Professional Documents
Culture Documents
1. INTRODUCTION
© 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 237
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 10 | Oct 2018 www.irjet.net p-ISSN: 2395-0072
Case study 1:- For mega infrastructure projects a flexible and effective
method is needed. Engineering Procurement Construction
Department:- Maharashtra State Road Development (EPC) contract is a popular type of contract for
Corporation Limited Mumbai. infrastructure and power projects. EPC contractors carryout
Name of Work:- Construction of elevated structure, designs, procure the material and equipment’s as per the
ROB and service roads of NH-4 from Km 24.500 to Km specifications and deliver the project in stipulated time.
25.570 in the state of Maharashtra under EPC mode.
Type of Contract:- Engineering, Procurement and
III. Advantages:-
Construction (EPC) Contract
Length in Km:- 1.07 Km a. Reduced total time during the contractual process by
Completion Period:- 18 Months
having just one process.
Estimated Tender Cost:- Rs. 46.1246 Crore
b. A seemingly “lower cost” when integrating “all” the
Case Study 2:-
elements under one provider.
Department:- Public Works Department (PWD)
c. The main advantage of this service is the peace of
Name of Work:- Construction of Flyover From
mind the owner gets when it hands over full
College of Engineering Pune to Patil Estate, Pune
responsibility of the project to “only one contractor”, it is
(Balance Work)
much easier for the owner to manage and communicate
Type of Contract:- Item Rate Contract
with one provider, which means “one neck to choke”.
Length in Km:- 0.80 Km
Completion Period:- 15 Months d. EPC minimizes the owner’s risks.
Estimated Tender Cost:- Rs.21.83 Crore
e. EPC for mega projects is more flexible and efficient
Case Study 3:- delivery method.
1. EPC Contract:- EPC contract carryout designs of project, c. Usually designs are oversized due to lack of information
procure equipment’s and materials required as per the available at the time when the offer is being prepared.
specifications and deliver the project within the specified
period of time. 2. Item Rate Contract:- It is also called a schedule contract,
in this contract, the contractor undertakes the execution of
I. Types of EPC contract: work on an item rate basis. The amount to be received by the
contractor, depends upon the quantities of various items of
a. Single document. work actually executed. The payment to the contractor is
made on the basis of detailed measurements of different
b. Privately negotiated. items of work actually done by him.
d. Issued under nomination basis. The item rate contract is most commonly used for all types of
engineering works financed by public or government bodies.
e. Multiple documents. This type of contract is suitable for works which can be split
into various items and quantities under each item can be
f. Single document. estimated with accuracy.
g. Lumpsum price. II. Advantages:-
h. Fixed price. a. There is no need for detailed drawings at the time of
allotting contract as in the case of lump sum contract. The
© 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 238
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 10 | Oct 2018 www.irjet.net p-ISSN: 2395-0072
c. The payment to the contractor is made on the actual b. Lump sum contracts pose greater risk to contractor.
work done by his at the agreed rates.
c. The overall construction completion could take longer
III. Disadvantages:- than other contractual alternatives.
a. The total cost of work can only be known upon d. Since the contract is based on fixed price, the
completion. As such, the owner may incur financial contractor may start using sub-standard means and
difficulty if the final cost increases substantially. methods and products. In such a case, the owner
should specify building materials well in advance.
b. Additional staff is required to take detailed
measurements of work done for releasing payments to e. Lump-sum contracts usually end up with higher fixed
the contractor. price to cover unforeseen circumstances. Owners are
responsible for unpredicted conditions which are
3. Lump-Sum Contract:- In this type of contract, the beyond the control of either party.
contractor offers to do the whole work as shown in
drawings and described by specifications, for a total 7. DATA ANALYSIS:-
stipulated sum of money. There are no individual rates
quoted, thus it becomes difficult to make adjustments in Site Dehu Road COEP Mundhawa
the contract value if any changes are to be made in the
work later on. The schedule of different items of work is Type of EPC Item Rate Lump-Sum
not provided and the contractor has to complete the work as Contract Contract Contract Contract
per drawings and specifications for the agreed lump sum Project Project In this case
amount. amount and amount is the project
scope of given by the amount is
I. Suitability:- work is client. Extra fixed and
fixed. Extra claim can be extra claim
A lump sum contract is more suitable for works for which
Cost claim can be done as per can be as
contractors have prior construction experience. This
done but not work per the
experience enables the contractors to submit a more realistic
easily executed. work
bid. This type of contract is not suitable for difficult
applicable, executed
foundations, excavations of uncertain character, and projects
as the scope
susceptible to unpredictable hazards and variations.
is defined
II. Advantages:- Work can be Work can be Work can be
started started even started
a. The owner can decide whether to start or shelve the when the if minimum when more
project knowing the total lump sum price quoted by land is land is than 50% of
different contractors. Feasibility
acquired acquired i.e. land is
more than 25%. available to
b. The contractor can earn more profit by in depth 90%. the
planning and effective management site. contractor.
c. Since the contractor has accepted a fixed price for the Easily time Time Time is
construction, the owner is not liable for any over extension is beyond the defined but
expenditure. This is the most important benefit. not available scope of time
as the scope work is extension
d. It is much simpler to get construction loan with a Time and the available can get
Lump sum contract as it provides a high degree of Overrun amount of and can get according to
certainty as far as cost is concerned. the project the time valid
is fixed. extension reasons.
e. It is much easier to supervise and manage Lump sum depending
contracts. on the work.
In this type Causes of Causes of
Cost
of project cost cost
Overrun
cost is overrun: overrun:
© 2018, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 239
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 10 | Oct 2018 www.irjet.net p-ISSN: 2395-0072
8. SOME MAJOR EPC COMPANIES IN INDIA:- 5) Abhishek Raj Singh, Dr. Sanjay Tiwari (July 2015), " EPC:
An Innovative Tool for Mega Project Construction"
Segment EPC Company 6) Soroush Hejazi Kia, Ahmad Reza Tohidi (March 2015), "
1. Larsen and Tourbo Ltd. Risk Allocation in Engineering Construction Contracts"
2. Shapoorji Pallonji and Co. Ltd. 7)Christopher Marato Gofhamodimo, "Construction
Construction
3. B.G. Shirke Construction Technology Contracts"
residential/
Pvt. Ltd. https://www.scribd.com/document/371256964/icm1999-
commercial
4. Man Infra Construction Ltd. 03
5.Supreme Infrastructure India Ltd.
1. Hindustan Construction Co. Ltd.
Infrastructur 2. Gammon India
e/general
contracting 3. Simplex Infrastructure Ltd.
4. Gayatri Projects Ltd.
5. Nagarjuna Construction Ltd.
9. CONCLUSIONS:-