Miscallaneous Activities Progress abstract till 05-06-2019(Complete Reach-1)

Qty Executed Qty Executed Qty Executed Qty Executed Qty Executed Qty Executed Qty Executed Avg.Qty
Total Executed Balance on 30-05- on 31-05- on 01-06- on 02-06- on 03-06- on 04-06- on 05-06- Executed Per Stock at Material
S.No Activity Scope(Qty) Qty Qty 2019 2019 2019 2019 2019 2019 2019 day site to indent
Omega
1 SealExpansion 264 262 2 0 0 0 0 0 1 0 0.74 2 0
Joint.
Square Man
264 257 7 0 0 0 0 7 0 4 1.30 7 0
Hole Cover
2
Circular
31 29 2 0 0 0 0 0 1 2 0.23 2 0
Manhole Cover
Drainage pipe
3 298 260 38 0 0 0 0 0 0 1 0.91 38 0
fixing
4 Recess filling 298 280 18 0 0 0 0 0 0 4 0.36 NA NA
Siesmic arrestor
5 150 150 0
casting
Earthing Plate
6 298 298 0
Fixing
SS Railing-
7 264 264 0
Viaduct
SS Railing-
8 20 20 0
Pocket track
Strip Seal
9 37 37 0
Expansion Joint