunt Reactor-3 Shunt Reactor-4
~25 MVAr ~25 MVAr ~25 MVAr ~25 MVAr
A1 A2 A3 A4 A5 A6 A7 A8
acceptable limits and thus maintain the power feeder circuit arrangements, connected directly Shunt Reactor-1 Shunt Reactor-2 Shunt Reactor-3 Shunt Reactor-4
~30 MVAr A1 A2 ~30 MVAr A3 A4 ~30 MVAr A5 A6 ~30 MVAr A7 A8 Onshore
quality at the point of common coupling. to the onshore substation. 630 mm 2 Offshore
20 km 630 mm 2
20 km
T1 T12 T22 T32 T43 T54 T64 T74
The requirement should be assessed during Each feeder circuit in this concept design can carry 400 mm 2 400 mm 2
the detailed design stages. a maximum of 66 MW of active power from the 1.5 km 1.5 km
wind turbines. As the maximum normal operating T2 T13 T23 T33 T44 T55 T65 T75
8.3.2.5 Dynamic Compensation current in the wind farm feeder circuit breakers 400 mm 2
400 mm 2
1.5 km 1.5 km
will not exceed 608 Amperes, the 66 kV circuit T3 T14 T24 T34 T45 T56 T66 T76
Grid code connection conditions are assumed breakers with a rated capacity of 1250 Amperes 2 400 mm 2
400 mm
to be applicable at the connection point with are considered appropriate. 1.5 km 1.5 km
the network. It is possible that the wind turbine T4 T15 T25 T35 T46 T57 T67 T77
reactive power range of 90 MVAr (Capacitive/ Sea bed burial, T7 T18 T28 T38 T49 T60 T70 T80
150 mm 2
Inductive) to cover an assumed power factor range J-tube entry, 150 mm 2
1.5 km
1.5 km
from 0.95 lagging to 0.95 leading as well as for Beach crossing, T8 T19 T29 T39 T50 T61 T71 T81
fault ride-through requirements. Connection to the switchgear at the WTG 150 mm 2
150 mm 2
1.5 km 1.5 km
Substation T9 T20 T30 T40 T51 T62 T72 T82
A final network connection study should be carried Jointing at the Onshore Transition Pit 150 mm 2 150 mm 2
out to evaluate the specific rating of each STATCOM. 1.5 km 1.5 km
T10 T21 T31 T41 T52 T63 T73 T83
To provide fibre optic communications between 2
150 mm
8.3.2.6 Auxiliary Systems the WTG’s and Onshore Substations, and 1.5 km
Interlink
Cables
Interlink
Cables
T11 T42 T53 T84
(Optional) (Optional)
An Auxiliary supply for the onshore substation will To withstand the subsea installation process *All Submarine Cables are 3 core Copper Cables
*Each Turbine is assumed for 6 MW capacity
be required. Although auxiliary transformer(s) and without damage.
the cores, which shall be suitable for both data onshore substation. All dimensions are shown
communication and for temperature monitoring in millimetres and are indicative. 10,000
Space for Outgoing Grid Circuits
10,000
of the cable through a temperature monitoring 25,000 40,000 25,000
system. The cable burial depths can vary although Space for harmonic filters and incoming/outgoing
2,000
2,000
for array cable networks 1m is usual. The depth cables are indicative and can be refined in
being dependent upon the marine vessel activity consideration of the physical directions of the
20,000
20,000
20,000
Harmonic Filter-1 220 kV GIS Switchgear room Harmonic Filter-2
in the area and the seabed conditions, particularly transmission interface point and offshore export
where sand waves are present. circuit routing. The overall dimension of the layout
here is 124 x 100 metres.
Interlink cables are optional and can provide
3,000
redundancy in the case of failure of an array cable. There are four onshore grid transformers
40,000
Suitable turbine switchgear and cables should be considered in this design, however this
selected in considering the optimized solution.
18,000
requirement should be assessed during the Space for Access to Substation
220/66 kV Transformers - T1, T2, T3 and T4
Space for Access to Substation
It is to be noted that the indicative cable sizes detailed design phase.
in Figure 8-3 have not considered the inclusion
of interlink cables as full power carrying Environmental noise emissions should also 3,000 Auxiliary
conductors. If full power capability were required, be assessed as local environmental conditions
25,000 40,000 Transformers 25,000
- 1 and 2
this would need to be considered as part of the need to be considered. Cooling Cooling
Tower
detailed design and the cable sizes adjusted Tower
20,000
66 kV GIS Switchgear and Control
The installation is to be compatible with and Valve and Control Rooms Valve and Control
the increased number of WTG’s that would be designed for reliable operation in a coastal/marine Room Room
45,000
45,000
be able to accommodate the required current
VSC VSC
capacity of the full 21 WTG’s being connected. The arrangement of the switchgear bays should
be of a clear and logical arrangement and allow
Reactor-3
2,000
2,000
DNV GL recommends the array cable design
15,000
Reactor-1
Shunt
and 4
adequate accessibility to all external panels and
Shunt
and 2
15,000
Coupling Transformer and Space for Incoming Array Cables Coupling Transformer and
optimisation be carried out as part of the instrumentation. Table 8-2 and Table 8-3 indicate circuit connecting structure circuit connecting structure
detailed design work. the number of bays for the 220 kV and 66 kV GIS
STATCOM-1 8,000 8,000 STATCOM-2
switchgear.
2,000 2,000
This cost includes only the supply cost. It excludes TABLE 8-6: OVERALL EQUIPMENT COST
any cost associated with design, management and
installation. It also excludes the cost of equipment Particulars Cost (Crore INR)
within the wind turbines. Installation costs are Onshore Equipment Cost 490
estimated using Turbine.Architect, see Section 9.1. Array Submarine Cable Cost 413
Total Equipment cost (Crore INR) 903
Cable Voltage
Config Name
WTG Rating
Cables Cost
Installation
(Crore INR)
(Crore INR)
Wind Farm
Interarray
Total Cost
Including
Onshore
(MW)
(kV)
FIGURE 8-6:
VISUALISATION
OF A GENERIC
MONOPILE
(LEFT), JACKET
(CENTRE) AND
GBS (RIGHT),
DNV GL BLADED
The specific values used for these design checks Designs that do not satisfy these criteria are FIGURE 8-7: JACKET MODEL OVERVIEW
are shown in Table 8-8. discarded whilst those that do are assessed
against each other in terms of fabrication cost.
Designs that do not satisfy these criteria are The design with the lowest cost is selected
discarded whilst those that do are assessed as the optimum and put forward for further
against each other in terms of fabrication cost. consideration.
The design with the lowest cost is selected
as the optimum and put forward for further The values used for these design checks are
consideration. shown in Table 8-9. An overview of the jacket
design process is shown in Figure 8-7. Internal
The monopile designs considered are of a form loads in the jacket members are determined using
consisting of an embedded hollow tubular the finite beam element method. Frequency is
monopile connected to a hollow tubular transition assessed using an eigenfrequency calculation.
piece which is surmounted by the tower and Approximations are made as to the level of fatigue
turbine. The transition piece overlaps the exterior and extreme loading contributed to member loads
of the monopile and a bond is formed by grout and pile vertical loads, respectively.
5. The unit costs are presented in terms of Euros however they represent DNV GL’s understanding of local unit cost rates based on experience of
fabrication within the oil and gas industry.
Results for monopile support structures are presented in Table 8-15, Table 8-16 and Table 8-17.
TABLE 8-13: TAMIL NADU SAND SOIL PROFILE FOR FOUNDATION COMPARISON TABLE 8-15: MONOPILE RESULTS 6MW TURBINE
8.4.4.2 Jacket
Results for jacket support structures are presented in Table 8-18, Table 8-19 and Table 8-20.
Mass (tonnes)
400
Jacket cost (mINR) 164,810 162,710
Transition piece cost (mINR) 52,080 52,530 200
Piles cost (mINR) 30,400 17,850
0
Total support structure cost (mINR) 247,280 233,090 4MW 6MW 10MW 4MW 6MW 10MW
Cemented Profile Sand profile
Monopile Jacket
20,000
18,000
16,000
14,000
12,000
10,000
8,000
6,000
Mass (tonnes)
4,000
2,000
0
4MW 6MW 10MW
Cemented profile
300,000
250,000
200,000
150,000
100,000
Cost (kINR)
50,000
0
4MW 6MW 10MW 4MW 6MW 10MW
Sand soil profile Cemented soil profile
Monopile Jacket GBS
availability (%)
configurations
installation of turbines, foundations and electrical a larger number of locations. It’s possible this
OPEX (mINR
per annum)
substations. Turbine and foundation installation effect would be lessened by the installation
Config. no.
Wind farm
strategies depend on the turbine size, the selected period extending over seasons where weather
Project
foundation type, the depth and the selected is less suitable for installation, which is more
metocean climate, the installation module likely to take place with larger numbers of
finds the appropriate vessel and installation turbines. The effect of installation seasonal
T1 150 MW wind farm (generic 4 MW turbine) 1,419 94.3
durations from pre-processed installation data. effects on installation durations has not been
The installation data is a database of simulation considered in the course of this study. T2 150 MW wind farm (generic 6 MW turbine) 1,201 94.3
results from DNV GL’s O2C tool for different
T3 150 MW wind farm (generic 10 MW turbine) 1,041 94.3
scenarios. For electrical substations, the lifts 9.2 OPERATION AND
are more problematic and may require a Heavy MAINTENANCE STUDY T4 504 MW wind farm (generic 4 MW turbine) 4,643 93.8
Lift vessel and as such day rates are very elastic,
ranging by a factor of ten depending on market As the name suggests Operations and
T5 504 MW wind farm (generic 6 MW turbine) 4,036 94.0
conditions. This results in a greater uncertainty Maintenance activities can be divided into T6 504 MW wind farm (generic 10 MW turbine) 3,521 94.0
for offshore substation CAPEX. See Table 9-1 for two main tasks:
the estimated installation and logistics CAPEX for
the different combinations of project capacity and 1. Monitoring, controlling and coordinating
turbine MW for Tamil Nadu’s sub-zone A3. These the wind farm operations; and
results are for monopile foundations which were 2. Maintenance activities of the turbines
selected in Section 8.4. Table 9-2 presents the and the balance of plant (BoP), which are
same information but for turbine installation. typically sub-categorised into; scheduled The access logistics associated with these mean significant wave height at zone A is 1.24 m
and unscheduled maintenance. maintenance activities, are one of the most (Section 5.3.3) and the nearest port Punnakaya
significant operational challenges facing the (13.5 NM away from zone A3) has been used in
offshore wind energy market. Access strategies the O2M analysis. It has been noted that the use
can be categorised into three main types; of helicopters or motherships is not envisaged
onshore-based marine access, helicopter access to prove optimal for most scenarios. The inclusion
and offshore-based marine access. Onshore- of helicopter operations to support wind farms
TABLE 9-1: FOUNDATION INSTALLATION TABLE 9-2: TURBINE INSTALLATION based marine access (e.g. workboats) is the most can be of significant relevance for a large number
CAPEX CAPEX common approach to date, however is heavily of turbines but will prove suboptimal for the rest
restricted by the sea-state during transfer onto of the configurations with a lower number of
the structures. This section presents a preliminary turbines (25, 38 and 84). However, due to the
Wind Farm Capacity
Installation CAPEX
investigation into suitable O&M strategies for significant logistical and regulatory complexity
WTG Rating (MW)
Total installation
Tamil Nadu and estimates for OPEX (Operational added to a project and related to helicopter
CAPEX (mINR)
CAPEX (mINR)
Expenditure). Common access vessels were operations, it has been deemed appropriate
Config Name
Config Name
introduced and minimum typical requirements to rule out these strategies and assume that
for O&M ports are discussed in the Supply Chain, all first offshore wind projects in India will be
(MW)
(MW)
Port Infrastructure and Logistics Study [2] Section based on the most proven work boats access
3.9.5. The top 3 O&M ports considered suitable for methodologies. Considering only workboat access
zone A have been identified, namely; Punnakayal, methods preliminary estimates for OPEX and
T1 152 4 2,100 55.3 T1 152 4 1,870 49.2
Koodankulam and Valinokkam which are 13.5 NM, availability have been presented for each identified
T2 150 6 1,350 54.1 T2 150 6 1,250 49.9 13.5 NM 16.2 NM away respectively. project configuration in sub-zone A3, farm
capacities (150 to 504 MW) and generic turbine
T3 150 10 1,190 79.5 T3 150 10 790 52.9
In order to select the most suitable O&M Strategy MW classes (4,6 & 10 MW).
T4 504 4 6,380 50.6 T4 504 4 5,770 45.8 DNV GL has used its in-house model: “O2M
Optimisation of Operations and Maintenance” The results of the analyses, considering only work
T5 504 6 3,910 46.6 T5 504 6 3,760 44.7
to simulate a variety of O&M strategies at sub boats operations, are presented in Table 9-3 for
T6 500 10 3,180 63.7 T6 500 10 2,220 44.3 zone A3 for each of the project capacity and wind these project configurations under consideration.
turbine capacities. The assumed long term annual
100 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 101
10. OUTLINE 10.1 INTRODUCTION
10.2 METHODOLOGY
AND KEY ASSUMPTIONS
DNV GL’s Turbine.Architect [7] has been used for
the cost modelling calculations. Turbine.Architect
is an automated cost modelling tool that executes
engineering calculations to derive the physical
properties (e.g. section properties, masses and
costs) of the sub-components of a wind turbine, its
support structure and other components of a wind
farm. These engineering outputs are combined with
financial calculations and an economic model to
calculate an overall LCOE.
102 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 103
The following key assumptions and caveats have LCOE
been made and must be taken into account when
viewing the results: Levelised cost of energy (LCOE) is a much-used
number in wind energy analysis, and is calculated
The modelling calculates an average LCOE in Turbine.Architect based on the methodology
for the selected sub-zone based on the used in Section 10.4 as:
parameters of each modelled location
i.e. assuming that the complete project LCOE = ∑ [(CAPEXt + OPEXt + Dt) * (1+r)-t]
exhibits the same water depth, metocean ∑ AEP * (1+r)-t
conditions and wind climate as that defined
at the reference point. The LCOE results can where:
be considered applicable for a wind farm
situated in the sub-zone only if there is no CAPEXt = total capital construction
variation in parameters between the reference costs in year t;
point and throughout the wind farm area. OPEXt = operation and maintenance
The optimised LCOE is representative and costs in year t;
should not be considered to necessarily Dt = decommissioning costs
represent the actual Cost of Energy of in year t;
a realised project. For example, effective AEP = annual electricity production
development and front end engineering by the farm (MWh/annum);
studies can yield a significant reduction (1+r)-t = discount factor for year t.
in cost of energy when compared to the
generalised modelling undertaken here. It is assumed that the discount rate r is stable
during the project lifetime. DNV GL has assumed a
Site climate conditions, such as wave
10% discount rate based on OECD’s guideline that
characteristics, used in the modelling are
a 10% discount rate “[corresponds] approximately
based on publicly available information FIGURE 10-1: TURBINE.ARCHITECT PROCESS
to the market rate in deregulated or restructured
and DNV GL’s preliminary metocean study.
markets” [47].
INPUT ENGINEERING FINANCIAL OUTPUT ECONOMIC
MODELS OUTPUT
CAPEX
10.2.1 Financial Modelling
Total wind farm CAPEX is defined as the sum TURBINE
TURBINE TURBINE
This section provides a general overview of the of turbine CAPEX multiplied by the number MODEL CAPEX
INPUTS
financial modelling methodology, used within of turbines, plus the Balance of Plant CAPEX. CoE
DNV GL for engineering purposes. For this study
BoP FARM
Turbine.Architect has been used to calculate the Turbine CAPEX is calculated by the tool via CAPEX CAPEX
relative financial attractiveness of wind farm a bottom-up approach, combining component SITE
& FARM WINDFARM ECONOMIC
MODEL MODEL IRR
project configurations in terms of LCOE. sizing calculations and material unit costs. INPUTS
GROSS
AEP NET AEP
The calculation of this parameters is achieved by Balance of Plant CAPEX includes the following
NPV
linking several engineering and financial models, elements:
MARKET AVAIL-
as illustrated in Figure 10-1. INPUTS O&M
ABILITY
MODEL FARM
Turbine support structures, as described above;
OPEX
Electrical infrastructure:
Array cabling; DISCOUNT
Export cabling; RATE
Offshore substation;
Installation of all components; TAXES,
Project costs. SUBSIDIES
9. Decommissioning costs have not been included in the modelling; however, as these costs are incurred at the very end of the project life, their net present value
is very small and their impact on LCOE is typically less than 1%.
104 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 105
10.3 TURBINE.ARCHITECT on publicly available information to calculate 10.4 PROJECT COST ESTIMATES 10.4.2 OPEX Comparison
INPUT PARAMETERS preliminary LCOE estimates. Regional conditions
in Table 10-1 have remined constant during analysis. Total annual OPEX is presented in Figure 10-3
DNV GL has used its offshore Cost of Energy Turbine and project configuration parameters 10.4.1 CAPEX Comparison for each wind farm capacity and turbine rating.
(COE) model with site condition information based in Table 10-2 and Table 10-3 have been varied.
Figure 10-2 presents a comparison of CAPEX
for the following items:
TABLE 10-1: REGIONAL CONDITIONS FOR PROJECT COSTING Turbines & towers; Electrical; and
Foundations; Development costs.
Tidal level HAT 0.8 m
50-year maximum wave height 11.0 m
50-year storm surge elevation 1.4 m
FIGURE 10-2: PROJECT COSTING: CAPEX COMPARISON
Annual mean significant wave height 1.24 m
Wind climate Weibull shape factor 2.0 60,000
Wind shear calculation method Roughness wind shear
Roughness height 0.001 m 50,000
40,000
Rating 4 MW 6 MW 10 MW 20,000
Rotor diameter 120 m 154 m 190 m
Capex (mINR)
Hub height 83 mLAT 100 mLAT 118 mLAT 10,000
RNA mass 205 tonnes 365 tonnes 605 tonnes
Drive train configuration Geared Direct drive Geared 0
4MW 6MW 10MW 4MW 6MW 10MW
Wind speed and turbulence class 1B
152MW 150MW 504MW 500MW
Cut-in wind speed 3 m/s Turbines Electrical Foundations Devex
Cut-out wind speed 25 m/s
5,000
TABLE 10-3: PROJECT CONFIGURATIONS FOR PROJECT COSTING
4,500
4,000
WTG Rating
Connectivity
Foundation
Inter-array
Wind Farm
Capacity
Electrical
3,500
Concept
Voltage
Config
Name
Cable
(MW)
(MW)
(kV)
3,000
2,500
T1 152 4 Monopile 66
500
T5 504 6 Monopile 66
T6 500 10 Monopile 66 0
4MW 6MW 10MW 4MW 6MW 10MW
152MW 150MW 504MW 500MW
106 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 107
10.4.3 Annual Energy Yield Comparison 10.4.4 Cost of Energy Summary
FIGURE 10-4: PROJECT COSTING: ANNUAL ENERGY YIELD COMPARISON FIGURE 10-5: PROJECT COSTING: COST OF ENERGY
1,800 12,000
1,600
10,000
1,400
1,200 8,000
1,000
6,000
Annual Energy Yield (GWhr)
800
600 4,000
LCOE (INR/MWhr)
400
2,000
200
0 0
4MW 6MW 10MW 4MW 6MW 10MW 4MW 6MW 10MW 4MW 6MW 10MW
152MW 150MW 504MW 500MW 152MW 150MW 504MW 500MW
TABLE 10-4: 150MW TO 152MW WIND FARM COST OF ENERGY MODELLING RESULTS
Total annual energy yield is presented in Figure 10-4 6MW to 10MW. In the case of the turbines
Devex (mINR)
annum mINR)
Configuration
for each wind farm capacity and turbine rating. assumed for this study, the 4MW and 6MW
LCOE (INR/
AEP (GWh/
Foundation
OPEX (per
configurations are based on commercial models,
Electrical
annum)
Turbine
Turbine
CAPEX
CAPEX
CAPEX
(mINR)
(mINR)
(mINR)
The contributions of each wind farm element whereas the 10MW design is conceptual; the
Rating
Name
MWh)
(turbines, foundations, electrical BoP) to the rotor diameter chosen for the 10MW turbine
total CAPEX is shown in Figure 10-2. The results is based upon the power density of typical
T1 4MW 9,965 3,660 6,230 8,500 14,270 1,419 471 (Figure 10-5, Table 10-4 and Table 10-5) show that current commercial offshore wind turbines.
increasing the array capacity from a small scale The power density of the 4MW and 10MW
T2 6MW 8,515 3,470 5,450 7,100 15,210 1,201 508 150 MW “demonstration” project to a larger 500 turbines is somewhat higher than that of the 6MW
T3 10MW 7,675 3,080 5,250 4,400 15,060 1,041 498 MW “utility-scale” project will yield some cost machine, hence the 6MW turbine will exhibit better
of energy benefits. Although larger wind farms low-wind performance. In a relatively low-wind
typically exhibit lower array efficiency, due to environment, such as Tamil Nadu, this will be
impact of wake accumulation on the downstream manifested as an increased capacity factor, and
TABLE 10-5: 500MW TO 504MW WIND FARM COST OF ENERGY MODELLING RESULTS turbines; the impact of this effect is minimised hence increased energy production for a given
in higher wind climates such as that at the Tamil installed capacity; this in turn contributes to
Nadu site. Accordingly, in this study, the reduction a lower cost of energy. If the modelling undertaken
in array efficiency from the smaller to the larger for this study were to be repeated using three
Devex (mINR)
annum mINR)
Configuration
project is not sufficient to counter the benefits conceptual turbine designs of equal power density,
LCOE (INR/
AEP (GWh/
Foundation
OPEX (per
Electrical
of increased scale, in which costs such as vessel the reduction in cost of energy with increasing
annum)
Turbine
Turbine
CAPEX
CAPEX
CAPEX
(mINR)
(mINR)
(mINR)
mobilisation and onshore facilities are shared over turbine size from 6MW to 10MW would be
Rating
Name
MWh)
a larger number of units and hence the effective expected to be more pronounced. This also
cost per unit is reduced. presents a useful note with regard to the
T4 4MW 9,087 10,050 20,060 12,900 46,880 4,643 1,502 development of offshore wind in low-wind
The results also show that increasing turbine size environments, in that the deployment of turbines
T5 6MW 7,832 9,920 17,670 11,400 50,660 4,036 1,661 results in decreasing cost of energy; the effect with a lower power density (i.e. a larger rotor
T6 10MW 7,362 9,270 16,720 8,700 49,760 3,521 1,627 is particularly noteworthy in moving from a 4MW for a given generator capacity) may contribute
WTG to one of 6MW capacity, but less so from to a lower cost of energy.
108 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 109
Figure 10-5 shows that the cost of energy from turbine size also increases turbine supply cost. Very large turbines may require construction include larger turbines and improved pile design
an offshore wind farm reduces as turbine size However, in general, the combination of reduced infrastructure that is either not available in some methodology, and contribute to the reductions
increases; this mirrors general industry experience expenditure and increased energy production locations, or significantly limited in its availability; in cost of energy that have been seen in recent
to date, primarily in European waters, in which results in a lower overall cost of energy – as can selection of these turbines may then result in an European offshore wind auctions. Similarly, as
technological development of larger commercially- be seen from the results, increasing the capacity undesirable increase in procurement and delay supply chains mature and production volume
available turbines has been the most significant of the wind turbines from 4MW to 10MW results in risk. In such a situation, smaller turbines may increases, the unit price of turbines is expected
driver behind the notable reductions in cost of a cost of energy reduction of approximately 23% reduce the risk premium to outweigh some of the to reduce, and industry evidence appears to
energy from utility-scale offshore wind farms. (152 MW project config.) and 19% (504 MW project cost of energy deficit and hence merit selection support this.
config.). for a project. In addition, the use of existing,
Increasing the size of turbines results in fewer proven technology, such as a commercial turbine The modelling approach has also been developed
units being required for a given wind farm Some of the factors affecting cost of energy model that has an established track record, may and refined, tracking industry developments
capacity; this in turn results in less foundation are project-dependent, and the selection (and reduce investor risk such that the cost of financing but also with the focus on particular sub-zones
steel, fewer installation operations, and fewer O&M hence quantification) of these would have to be for a project is lower and, again, the apparent enabling more project-specific system modelling,
transits, all of which contribute to a lower total completed as part of the project development cost of energy deficit is outweighed. Deploying such as in dedicated electrical system studies
CAPEX and lower annual OPEX. In addition, larger process; furthermore, early projects which new, unproven technologies typically brings an which yield a significant reduction in the estimated
WTG rotors reach higher, to where wind speeds are perhaps are smaller in scale or closer to shore increased cost of financing, as lenders or investors electrical CAPEX versus that calculated in the
typically higher, and hence larger turbines would may offer the opportunity to utilise lower-cost allow for increased risk, which for project-financed Pre-feasibility Study. Local fabrication has been
be expected to yield a higher capacity factor and infrastructure. For example, smaller wind farms developments may significantly reduce the returns considered for WTG and OSS substructures, hence
higher total AEP than an equivalent wind farm with short offshore export distances may be able to the developer. a -15 to -18 % reduction in fabrication rates per
comprising more, smaller, turbines. It should be to export power via medium-voltage cables direct tonne has been assumed compared with typical
noted that increasing turbine size typically results to the onshore grid, without requiring an offshore The estimated cost of energy reported in this European rates.
in cost increases for turbine supply, as shown in substation platform and high voltage cabling; this study is lower than that calculated in the Pre-
Figure 10-2; this is due to the scaling effect of would likely be a less costly alternative, however feasibility Report [1], which is a function of a In emerging offshore wind markets, such as India,
larger rotors, in which turbine loads scale with the increased cable installation costs and electrical number of both technical and economic factors. investors or lenders may demand a higher risk
the square of the rotor diameter, and structural losses would render such an option unfeasible premium. Therefore, a high discount rate (used
requirements which mean that blade structure, for a large project. The focus on the most economically-optimal sub- in the Pre-feasibility Study) has been applied
towers etc. scale with the cube of rotor diameter. zone within a designated zone means that the in the economic module of the model. As offshore
Whilst the calculations detailed in this section project and site parameters are more specific, and wind becomes a more established, mature industry
Technology developments, such as direct drive show that increasing turbine size reduces the cost the impact of the less-suitable areas of the zone and asset class, it will attract lower-cost financing
transmissions or novel materials, can help reduce of energy, there are potential advantages will have been removed. Industry practice has also (i.e. lower discount rate seen in European
the rate of cost increase with scale, however the to deploying smaller turbines. developed in the time between the Pre-feasibility markets) and discussion with potential financing
wind industry has seen in practice that increasing Report and this study; such developments organisations would be recommended.
110 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 111
11. OUTLINE PROJECT
TABLE 11-2: QUALITATIVE ASSESSMENT OF MAIN RISKS AND POTENTIAL MITIGATION MEASURES
No#
Uncertainty
Description
A proper defined
of the wind permitting and consenting cause delays in the permitting and
regulatory regime for the EEZ in India. approval process and/ consenting process
11.1 INTRODUCTION regime This leads to a number of or the installation based on suitable
1 uncertainties with regards to process with financial regulatory framework
Table 11-2 undertakes a qualitative assessment of the consenting schedule and consequences on the forms the basis for
When planning offshore wind farm projects, technical requirements for off- overall project budget. any offshore wind
all decisions have to be made regarding future the main risks identified in this report, incorporating
and onshore construction. development and needs
actions, although outcomes cannot be foreseen potential mitigation measures. It should be noted to be setup upfront.
with certainty due to incomplete information. that all of the risks listed in Table 11-2 are zone Wind Uncertainty At this stage of the project wind A high uncertainty It is common practice
This uncertainty associated with all business related risks that would generally apply but given resource of the wind resource assessments are based of the wind resource to conduct a site
activity is defined as risk. Therefore the aim of the high level information obtained for the Tamil resource on mesoscale modelling. This assessment can have specific wind potential
Nadu region to date, the uncertainty is considered assessment data are generally associated significant financial analysis and energy
this chapter is to provide a high level qualitative
assessment of the principal risks for the potential high. It should be considered non-exhaustive 2 with a relative high uncertainty. consequence for the yield assessment based
project. on long term wind
offshore wind farm zones identified in Tamil Nadu. but nevertheless a starting point for project risk measurements on the
It is important to ensure that significant risks are consideration. Table 11-1 offers an overview of risk proposed offshore wind
managed and mitigation measures are identified. levels, categories and actions required. farm site.
Metocean Uncertainty For the design and the This may impact the To reduce uncertainty a
climate of the wave installation of the offshore wind foundation design, detailed metocean site
(water) and current farm it is important to fully project costs and project condition assessment
data comprehend the oceanographic timeline. is recommended and
11.2 HIGH LEVEL QUALITATIVE ASSESSMENT conditions in the proposed area. should be combined
3
OF MAIN TECHNICAL RISKS In particular high tidal currents with a validation period
have been identified in several from on-site data.
areas around river estuaries in
TABLE 11-1: RISK LEVEL AND CATEGORY the Tamil Nadu region which
need to be considered.
Bathymetry Uncertainty The data gathered during the High uncertainty of After the selection
Risk Level Risk category Action required of the bathymetry desktop study are the bathymetry data of potential offshore
bathymetry associated with a relative high could have significant wind farm sites on-site
LOW Acceptable
Low risk level. No risk mitigations required. Check that 4 assessment uncertainty. consequences on the bathymetry surveys are
no other risks can be eliminated. foundation costs. required to be carried
Risk identify that will require mitigation measures. out.
Reduce risks as low as reasonably practical (ALARP); Geotechnical There is The results of the conducted Geological data are Detailed geotechnical
Might be reduced
MEDIUM to ALARP
Consider alternative design or construction method; conditions only limited desktop study of the geology essential for the and geophysical site
If alternatives are not available, specify precautions information of the Tamil Nadu region shows design of the WTG and surveys are to be
on the that only limited suitable data substation foundation. conducted in a later
to be adopted.
seabed for planned offshore wind region The limited availability of project stage to reduce
Potential major impact. Mitigation is required. Seek geology of exist. suitable data increases the uncertain in the
HIGH Not acceptable alternative solutions or if alternatives are not available, 5 the Tamil the uncertainty in the foundation design
specify precautions to be adopted Nadu region design process of the process.
available foundation and could
have a significant
influence on the
foundation costs.
Soil The soil The current desktop study for A high level of very If jack-up vessels are
conditions conditions the proposed offshore wind loose sand may limit the considered as part of
and Jack-up on site farm zones shows loose sands at suitability for jacking the offshore installation
vessels indicate certain location. Jack up vessels operations on site. concept, a full site
6 loose sands usually required for jacking specific assessment for
at certain operations require firm soils. the proposed offshore
locations wind farm site is
required.
112 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 113
No# No#
& &
Risk Issue Risk Description Consequences Mitigation Risk Issue Risk Description Consequences Mitigation
Level Level
Ports and Uncertainty The conducted desktop study on This may impact the It is recommended Turbine Technology The technology of offshore Technology related Given the current status
logistics of the port suitable construction and O&M sub-zone selection for to conduct a full port Technology risk wind turbines is still immature turbine breakdowns of production and
assessment ports in the Tamil Nadu region the potential wind farm assessment including in case of larger capacities. can cause a significant commercial experience
7 is based on a limited number of developments. site visits in a later Hence choosing a large reduction of the turbine of large scale offshore
available data. project stage to reduce capacity turbine can be risky. availability. wind turbines with 5
uncertainty. 13 Furthermore, wind turbine MW and above. Turbines
Ports and Availability So far only a limited number The general availability Medium To ensure that technology has not been tested with a suitable track
logistics of suitable of the offshore wind activities of suitable installation installation capacities in Indian offshore conditions. record should be
(vessels) installation can be observed in the APAC vessel can have a are available to chosen to reduce the
and O&M region which leads to a reduced significant influence on acceptable costs it is technology risk.
vessel availability of specialist offshore the overall installation recommended to start Grid Grid These existing transmission Unavailability of adequate For large GW scale
8 wind installation vessels. time schedule and negotiating installation connection availability infrastructures may be utilised to
cover small scale offshore wind
grid infrastructure and
grid reliability reduces
offshore wind farm
projects new or upgraded
The availability of suitable budget and may require contracts in ample time.
vessels from the oil and gas mobilization of suitable developments in Tamil Nadu, but the amount of electricity transmission infrastructure
not for large scale deployment of feeding into the grid. will be required. A sufficient
industry is highly dependent on
demand and is subject to high
vessels from Europe. 14 offshore wind power plants. test programme of the grid
fluctuations. infrastructure should be
simulated in advance to
Shipping Marine High density of shipping traffic This may risk vessel Is it recommended to avoid shut downs during
traffic traffic identified within some of the collisions on the conduct a full navigation operation.
development zones. potential wind farm safety assessment
9 developments. including impact of new
Installation Weather
down time
Weather down time needs to be
adequately considered in overall
Not considered weather
down time could lead to
It is common praxis within
the industry to calculate
developments on marine project schedule. In particular the higher lead times and the weather down time
safety. impact of the summer monsoon increased project costs. based on statistical
Environmental Uncertainty Construction activities in The occurrence of Piling noise can be 15 period on the turbine availability has weather. However, there is
and Social on the breeding and feeding seasons migrating birds and reduced with bubble not been thoroughly assessed. still a risk that the weather
Impact outcome of may impact marine life. marine mammals in the curtains or using down time is above the
Assessment the ESIA proposed offshore wind vibration technologies statistical norm.
(ESIA) farm zones can have instead of hydraulic Installation Availability The monopile is one of the preferred The availability of suitable The availability of suitable
significant consequences hammer. of suitable WTG foundation designs. The equipment can have a equipment needs to
10 on the construction The impact on installation
equipment
diameter of the monopile designs
for up to 30m water depth can
significant influence on the
installation time schedule
be considered in the
foundation design phase.
schedule and the migration of birds
installation methodology, and marine mammals
16 exceed 6 m. The size of a hammer and budget. Installation equipment
e.g. piling with noise can be mitigated required to drive such monopiles are contracts are to be
mitigation measure could by programming currently limited in availability. negotiated right before the
be required. construction activities start of the installation.
suitably. CAPEX Uncertainty The project CAPEX are estimated The project CAPEX can It is recommended to
of CAPEX based on DNV GL’s experience vary significantly from the update the CAPEX cost
Health, Health and Working in an offshore Injury to persons, A high safety culture is from previous projects and may be estimated figures depending model in a later project
safety and safety risk environment represents extensive damage essential to ensure the 17 subject to significant changes. on parameters of the final stage considering the final
environment an event with significant to structures and project success without offshore wind location and offshore wind farm layout.
requirements on man and systems and delay to having severe incidents. layout.
material. In particular project, pollution of the A health, safety
11 considering that the offshore environment. and environment
OPEX Uncertainty Considering the available project The OPEX can vary It is recommended to
of OPEX parameters the OPEX are relatively significantly from the update the OPEX cost
wind industry is relatively management system is
young industry compared to to be considered as an 18 uncertain and may be subject to estimated figures depending model considering the final
significant changes. on the final offshore wind layout of the proposed
established industries like important cornerstone project parameters. offshore wind farm.
offshore oil and gas. of a H&S culture.
DecEx Uncertainty Based on the current development The decomEx can The decomEx should be
Electrical Uncertainty The data gathered during the The uncertainty of The available of decomEx stage of the offshore wind zones, vary depending on included in the financial
design & of the conducted desktop study are potential grid connection information needs to be the decomEx can only be estimates the final installation model as a share of the
engineering electrical subject to high uncertainty. point may cause verified to reduce the with a high uncertainty. and decommissioning CAPEX.
design changes in the electrical existing uncertainties 19 methodology. Offshore decommissioning
12 design and layout with works are assumed to be
significant consequences similar, in cost and effort to
on project costs and the the installation work.
overall project schedule.
114 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 115
12. ENVIRONMENTAL
AND SOCIAL
IMPACT REGISTER
12.1 INTRODUCTION 12.3 KEY PRINCIPLES
The FOWIND Pre-feasibility Study for Tamil Nadu The environmental impact assessment (EIA)
[4] included chapters on Environmental and Social needs to consider all potential impacts, with
Impact that discussed the potential impacts of the scope including:
offshore wind projects, regulatory mechanisms
and protocols for planning consent. All elements of the offshore wind farm (OWF)
development:
This section discusses the scope, key principles The offshore wind farm site: the offshore
and best practice for Environmental and Social turbines and their support structures,
Impact Assessments (EIAs). Key biological, physical meteorological masts, array cables,
and human aspects are discussed. offshore substations (topsides and support
structures), scour protection;
12.2 SCOPE OF ENVIRONMENTAL The export cable corridor from the OWF
AND SOCIAL IMPACT to the shore including any inter-tidal zone;
ASSESSMENTS Onshore facilities: onshore export cable
route and substation; operations base.
The European EIA Directive requires an
All stages of the project timeline: construction,
Environmental Impact Assessment (EIA) for
operation and decommissioning phases.
certain types of development. In practice
There may be separate EIAs required for
these always apply to large offshore wind
pre-construction work such as erection
farms. Similar legislation applies worldwide.
of met masts and site investigations.
The EIA is required to assess and list the “likely The potential impact on the biological and
significant effects” on the environment and physical environment, on other human users
to consider and describe mitigation measures of the sea, and socio-economic impacts such
to prevent, reduce and offset the negative effects as employment.
and finally to summarise the residual effects. Positive and negative impacts, and proposed
The resulting Environmental Statement forms mitigation measures to address potential
the basis of the permit application. negative impacts.
In this section, the key principles and scope of Plans for monitoring programmes.
typical EIAs for offshore wind farm developments The assessment will typically include:
are described, with focus on major potential issues
and methods of mitigation. Desk-studies and, if warranted, more detailed
survey work to provide baseline data.
Stakeholder engagement: consultation
with the public and with interested parties.
116 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 117
From the developer’s viewpoint, the EIA will need Through the envelope approach, each
to consider the environmental risks in relation to environmental impact is assessed according
the other key drivers of engineering feasibility and to the maximum adverse scenario within the
technical risk, economics, wind farm energy yield, envelope of parameters. For example, the options
and Health & Safety. These will be outlined in the may be a large number of small turbines; or
submitted documents to provide context. a smaller number of large turbines. Some impacts
may be most sensitive to the highest tip height,
At the start of the EIA process, there may whereas others may be more sensitive to the
typically be an initial scoping phase to agree number of turbines, and they are assessed
with the authorities which areas require detailed accordingly. Part of the protocol of this approach
consideration. The intention is to ensure is that the developer communicates with the
appropriate levels of time and effort are authorities when decisions within the envelope
spent on the EIA. become more firm or options are ruled out.
Typically, the permitting process may be split up, 12.5 BIOLOGICAL ASPECTS
for example with separate applications for the
offshore wind farm site, for the offshore export Biological aspects of the EIA will cover all relevant
cable route and for onshore facilities. The following species of flora and fauna. The presence of species
descriptions focus on the offshore aspects. may be very location-specific and any impact is
often species-specific.
12.4 ENVELOPE APPROACH
In Denmark, the initial Danish offshore wind
In many established offshore wind regulatory programme selected sites in the North Sea Marine mammals (seals, dolphins, whales etc); Sound levels are not thought to ever reach
regimes, it is accepted that the exact details of (Horns Rev OWF) and in the Baltic (Nysted and magnitudes considered to be lethal [52]. The
the proposed OWF are not yet determined when OWF), enabling the effects on the species impact occurs mainly during construction,
Birds (sea-birds or migratory species).
planning permission is granted. The developer’s found in the different Danish waters to be though to a lesser extent from marine traffic
application therefore defines a range (or envelope) explored, with extensive reporting of the during all stages of the life of the project. The
Sensitive flora and fauna in coastal and inter-tidal
of parameters to be considered, sometimes findings [48] and ongoing work [49]. severity during construction depends on the
habitats should also be considered, primarily
referred to as the “Rochdale Envelope”. choice of foundations, with the most noise
In UK, the COWRIE project between 2005 and regarding the route and land-fall of the export
created by piling (of monopiles or jackets).
2010 produced a large body of collaborative cable. Standard onshore EIAs for onshore facilities
By this process, the design of the project is Position papers [54] [55] describe mitigation
research [50] and led to the creation of the and onshore cable route may also be needed,
allowed to evolve during the development measures that include project-specific
ongoing Marine Data Exchange portal [51] for and are generally separate from offshore permits.
phase; the developer can take advantage of new conditions to avoid piling at critical times or
sharing of data collected under the permitting In addition to assessments of potential injury
technologies becoming available to the market, dates, such as the fish spawning season; use
process. Results of UK post-consent monitoring or mortality to the species, consideration is made
and can make final technical choices as more of acoustic deterrent devices (“seal-scarers”)
programmes were reviewed by MMO in 2014, of the disturbance to different behaviour which
detailed site data is amassed, thus benefitting and soft-start of the pile-hammer to give
and incorporated non-UK findings [52]. may be seasonal (feeding, breeding, migrating,
the economics of the project. animals the chance to move away; use piling
resting, commuting to and from feeding areas).
In Germany, ecological aspects were studied technology which create lower noise levels;
Typical parameters that may not be finalised comprehensively at the Alpha Ventus and noise reduction through mufflers and
Designated sites of international, national and
until nearer to construction can be: demonstration project [53] and ongoing bubble curtains. A marine mammal protocol
local biological conservation importance will be
studies continue largely through the BFN, the may be adopted using observers and passive
identified in the EIA and may require additional
Turbine capacity and dimensions; federal bureau for nature conservation. acoustic monitoring equipment to ensure the
provision.
surrounding area is clear of marine mammals
Number of turbines and their exact locations The main wildlife communities potentially affected
prior to commencement of piling.
within the site area; will be: Common considerations required for offshore
wind projects are:
Foundation type and details (e.g. jacket, Benthic communities (flora and fauna Studies have shown no evidence of
suction bucket or monopile); in the surface layers of the seabed); disturbance caused by the operational noise of
Noise impact on fish and sea mammals.
Fish (commercial or otherwise); turbines [52].
Offshore transmission structure design For OWFs, the main impact of noise and
(array cable voltage, design of offshore Reptiles (turtles etc); vibration is disturbance and displacement,
substation, detailed export cable route). or in the worst case injury to sea mammals.
118 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 119
Influence on fish and fisheries. It is generally habitats for fish, whilst there is no discernible Influence on birds. In general, sea-birds higher incidence of food around the structures
assumed that fish will be only temporarily evidence of vessel noise deterring fish tend to avoid wind farms, though there is and the refuge from shipping lanes.
disturbed during the construction phase as [52]. It is known that fish may be sensitive some evidence from Denmark that over time,
they can easily move away, provided noise- to electromagnetic fields (EMF), such as birds adapt and return [Ref 2013 follow-up
12.6 PHYSICAL ASPECTS
mitigation measures are in place such as around power cables. However, there is little study]. The main potential effects are loss of
soft-start piling. Any disturbance will only evidence that fish behaviour is changed, and habitat; disruption to movement for feeding
The main factors to be considered are:
be significant if spawning grounds of a fish the EMFs will be small for buried cables [52]. or breeding; barrier effects to migration; and
species are disturbed. In this case, mitigation collision with turbines. The effects can vary
Water pollution, such as from fuel spills or
generally requires avoiding construction according to the species, and they need to
Influence on other sea-life. Depending on discharges of hazardous materials. Compared
during the spawning season. be assessed separately. Moreover, if multiple
the location, there may be populations of with oil and gas facilities there are far fewer
projects are to be built in the same area,
seabed worms, shell fish, turtles, etc. Seabed potential hazards from offshore wind projects,
During the operational phase of the OWF, the cumulative effects need to be assessed.
surveys are done by grabs and trawl surveys, and the severity of any incident is much lower.
fish monitoring has shown some positive
and video and stills photography. Localised Bearing oils and transformer fluids are present
reef effects with the OWF providing more When monitoring birds, methods that
benthic populations may need to be avoided. in small quantities that should be contained by
minimally disrupt the birds are preferred.
best practice in design. Fuel and other fluids
The early technique of observation from
in construction and maintenance vessels are
boats is largely being replaced by digital
addressed by good practice design and operation.
aerial photography from high above, together
with improvements in identification methods.
Waves, tides and currents should be assessed for
Radar methods are also used, particularly
potential effects by the OWF. However, monitoring
for tracking migrating birds.
at early OWFs has shown little effect [52].
Intertidal zones. Where export cables make
landfall across sensitive habitats such as salt Sediment movement and coastal processes.
marshes or mangroves, standard cable burial There are often likely to be temporary increases
techniques may cause unacceptable disruption in suspended sediments during construction,
to sensitive plant life and feeding or breeding from the levelling of seabed or burial processes
habitats of birds and other species. Mitigation or cables. Knowledge of the mobility of the seabed
measures include project-specific protocols is required from records of sand waves and water
to avoid certain dates or techniques such depths over time, to indicate likely changes during
as horizontal directional drilling (HDD) or other the life of the project.
specialised equipment to minimise the impact.
Sea-bed mobility and scour around foundations
The cumulative effects of multiple projects
or cables should be regularly surveyed, especially
in an area need to be assessed. Disruption
with sandy seabed that is historically mobile
during a single season may be acceptable
with sand-waves and shifting sand banks.
to a wildlife population that is temporarily
Monitoring is generally done for engineering
displaced and can quickly recover. However,
purposes, to check whether cables or foundation
disruption over multiple seasons, and over
structures are becoming exposed and whether
a wider geographical area may not be
scour protection needs to be added.
acceptable or need additional mitigation.
Positive effects of offshore wind farms can
be provision of marine habitats, for example 12.7 HUMAN ASPECTS
rock placed for scour protection around
subsea foundations may provide refuges and 12.7.1 Seascape, landscape and visual
nurseries for juvenile fish if the surrounding
seabed is otherwise barren. There is evidence The assessment will typically include visualisations
[56] [57] [58] that marine mammals are of the proposed Project from selected points
attracted to offshore wind structures (and also on the shore in daylight, and also the impact
other offshore structures), taking advantage of of aviation lighting on the night sea-scape.
120 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 121
The influence of the new Project is compared with Non-windfarm vessels may be excluded from Public opinion tests. Typically, information 12.8 RECOMMENDATIONS
the existing nature of the seascape. Similarly, the the site during the construction phase, though is made available to the local public online
effect at shore of any sound warning systems will movement of smaller vessels may be allowed and via events and local information points Building on the global experience of offshore
be assessed. within the OWF during the operational phase. (typically libraries and local authority facilities). wind development, the following approaches
Clear navigational aids are needed for all The information may include non-technical to the Environmental Impact Assessments (EIAs)
12.7.2 Marine artefacts weathers. briefing notes and consultation reports. and the permitting process are recommended:
Oil and Gas facilities (platforms, well-heads Local media. Local media will typically take
The assessment will consider typically: Setting up a single authority to coordinate all
etc). This consideration can include buffer zones interest in the development and should be well
around existing facilities, access by boats and/or briefed to prevent the publishing of incorrect the permits and consultations required, and
Cultural heritage and marine archaeology: providing a single contact point for developers.
helicopters to the facilities, and the potential for or unhelpful information. Local media may also
wrecks of archaeological significance, other This has been done in the expansion of NIWE
future facilities. be used to inform the public of the development
heritage sites such as sunken villages. These to cover offshore wind and act as a conduit
and where to find consultation information.
may need to be left undisturbed with localised Aviation, Defence, Radar and Telecommunications. for applications and clearances.
exclusion zones. Measures may be needed to mitigate potential Engagement of politicians. As part of the
radar and telecommunications disruption by the stakeholder engagement and a key objective. Initial data gathering by central authority
Wrecks, unexploded ordnance (UXO), and - for example geophysical surveys, initial
moving turbine blades. Aviation lights are fitted
potentially other dumped objects that may Green and environmental organisations. geotechnical data, tidal, wind and wave
as required to selected turbine nacelles at the
be hazardous to the Project or related activities. Again, this would be part of the general measurement - with the results made available
edges of the OWF. In Germany, turbine blades
The objects may need to be removed, or avoided stakeholder consultation. The environmental to potential bidders at the pre-tender stage.
are required to have red tips for greater visibility
if left in place. organisation may have a general scope This reduces the risk to the developers and
to aircraft. Access to certain areas may be
(e.g. Natural England in the UK) or could the cost could be refunded by winner. This
Cables and pipelines, either disused or active. restricted due to defence-related activities.
be more specific (e.g. Royal Society for the is in progress (wind resource) and planned
Even if known, routes may not be charted exactly.
Extraction (minerals, gravel etc.). The extraction Protection of Birds in the UK). (ground conditions).
In practice, some marine artefacts may only be
of sand and gravel is necessary for a number
discovered during detailed site investigations. Employment. Offshore wind energy may bring Enable pre-application dialogue between
of onshore activities including land reclamation,
considerable job opportunities to the local area, developer and the permitting authorities
beach nourishment and construction. There
12.7.3 Other users of the sea is typically only limited scope for co-existence
both during construction and operational phases. to ensure appropriate scope and depth
This is generally put forward as a key benefit of of each application.
with offshore wind energy and extraction has
Typically, this aspect of the assessment will offshore wind.
historically taken precedence, though this may Allow an envelope approach in permit
consider primarily the impact of the offshore Port infrastructure. Local ports may be used
be location-specific. applications to give flexibility to the developer.
wind project on other users, whilst taking into as construction and/or operations and
account any impact of other users’ activities Leisure amenity. In some locations, sailing and Use a transparent process with submitted
maintenance hubs. As such, they may require
on the offshore wind project. Early consultation other leisure activities may share the sea with documents and responses in public domain.
upgrades for this use, which could have benefits
is important. the project. Sailors are unlikely to be affected by
for other port users and the ports themselves. Employ sufficient staff and resource to
wind turbine wakes since wind turbine rotors are
at least 20 m above the water. Generally, these Transmission infrastructure. Ideally, an offshore avoid delay in addressing applications; and
Fishing. The relationship of the Project to fishing
other users are allowed within the OWF area, wind will connect to a pre-existing strong grid subsequently to ensure compliance with
grounds and fishing activities is assessed, in
though must not land on the OWF structures point (an existing or decommissioned power the permitting conditions.
addition to consideration of any impact on fish
stocks. There may be restrictions to fishing except in emergency. Although the wind farm station, for example). However, there may be Require standard methodologies for
activities during the construction phase, and vessels create some additional traffic, they are a need for the appropriate authority to strengthen environmental monitoring and measurement.
in some cases, during operation of the project. also available and capable for marine rescues. the transmission infrastructure.
Require an Environmental Management Plan,
Typically cables will be sufficiently buried to guard Manufacturing. Some of the employment including designation of a responsible officer
against damage to (and by) fishing gear and ship’s 12.7.4 Socio-economic aspects arising from the offshore wind development at each OWF. During the operational phase,
anchors, and any scour protection will be designed could be local manufacturing, whether regularly review the OWF monitoring regime
to allow “overfishing” – so they do not damage The assessment will consider typically: through indigenous companies or through and its ongoing suitability.
fishing gear. the establishment of local facilities by foreign
Stakeholder consultations. Stakeholders manufacturers of wind turbines, support Use a central body to receive and collate
Shipping and Navigation. The distance of the
will typically include local authorities (including structures, cables, electrical equipment etc. post-consent data in common format; and
project from shipping lanes needs to be assessed,
those with coastal and landward jurisdictions which review and analyse data from all OWFs to
from the point of view of any disruption to
include the development footprint), statutory expand the evidence base for all.
shipping routes and the potential for damage
bodies, local community and interest groups.
to the OWF should a vessel lose control.
122 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 123
13. KEY FINDINGS AND
A feasibility study has been completed for This site data then enabled concept design and
a future demonstration project in Tamil outline project costing using DNV GL’s Levelised
Nadu’s lowest cost of energy zone, which was Cost of Energy (LCOE) design tool “Turbine.
124 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 125
13.1 SITE CONDITIONS 13.1.3 Geotechnical Despite A3 having the second lowest annual Consideration was given to the known site-specific
mean wind speed and hence one of the lowest climatic conditions within Tamil Nadu and the
13.1.1 Wind DNV GL’s offshore geotechnical department energy yields, it still has a lower cost of energy likely turbine class requirements to meet these
have developed experience based Geotechnical than the other sub-zones. This is due to small conditions (e.g. IEC 61400-1 edition 3 turbine
There is currently no installed offshore wind zone descriptions for the Tamil Nadu offshore variation in wind speeds across the selected classification). Turbines are classed by three main
measurement in Tamil Nadu. A LIDAR is planned by region and provided indicative lower/upper bound zone. A3 was therefore taken forward for further parameters: the average wind speed, extreme
NIWE. The mesoscale wind resource map modelled soil profiles for zone A. This is based on publicly concept engineering and cost of energy studies. 50-year gust, and turbulence. Mean wind speeds
during the Pre-feasibility Study has been used. available data and knowledge/experience from identified from the mesoscale modelling indicate
Once 12 months of on-site LIDAR data becomes working offshore in this region for a number a requirement for IEC Class II and above (noting
available, the MNRE may wish to conduct a full of decades. 13.3 TURBINE SUITABILITY the uncertainty without a sufficient duration of
energy assessment in support of this feasibility onsite wind measurements). Regarding extreme
study. The Pre-feasibility Study relied on available The stratigraphy within zone A is believed to The FOWIND consortium has completed a revised wind speeds further investigation is required,
satellite data and mesoscale modelling methods. generally comprise of a sand and cemented sands review of potential wind turbine offerings for the especially given the typhoon risks within this
Without offshore measurements available to with occasional stiff clay seams to depths of Tamil Nadu region, given a commercial turbine region. In lieu of long term measurements,
provide validation points there exists a high level around 45m, with relative density of the sands procurement date target between 2020 and it has been possible to estimate (with noted
of inherent uncertainty and the presented results ranging from loose to very dense. A high degree 2025. The objective of this exercise was to review uncertainties) a 50-year return gust wind speed
must be treated with due caution. Wind speed of spatial variation is identified with the limited the suitability of these wind turbine offerings using two approaches, one by extrapolating
spatial variation has been presented for projected available data. Profiles range from very firm considering the key drivers for wind turbine extreme wind speeds from the metocean study
turbine hub heights of 100 m and 120 m above cemented sands to very loose sands to depth. selection, specifically: to hub-height, and the second by applying the
sea level. For a height of 120 m above sea level Both of these extremes present different Indian Standard relating to Codes of Practice
modelled mean wind speeds were in the range challenges for foundations. Site suitability (ability to withstand the site for Design Loads for Buildings and Structures.
of 8 to 8.3 m/s. European projects are known to climatic conditions over the design operating life); For zone A (including sub-zone A3) both methods
possess mean wind speeds in the range of 8 to 10 It should be highlighted all geotechnical findings WTG track record (a loose measure of wind indicate IEC Class I turbines could be sufficient
m/s hence the values predicted in Tamil Nadu from are still subject to a high-level of uncertainty turbine reliability); with 3-second gusts of 63.8.8 m/s and 65.4 m/s
the mesoscale model are promising. and any future developer will need to conduct for hub-heights of 100 mMSL and 120mMSL
Suitability of wind turbine to the site respectively. More detailed extreme wind
a suitable geophysical and geotechnical survey
foundation selection; speed studies are recommended to verify
13.1.2 Waves and Currents campaign.
Site specific power production (which contributes this preliminary analysis.
A preliminary metocean study for zone A in 13.2 SELECTION OF POTENTIAL significantly towards the cost of energy).
Tamil Nadu has been conducted by DNV GL’s WIND FARM SITE
metocean department, it provides wave, current
and tidal data suitable for concept design. Extreme An optimal location, sub-zone A3, has been
parameters are provided both with and without the identified in Tamil Nadu’s most promising
presence of typhoons. Consideration of typhoon offshore wind development area, “zone A”, for
induced waves is important for both loads analysis demonstration projects ranging from 150 to 504
and calculating foundation platform elevations. MW.
Extreme 50-year return typhoon induced waves
are estimated at 11.0 m Hmax, this is comparable In total 10 sub-zones were defined in zone A
with extreme wave conditions seen in some parts based on the assumption that they could each
of the North Sea. 50-year return currents are accommodate a wind farm with a capacity between
estimated at 1.6 m/s at mid-depth, which is in- 150 and 504 MW. Further known hard constraints
line with magnitudes seen in some areas of the such as shipping traffic were applied and should be
North Sea. An all-wind speed and omni direction considered in any future spatial planning activities.
wave scatter table is also provided, this has been These 10 sub-zones have been modelled using DNV
used in the calculation of fatigue loads during the GL’s system design and cost modelling tool Turbine.
foundation comparison studies. During later design Architect and evaluated against their normalised
stages the effects of full wind/wave misalignments levelised cost of energy (LCOE) to establish the
should be considered. optimum demonstration project location.
126 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 127
Classification of a wind turbine as Class A or B is for the proposed layout. This layout would be 13.5 CONCEPT ELECTRICAL Supply Chain, Port Infrastructure and Logistics
dependent on the turbulence level within the wind broadly similar for other project configurations CONCEPT DESIGN Study [2] and findings from the site data study.
farm. This will be mainly driven by wind turbine and wind turbine capacity. An elliptical exclusion
array layout and can be quantified and mitigated zone around the turbines was generated using A preliminary investigation has been conducted Results show jackets as being lighter than
at a later stage however it is probable Class B will DNV GL’s WindFarmer software. During the wind into the electrical layouts of the onshore monopiles for all turbine sizes and soil conditions
be sufficient offshore in Tamil Nadu. Based on the farm layout design, the long axis of the ellipse has substation and offshore cables for a Tamil Nadu at the A3 sub-zone. In terms of cost the results
assessment, Class I or S wind turbines were taken been aligned with the assumed prevailing wind demonstration offshore wind farm, as well as show monopiles as being more economical for
forward for further assessment. direction in order to minimise both losses due to indicative costing and sizing for the equipment. both ground conditions modelled. GBS foundations
wake effects and loads on downwind turbines. It is assumed that the Tamil Nadu offshore are only suitable for the stronger cemented soil
Offshore wind turbines with a significant operating It should be noted that the proposed layout is development will not include an offshore profile and for the lower bound weaker sand
track record are still few and far between in a market preliminary in nature and should be revised further substation due to its close proximity to shore. profile are deemed unsuitable. For the soil profile
dominated by a few suppliers and this effect has based on the onsite measured wind resource and where gravity base structures are suitable they
been compounded between 2013 and 2017 with detailed grid studies specific to sub-zone A3. The offshore wind farm location within zone A are shown to have significant economic
significant mergers and formation of strategic joint is assumed at 15 km away from the shore. The advantages over jackets and monopiles.
ventures between the big players. The Siemens G4 The FOWIND consortium has conducted a high- wind farm being near to the shore and by utilising
platform still has accrued a substantially stronger level energy production assessment for sub-zone a 66 kV collection system voltage level, FOWIND Compared with typical north European pile
track record than the other WTG’s considered, with A3 in Tamil Nadu. The assessment was undertaken estimate that direct HVAC connection of the embedment, the predicted embedment depth
the Vestas V112-3MW platform (including onshore assuming uniform layouts for both 150-152 MW and offshore wind farm to the onshore substation for monopiles and jackets in Tamil Nadu are not
experience) still coming in second place. With the 500-504 MW wind farm capacity options, using could be feasible. This arrangement reduces overly onerous. If very hard, cemented or rocky
successful offshore cost reductions recently seen in the generic 4 MW, 6 MW and 10 MW wind turbines. the overall CAPEX and future operation and soil conditions are encountered then there is risk
Europe and with subsidy-free offshore wind projects It is important to take note of the preliminary maintenance cost. However, towards the detail that alternative installation methods to pile driving
on the horizon the next round of bids in Europe are nature of these estimates and the uncertainties engineering if the offshore wind farm is finally will be required. In these scenarios piles can be
predicted to feature much larger “1x MW” turbine highlighted within the report. located more than 20 km from the shore, then installed with the assistance of drilling equipment,
platforms with MW capacities exceeding 10 MW the requirement of having an offshore substation either to drill a cavity in rock into which the pile
and with rotor diameters more than 200 m. These For the Generic 4 MW turbine, Project Net Capacity should be assessed. is then grouted, or drilling during a pause in pile
larger turbines are critical to meet the LCOE Factors were estimated in the range of 30.0 % driving to remove hard ground beneath the pile
targets and as such developers will need to accept and 35.3 % (depending on the MW capacity of the For the propose of the electrical concept tip before pile driving resumes. Both of these
“1x MW” platforms with limited operational hours, farm). When deploying the larger 6 MW and 10 MW design a base case has been established, options are time consuming, costly and present
but likely from suppliers with extensive experience Generic turbines Project Net Capacity Factors were considering 84 WTGs each of 6 MW capacity. risks to installation. Gravity base structures
of the design and operation of established smaller estimated in the range of 37.6 % to 38.1 % and 37.1 The overall installation capacity is therefore are shown as a highly competitive solution but
platforms. However a strong track record may still % to 37.9 % respectively. These values might be calculated as 504 MW. For the remaining only when the soil conditions are suitable. Their
come at a price premium and it should be noted considered equivalent to those achieved in recent project configurations Turbine.Architect has attractiveness is a result of the relatively cheap
that there may be opportunities to partner with European projects [97] [98]. Lower capacity been used to validate and scale the results from cost of materials in comparison to steel. The
organisations which are bringing new WTG’s to the factors in early UK projects were largely a result this concept design study. To minimise electrical variation in soil conditions over sub-zone A3
market. This may result in more favourable economic of poor turbine reliability and availability resulting losses, 66 kV array cables have been assumed is not known and therefore, it is not clear how
conditions with respect to turbine procurement from un-optimised maintenance access strategies for all turbine MW capacities. applicable gravity base structures are. It is
in return for sharing the risk associated with the and worse than anticipated weather restrictions. expected that cemented soils, or very dense
lack of a proven offshore track record. Current and future European projects are set to 13.6 CONCEPT FOUNDATION surface sands, will not be found to extend over
achieve significantly higher capacity factors due DESIGN a large proportion of sub-zone A3.
13.4 LAYOUT AND ENERGY to the development of optimised operation and
PRODUCTION maintenance strategies and improved turbine Turbine.Architect’s foundation module has been The foundation studies completed thus far should
reliability. For example, recently Danish offshore used to undertake a foundation comparison be treated as preliminary only. The level of detail
An offshore wind farm layout using the 6MW wind farms have been reported as achieving a total for sub-zone A3. Monopile, jacket and GBS is applicable for preliminary costing studies and
and a 154m rotor diameter generic offshore average capacity factor of 41.6 %[59]. The UK foundation types have been assessed to determine CAPEX estimates cost modelling. However, more
wind turbine with a 504MW project capacity average capacity factors have grown significantly preliminary estimates of dimensions, masses and detailed design exercises should be completed
has been developed to represent a base case. over the years and current averages are reported costs. Three turbine types have been considered before forming firm conclusions regarding
A minimum inter-turbine constant spacing of at 37.8% [59]. and each combination of foundation and turbine foundations. A detailed understanding of the
8 x 7 rotor diameters (D) has been assumed has been assessed using upper and lower bound local ground conditions in terms of its geospatial
soil conditions. Monopile, jacket and GBS types variation should be obtained as this will lead to
have been selected for Tamil Nadu, based on a better understanding of the applicability of
findings from the Pre-feasibility Study [4], gravity base foundations.
128 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 129
may require a Heavy Lift vessel and as such general industry experience to date, primarily
day rates are very elastic, ranging by a factor in European waters, in which technological
of ten depending on market conditions. This development of larger commercially-available
results in a greater uncertainty for offshore turbines has been the most significant driver
substation CAPEX. behind the notable reductions in cost of energy
from utility-scale offshore wind farms. In addition,
13.8 OPERATION AND larger WTG rotors reach higher heights, to where
MAINTENANCE wind speeds are typically higher, and hence larger
CONSIDERATIONS turbines would be expected to yield a higher
capacity factor and higher total AEP. Increasing
The access logistics associated with these the capacity of the wind turbines from 4 MW
maintenance activities, are one of the most to 10 MW results in a cost of energy reduction
significant operational challenges facing the of approximately 23% (152 MW project confg.)
offshore wind energy market. Access strategies and 19% (504 MW project config.). It was also
can be categorised into three main types; onshore- noted that, with regard to the development of
based marine access, helicopter access and offshore wind in low-wind environments, that the
offshore-based marine access. Onshore-based deployment of turbines with a lower power density
marine access (e.g. workboats) is the most common (i.e. a larger rotor for a given generator capacity)
approach to date, however is heavily restricted by would likely contribute to a lower cost of energy.
the sea-state during transfer onto the structures.
Although increasing turbine size reduces the
In order to select the most suitable O&M cost of energy, there are potential advantages to
Strategy DNV GL used its in-house model: “O2M deploying smaller turbines, particularly in new
Optimisation of Operations and Maintenance” to markets with developing supply chains. Very large
simulate a variety of O&M strategies at sub-zone turbines may require construction infrastructure
A3 for each of the project capacities and wind that is either not available, or significantly limited
turbine capacities. It has been noted that the use in its availability; selection of these turbines
of helicopters or motherships is not envisaged may then result in an undesirable increase in
to prove optimal for most of the demonstration procurement and delay risk. In such a situation,
project scenarios. Due to the significant logistical smaller turbines may reduce the risk premium to
13.7 INSTALLATION up to 20% of the total CAPEX of an offshore wind and regulatory complexity added to a project outweigh some of the cost of energy deficit and
CONSIDERATION project, transport and installation expenses have and related to helicopter operations, it has been hence merit selection for a project.
a significant impact on the profitability of the deemed appropriate to rule out these strategies
The FOWIND consortium provided a high-level wind farm. Therefore, optimising the strategy and and assume that all first offshore wind projects in The LCOE for the Tamil Nadu demonstration
overview for key installation considerations and reducing potential downtime due to weather can India will be based on the most proven work boats project has been estimated at between 7,675 INR/
methodologies for optimisation as part of the support cost reduction and mitigation of schedule access methodologies. Considering only workboat MWhr and 9,965 INR/MWhr for a 150-152 MW wind
Supply Chain, Port Infrastructure and Logistics over runs during the transport and installation access methods preliminary estimates for OPEX farm capacity and between 7,362 INR/MWhr and
Study [2] Section 3.2 and the Pre-feasibility phase of the project. and availability have been presented for each 9,087 INR/MWhr for a 500-504 MW wind farm
Study [1] Section 6.3. The key areas of focus for project configuration in sub-zone A3. OPEX ranges capacity. Figure 13-1 compares recently awarded
installation studies are offshore wind port types, The CAPEX for installation and logistics is between 1,041 mINR and 1,419 mINR per annum for European offshore wind tenders against LCOE
vessels and strategy planning. calculated using Turbine.Architect’s installation 150-152 MW farm capacities and 3,521 mINR and projections for the Tamil Nadu demonstration
module which estimates the costs for the 4,643 mINR per annum for 500-504 MW capacities. project. It can be seen the lower bound of the
Considering Tamil Nadu’s climatic conditions, installation of turbines, foundations and electrical This variation relates to cost savings seen when projected LCOE figures for Tamil Nadu is broadly
the summers are extremely hot and dry, while substations. Turbine and foundation installation operating and maintaining a fewer number of larger in line with the UK 2020 target and the upper
the monsoons are quite strong and can cause strategies depend on the turbine size, the selected capacity WTGs. Larger turbines are a key driver for bound is slightly above but still tracking LCOE
severe floods. Therefore it is important to consider foundation type, the depth and the selected reducing LCOE. figures for recent European projects. This appears
an adequate amount of weather downtime within metocean climate, the installation module finds positive for Tamil Nadu, especially considering the
the overall transport and installation schedule. the appropriate vessel and installation durations 13.9 OUTLINE PROJECT COSTING demonstration project figures have be calculated
Furthermore, schedule planning should consider from pre-processed installation data. For electrical based on a higher financial discount rate (i.e. 10%
monthly weather fluctuations during the year, substations, the lifts are more problematic and The cost of energy from an offshore wind farm vs. 6-7%).
like cyclones (Typhoons). With a typical share of reduces as turbine size increases; this mirrors
130 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 131
14. INDUSTRY PERSPECTIVE
FIGURE 13-1: EUROPEAN LCOE TRENDS VS TAMIL NADU PROJECTIONS
(Adjusted for grid, development costs and contract length where required)
ON INDIA’S OFFSHORE
WIND POLICY Written by ReNew POWER
The objective of this exercise was to supplement With the expectation that the early offshore
FOWIND’s feasibility assessments undertaken wind projects will have a very high import
for Gujarat and Tamil Nadu with an informed requirement for necessary components.
feedback from an experienced renewable energy Providing exemption from excise duties
project developer’s perspective on the key areas or GST on offshore wind turbines (WTGs),
of offshore wind policy design, regulatory inverters, transformers, evacuation
framework, financial mechanism, tariff regime infrastructure etc. for the early phase
and the supply chain ecosystem. projects would make project development
possible at reasonable cost.
We structured our discussions under five core
areas. During our discussions with the wind The Ministry should consider providing time
13.10 PRELIMINARY PROJECT Wind Resource: high uncertainty of the wind industry and project developers in the past months bound incentives similar to the provisions
RISK REGISTER resource assessment (noted LIDAR is planned we found that there are recurring threads in their of Generation Based Incentive, Accelerated
for Tamil Nadu by NIWE); perspective on the current offshore wind policy Depreciation etc. that supported the creation
When planning offshore wind farm projects, Geotechnical conditions: there is only limited and the development of a successful offshore wind of India’s successful onshore wind sector.
all decisions must be considered regarding information on the seabed geology of the sector in India. In the following paragraphs we The incentives would have to be designed
potential future actions, although outcomes Tamil Nadu region available, and DNV GL’s highlight and synthesize our discussions from the keeping in mind the unique conditions
cannot be foreseen with certainty due to experience in the region indicates high spatial industry perspective. associated with the complex range of actors
incomplete information. This uncertainty variation from loose/weak to strong highly within the offshore wind sector.
associated with all business activity is defined cemented sand material to depth; 14.1 POLICY SUPPORT: The Ministry of New and Renewable Energy
as risk. This section provided a high level should work with the Ministry of Power,
Grid connection: grid availability.
qualitative assessment of the principal risks For providing long-term clarity and certainty Ministry of Finances, the Central and State
for the potential offshore wind farm zones to the sector the Ministry of New and Electricity Regulatory Commissions, and lastly
identified in Tamil Nadu. It is important to ensure 13.11 ENVIRONMENTAL
Renewable Energy should declare offshore the Central and State Transmission Utilities
that significant risks are managed and that AND SOCIAL IMPACT
specific targets (e.g. Renewable Purchase to provide a comprehensive polity roadmap
mitigation measures are identified. Risks were Obligations for the states). for offshore wind development in India.
characterised into three major categories The FOWIND Pre-feasibility Study for Tamil Nadu
(High, Medium and Low) with “High” indicating [1] included chapters on environmental and social Further the Ministry in conjunction with the
the risk is considered “Not acceptable” and impact that discussed the potential impacts of grid companies plan for an expansion of
mitigation through an alternative solution offshore wind projects, regulatory mechanisms and onshore transmission targets to facilitate
is likely to be required. Further tasks have protocols for planning consent. In this feasibility timely grid integration of all new generation
been identified as “Medium” indicating that study the scope, key principles and best practice from offshore wind farms.
mitigation measures would likely be required for environmental and social impact assessments
to reduce risks to “as low as reasonably is discussed. Key biological, physical and human
practicable” (ALARP) levels. At this preliminary aspects are considered. Along with other
stage the following tasks have been highlighted permitting recommendations the importance of
as “High” risk and are recommended as priorities allowing a design envelope approach in EIA permit
for mitigation measures in future offshore wind applications, to give flexibility to the development,
developments: is highlighted.
132 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 133
14.2 REGULATORY SUPPORT: 14.3 FINANCING SUPPORT/TARIFF 14.4 G
RID INTEGRATION 14.5 SUPPLY CHAIN SUPPORT:
REGIME: SUPPORT:
The Ministry of New and Renewable Energy Recommendations provided under the FOWIND
in collaboration with the relevant state With higher expected cost of energy from The state governments could provide Supply Chain, Ports and Infrastructure Study
authorities should pre-identify dedicated the early projects, the financial viability of significant risk management benefits for should be looked at by the Ministry.
offshore wind development zones within the projects can be improved by securing lending offshore wind projects by improving the The government should undertake the
Indian SEZ. from public sector banks/government backed onshore existing grid infrastructure by floating development of ports and make them ready
The industry sees the UK’s Crown Estate Model special purpose funds (e.g. similar to the Green concurrent tenders for connection of offshore for offshore wind project delivery. Current port
[60] as a desired seabed use and management Investment Bank in the UK) to promote the plants to the onshore grid. infrastructure in India will be a limiting factor.
model that the government could consider inception of this industry in India.
The Ministry of New and Renewable Energy Early assistance from public sector specialist
towards developing India’s offshore wind The government can seek tie-ups with the in collaboration with the CTU should initiate companies like the Oil and Natural Gas
specific assets. European Investment Bank who have provided a review of the current grid-code for the Corporation could be extremely beneficial
The industry applauds the current policy’s significant lending to offshore wind projects in need of a separate grid code or modifications both for operational and in competency
intent to undertake ‘Single Window Clearance’ Europe over the last decade, the KfW that has specifically for offshore wind. Future grid development for offshore wind project
system for all necessary approvals and an offshore wind lending program, the World code modifications should be reviewed in light development. This could include help from
permits, by its nodal agency the National Bank and other sister development banks of the specific characteristics and quantum lending of jack-up rig vessels to drilling and
Institute of Wind Energy. This facility should for low-cost funds for offshore wind projects. of power from offshore wind farms and the foundation casting. A government directive to
comprise all relevant aspects including Similar to the State Bank of India’s recently capacity addition envisaged under long- this effect would greatly expedite collaboration
environmental clearances to onshore power availed US$ 625 M facility from the World Bank term plans for the offshore sector of the between the ONGC, its suppliers and offshore
evacuation approvals. This is a crucial element for promotion of grid connected rooftop solar government. project developers. This would expedite the
within the supporting regulatory ecosystem projects. build-up of Indian offshore wind sector’s
The state and central agencies must clarify the
as it is expected a multitude of ministries and The Ministry could also consider ensuring that compliance boundary of offshore wind farms competency indigenously.
regulatory bodies, both at central and state a Feed-In Tariff with mandatory procurement by under the individual grid code requirements, Development of offshore focused R&D by
levels, would have to be involved for securing the DISCOMs is available to the offshore wind as applicable. government for long-term LCOE reduction.
the necessary project development clearances. projects. The industry had recommendations This could include bilateral MoUs with the
Development of underwater/seabed power
Given the initial cost of early offshore wind for the design of this tariff regime: relevant European agencies and governments
evacuation infrastructure and setting
projects, these wind farms should include the Offshore tariff could be structured to up of offshore sub station to be PGCIL’s etc. for sharing of expertise, training of key
obligation from the offtaker as “Must Run” factor in the nature of each specific responsibility. This reduces significant project technical personnel etc. in order to have a long
status. project. The tariff bands could be built risk for the offshore wind farm developer(s). term development plan for the sector.
Further for these ‘first of its kind projects’ in to consider the impact of water depth, Ensure a transparent system for acquisition
Training of PGCIL personnel in key offshore
India – the regulators must ensure measures distance from shore, capital cost involved of approvals and all related information
countries such as the UK, Germany, Denmark
are taken to safeguard them against losses etc. This would be similar to onshore wind through dedicated online portals that are
etc. as underwater/seabed power evacuation
from curtailment by the state or regional policy developed by states where tariff is regularly updated. Also, NIWE as the nodal
and cabling expertise is currently not available
grid operators, as witnessed by land-based determined based on wind power density, agency under the policy framework must
in India.
renewable energy generators. To make the capital cost of installation, O&M cost etc. work towards ensuring effective collaboration
National Clean Energy Fund allocation could
projects viable offshore wind must be granted Tariff could also be differentiated based on between involved/affected parties during
be utilized for investments in the relevant
the “deemed generation provision” to offset project size. the planning stages to minimise execution
transmission sector improvements.
any curtailment. Tariff should be worked out based on a challenges later on.
Further, in line with the expected high ‘Front Loaded’ payment method, wherein
investment needs for offshore projects, instead of having a constant tariff level
priority payments from DISCOMs must be over the complete duration of support, the
ensured. tariff structure could pay higher tariff for
the early years of a project, with a tapering
out of the tariff towards the end of the
tariff agreement period. This can help to
reduce financing cost without increasing
the total sum of financial support for the
early offshore wind projects.
134 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 135
15. FIRST OFFSHORE 15.1 DESIGN BASIS OF FOWPI At site of the LIDAR-platform, ref. Figure 15-2,
NIWE has carried out a geotechnical drilling,
A site specific desk top wind study has been which is available for FOWPI. It shows around
136 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 137
15.2 DESIGN FOR FOWPI
A study on electrical design for the site opens
FOWPI has prepared a number of design studies for two very different options to be decided
to guide project developers in their preparations. upon by eventual project developer. Either
All of these studies are advisory only as neither an offshore substation will be used, which converts
full design basis has been established nor has from 33 kV to 220 kV in the windfarm before
wind turbine type and size been chosen. export via one cable to shore and grid connection.
Or an onshore substation will be used, which
A study on Wind Turbine Technology, Layout is fed via multiple (4-6) 33 kV export cables from
and AEP has been prepared. Reference wind the windfarm to shore. An offshore substation
turbines of two sizes are defined and desk top preparation requires sophisticated marine
based wind resource are provided for the two electrical designers, experienced high quality
reference wind turbines. Choice of wind turbine manufacturers and large installation vessels.
type has to cope with typhoon conditions and The onshore solution on the other hand has
low annual mean wind speed exactly as onshore. large costs for many kilometre of marine cables
The wind farm layout is simple and consists of and marine installation of these. The study gives
3 lines of wind turbines perpendicular to advises on electrical offshore windfarm design
dominating wind direction, ref. Figure 15-1. for newcomers and decision makers.
A study on foundation design for the site FOWPI is organising workshops and conferences
recommends to use monopiles. Advisory to share the results as fast as possible, ref. Figure
comments on design of main structure as well 15-7. It will facilitate the fast preparation and
as of secondary steel are given. This should implementation of the First Offshore Windfarm
give easy access to the technology for Indian Project of India – maybe already by 2020.
designers and decision makers.
138 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 139
WIND IS THE MOST COMPETITIVELY PRICED In Europe offshore wind power saw
a record 3,148 MW of net additional
MW. This corresponds to 4,149 grid-
connected wind turbines across 11
TECHNOLOGY IN MANY IF NOT MOST MARKETS; installed capacity in 2017. This countries. 2017 was a record year:
AND THE EMERGENCE OF WIND/SOLAR HYBRIDS, corresponds to 560 new offshore wind
turbines across 17 wind farms. There
twice as much as 2016 and 4% higher
than the previous record in 2015.”
MORE SOPHISTICATED GRID MANAGEMENT AND were 14 projects fully completed and
connected to the grid, including the The numbers show a maturing
INCREASINGLY AFFORDABLE STORAGE BEGIN TO first floating offshore wind farm. industry, in transition to a market-
PAINT A PICTURE OF WHAT A FULLY COMMERCIAL Europe now has a total installed
based system, competing successfully
with heavily subsidized incumbent
FOSSIL-FREE POWER SECTOR WILL LOOK LIKE. offshore wind capacity of 15,780 technologies.
140 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 141
16. REFERENCES [30] The United Kingdom Hydrographic Office, Admiralty Sailing Directions, vol. Various, Taunton, UK: The Hydrographer of the
Navy.
[31] P. E. Tucker MJ, “Waves in ocean engineering:,” Elsevier Science Ltd, 2001.
[1] FOWIND, “Pre-feasibility Study for offshore wind farm development in Gujarat,” 2015. [32] Det Norske Veritas, “Environmental Conditions and Environmental Loads,” DNV, 2010.
[2] FOWIND, “Supply Chain, Port Infrastructure and Logistics Study for offshore wind farm development in Gujarat and Tamil [33] F. J. D., “Nonlinear Wave Theories,” Ocean Engineering Science, vol. 9, 1990.
Nadu,” 2016.
[34] E. Spentza, B. Chicaud and I. Garcia de Andoin, “Parametric Modelling of Cyclonic Winds for Quick Location Assessment,” in
[3] FOWIND, “Grid Integration Study for offshore wind farm development in Gujarat and Tamil Nadu,” 2017. 22nd International Ocean and Polar Engineering Conference.
[4] FOWIND, “Pre-feasibility Study for offshore wind farm development in Tamil Nadu,” 2015. [35] C. K. Cooper, “Parametric Models of Hurricane Generated Winds, Waves and Currents in Deep Water,” in 20th Offshore
Technology Conference, Houston, Texas, 1998.
[5] Global Wind Energy Council, “Offshore Wind Development in India: FOWIND Commissions India’s First LIDAR for Offshore Wind
Resource Assessments in Gujarat,” 02 11 2017. [Online]. Available: http://gwec.net/offshore-wind-development-in-india-fowind- [36] H. E. Willoughby, R. W. R. Darling and M. E. Rahn, “Parametric Representation of the Primary Hurricane Vortex, Part II: A New
commissions-indias-first-lidar-for-offshore-wind-resource-assessments-in-gujarat/#. [Accessed 01 12 2017]. Family of,” Monthly Weather Review, vol. 134, pp. 1102-1120, 2006.
[6] FOWIND, “From Zero To Five GW: Offshore Wind Outlook for Gujarat and Tamil Nadu,” 2017. [37] ONGC, Composite Bouguer Gravity Map of Cauvery Basin, Tamil Nadu, 1993.
[7] DNV GL, “Turbine.Architect,” [Online]. Available: https://www.dnvgl.com/services/turbine-architect-49342. [Accessed 01 12 [38] Geological Survey of India, Geology and Mineral Resources of the states of India, Chennai, 2006.
2017].
[39] NGRI - Natural Geophysical Research Institute, India., Gravity Map Series of India (1: 5,000,000), First Edition, Explanatory
[8] “Cost of Energy Model Theory Guide,” DNV GL, 2015. Notes., 1978.
[9] “Marine Traffic,” [Online]. Available: https://www.marinetraffic.com/en/ais/home/centerx:71.7/centery:20.1/zoom:8. [Accessed [40] S. Badrinarayanan, D. Sasisekaran and K. Sivakolun, New Archaeological sites in the Gulf of Cambay, India , Chennai., Chennai:
15 December 2017]. National Institute of Ocean Technology., 2003.
[10] “Anemoscope User’s Guide,” Canadian Hydraulics Centre and Environment, [Online]. Available: http://www.anemoscope.ca/ [41] K. Vasudevan, L. V. Ramana, N. Nagasudha, A. Borthakur and S. K. Das, “Petroleum System and Play Types of Synrift
Documents/AnemoScope_User_Guide.pdf. [Accessed 18 05 2013]. Sequences, Ramand Subbasin, Cauvery Basin.,” in 7th Internaitonal Conference and Exposition on Petroleum Geophysics.,
Hyderabad., 2008.
[11] “Anemoscope Reference Guide,” Canadian Hydraulics Centre and Environment, [Online]. Available: http://www.anemoscope.
ca/Documents/AnemoScope_ReferenceGuide.pdf. [Accessed 18 02 2013]. [42] IEC, “International Standard IEC 61400-1 Third edition 2005-08,” 2005. [Online]. Available: http://webstore.iec.ch/preview/
info_iec61400-1%7Bed3.0%7Den.pdf.
[12] “Global Map V.1 (Global Version) – Land Cover (GLCNMO) Download, ISCGM, Geographical Survey Institute, Chiba University
and collaborating organizations; http://211.19.49.27/gmd/download/glcnmo.html, accessed 18/02/2013.,” [Online]. [43] Bureau of Indian Standards, “Code of Practice for Design Loads for Building and structues,” Bureau of Indian Standards.
[13] “Shuttle Radar Topography Mission, Jet Propulsion Laboratory, NASA; http://www2.jpl.nasa.gov/srtm/, accessed 18/02/2013.,” [44] Building Materials & Technology Promotopn Council (BMTPC); India..
[Online].
[45] “4COffshore,” 4C Offshore Market Overview Report, June 2017. [Online]. Available: http://www.4coffshore.com/.
[14] “NCEP/NCAR Reanalysis dataset, Earth System Research Laboratory, NOAA; http://www.cdc.noaa.gov/data/gridded/data.ncep.
reanalysis.html, accessed 18/02/2013.,” [Online]. [46] DNV GL, “FOWIND Offshore Wind Speed Mapping of Gujarat and Tamil Nadu,” 2014a.
[15] “Modern Era Reanalysis for Research and Applications (MERRA),” NASA GSFC Global Modelling and Assimilation Office , 2008. [47] International Energy Agency; Nuclear Energy Agency; Organisation for Economic Cooperation and Development, “Projected
[Online]. Costs of Generating Electricity,” Paris, France, 2015.
[16] A. Chawla, D. M. Spindler and H. L. Tolman, “30 Year Wave Hindcasts using WAVEWATCH III with CFSR winds, Phase 1,” NOAA/ [48] DONG Energy; Vattenfall; The Danish Energy Authority; The Danish Forest and Nature Agency, “Danish Offshore Wind - Key
NWS/NCEP/MMAB, Maryland USA, 2012. Environmental Issues,” 2006.
[17] A. Chawla, D. M. Spindler and H. Tolman, “WAVEWATCH III Hindcasts with Re-analysis winds, Initial report on model setup,” [49] Danish Energy Agency; Danish Nature Agency; Dong Energy & Vattenfall, “Danish offshore wind key environmental issues – a
NOAA/NWS/NCEP/MMAB, Maryland USA, 2011. follow-up,” 2013.
[18] D. Spindler, A. Chawla and H. Tolman, “An initial look at the CFSR Reanalysis winds for wave modeling,” NOAA/NWS/NCEP/ [50] Collaborative Offshore Wind Research into the Environment, “COWRIE reports,” [Online]. Available: http://www.
MMAB, 2011. thecrownestate.co.uk/energy-minerals-and-infrastructure/downloads/cowrie/. [Accessed 01 November 2017].
[19] Logica, “DUE GlobWave Deliverable D.2 - Technical Specification, V1.3,” 2010. [51] The Crown Estate, “Marine Data Exchange,” [Online]. Available: http://www.marinedataexchange.co.uk/. [Accessed 01
November 2017].
[20] Satellite Oceanographic Consultants, “DUE GlobWave Deliverable D5 Product User Guide, V1.4,” 2010.
[52] Marine Management Organisation, “Review of post-consent offshore wind farm monitoring data associated,” 2014.
[21] NASA/GSFC/NOAA, NASA/GSFC/NOAA, 2009. [Online]. Available: http://podaac.jpl.nasa.gov/dataset/CCMP_MEASURES_
ATLAS_L4_OW_L3_0_WIND_VECTORS_FLK. [Accessed 2014]. [53] . A. Beiersdorf and A. Radecke, Eds., Ecological Research at the Offshore Windfarm alpha ventus, Springer Spektrum, 2014.
[22] HYbrid Coordinate Ocean Model, Center of Ocean-Atmospheric Prediction Studies, 2010. [Online]. Available: http://www. [54] OSPAR Commission, “Inventory of measures to mitigate the emission and environmental impact of underwater noise,” 2014.
hycom.org. [Accessed 2014].
[55] Joint Nature Conservation Committee, “Statutory nature conservation agency protocol for minimising the risk of injury to
[23] DHI, MIKE 21/3 Flow Model FM Hydrodynamic and Transport Module - Scientific Documentation., 2005.. marine mammals from piling noise,” 2010.
[24] NOVELTIS, 2015. [Online]. Available: http://tips.noveltis.com/. [56] B. Berwyn, “How do offshore wind farms affect ocean ecosystems?,” Deutsche Welle, 22 11 2017. [Online]. Available: http://
www.dw.com/en/how-do-offshore-wind-farms-affect-ocean-ecosystems/a-40969339. [Accessed 30 November 2017].
[25] OSU. [Online]. Available: http://volkov.oce.orst.edu/tides/.
[57] V. L. G. Todd, J. C. Warley and I. B. Todd, “Meals on Wheels? A Decade of Megafaunal Visual and Acoustic Observations from
[26] K. Knapp, M. C. Kruk, D. Levinson, H. Diamond and C. Newmann, “The International Best Track Archive for Climate Stewardship Offshore Oil & Gas Rigs and Platforms in the North and Irish Seas,” PLoS ONE, vol. 11, no. 4, 2016.
(IBTrACS): Unifying tropical cyclone best track data,” 2010.
[58] D. J. Russell, S. M. Brasseur, D. Thompson, G. D. Hastie, V. M. Janik, G. Aarts, B. T. McClintock, J. Matthiopoulos, S. E. Moss and
[27] NOAA, National Climatic Data Center, NOAA National Climatic Data Center, 2010. [Online]. Available: http://www.ncdc.noaa. B. McConnell, “Marine mammals trace anthropogenic structures at sea,” Current Biology, vol. 24, no. 14, pp. R638-R639, 2014.
gov/ibtracs/. [Accessed 2014].
[59] “Energynumbers.info,” 18 01 2018. [Online]. Available: http://energynumbers.info/uk-offshore-wind-capacity-factors. [Accessed
[28] ISO, “Petroleum and natural gas industries - Specific requirements for offshore Structures, Part 1: Metocean design and 27 01 2018].
operating considerations,” ISO, 2005.
[60] CROWN ESTATE , “Offshore wind cost reduction: Pathways study.,” May 2012. [Online]. Available: http://www.thecrownestate.
[29] American Petroleum Institute, “Interim Guidance on Hurricane Conditions in the Gulf of Mexico,” 2007. co.uk/media/5493/ei-offshore-wind-cost-reduction-pathways-study.pdf. [Accessed 27 04 2015].
142 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 143
APPENDIX 1
APPENDICES MODELLED WIND SPEEDS
FIGURE 16-1: MODELLED WIND SPEED OVER TAMIL NADU AT 80 M ABOVE SEA LEVEL
144 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 145
APPENDIX 1
MODELLED WIND SPEEDS
FIGURE 16-2: MODELLED WIND SPEED OVER TAMIL NADU AT 100 M ABOVE SEA LEVEL FIGURE 16-3: MODELLED WIND SPEED OVER TAMIL NADU AT 120 M ABOVE SEA LEVEL
146 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 147
APPENDIX 2
HEAT MAPS
FIGURE 16-4: OFFSHORE HEAT MAP WITH POTENTIAL DEVELOPMENT ZONES FIGURE 16-5: OFFSHORE POTENTIAL DEVELOPMENT ZONES OF TAMIL NADU
OF TAMIL NADU
148 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 149
PROJECT PARTNERS
KNOWLEDGE PARTNER INDUSTRY PARTNER
Global Wind Energy Council Center for Study of DNV GL is the world’s
(Brussels, Belgium) is Science, Technology and largest provider of
the international trade Policy (Bangalore, India) independent renewable
association for the is one of the largest think energy advice. The
wind power industry. tanks in South Asia; its recognised authority in
The members of GWEC vision is to enrich the onshore wind energy, DNV
represent over 1,500 nation with technology- GL is also at the forefront
companies, organisations enabled policy options for of the offshore wind, wave, National Institute of Wind Energy ReNew Power Ventures Private
and institutions in more equitable growth. tidal and solar sectors. (NIWE) will support FOWIND efforts Ltd. join as an industry partner.
than 70 countries. www.cstep.in www.dnvgl.com towards offshore wind feasibility ReNew Power is a leading clean
www.gwec.net assessments for potential offshore energy IPP with more than 3
wind project development in the GW of commissioned and under-
states of Gujarat & Tamil Nadu construction clean energy assets,
– with a special focus on wind and a pipeline of close to 1.8 GW
resource validation. NIWE is an wind, solar and distributed.
autonomous R&D institution under
the Ministry of New and Renewable
Energy, Government of India,
established to serve as a technical
focal point for orderly development
of Wind Power deployment in India.
www.niwe.res.in
Gujarat Power Corporation World Institute of
Limited (Gandhinagar, Sustainable Energy
India) has been playing (Pune, India) is a not-for-
the role of developer and profit institute committed
catalyzer in the energy to the cause of promoting
sector in the state of sustainable energy and
Gujarat. GPCL is increasing sustainable development,
its involvement in power with specific emphasis on
projects in the renewable issues related to renewable
sector, as the State of energy, energy security,
Gujarat is concerned about and climate change.
the issues of pollution and www.wisein.org
global warming.
www.gpclindia.com
150 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU 151
ACKNOWLEDGEMENTS
Authors:
Design:
Sweeta Patel
DISCLAIMER
This publication was produced with the financial support of the European Union. Its contents are the sole responsibility of
FOWIND consortium and do not necessarily reflect the views of the European Union.
This report is provided for illustrative purposes only without any representations, warranties or undertakings from GWEC or
DNV GL as to the content or any part of this report and the data contained therein, including without limitation in respect of
quality, accuracy, completeness, or reliability.
The information contained in the report does not represent endorsement by GWEC, or DNV GL of any particular project,
product or service provider. By accessing the report either in a hard copy or electronically, users accept that GWEC, DNV GL
or the authors are not responsible for any kind of loss or damage resulting from the use of the information contained in the
report or for any reliance placed thereon and the users further acknowledge that the content of the report and data therein are
subject to change.
Copyright © FOWIND 2018
Unless otherwise indicated, material in this publication may be used freely, shared or reprinted, but full acknowledgement is
requested. This publication should be cited as FOWIND (2018), Offshore Tamil Nadu Feasibility Report.
152 | FEASIBILITY STUDY FOR OFFSHORE WIND FARM DEVELOPMENT IN TAMIL NADU