You are on page 1of 12

Performance of Precast Concrete

Beam-to-Column Connections
Subject to Cyclic Loading
Geraldine 5. Cheok
Research Structural Engineer An experimental study of the behavior of
United States Department of precast concrete beam-to-column connec-
Commerce
National Institute of Standards tions subjected to cyclic inelastic loading
and Technology conducted at the National Institute of
Gaithersburg, Maryland
Standards and Technology is presented. The
study was initiated to provide data for the
development of a rational design procedure
for such connections in seismically active
regions. The objective of the study is to de-
velop a moment resistant precast concrete
connection that is economical and can be
easily constructed. Four one-third scale
monolithic concrete beam-to-column connec-
tions were tested: two were designed accord-
H. 5. Lew
Chief, Structural Division ing to the 1985 Uniform Building Code (UBC)
United States Department Seismic Zone 2 criteria and two to UBC Zone
of Commerce
National 'Institute of Standards 4 criteria. In addition, two precast, post-
and Technology tensioned concrete beam-to-column connec-
Gaithersburg, Maryland
tions similar in design to the monolithic Zone
4 specimens were tested. These tests
constitute the first phase of a multi-year test
program.

56 PCI JOURNAL
M
any experimental and analyti- on an economical and easily con- based on research data for precast con-
cal studies have been conduct- structible connection since economics crete construction in various seismic
ed in the past on the perfor- is a key consideration in the undertak- zones.
mance of reinforced monolithic con- ing of any construction project. Prior to presenting the main results
crete beam-to-column connections The overall test program involved of Phase I of the test program, a litera-
subjected to cyclic inelastic loadings. the testing of one-third scale model in- ture review is given. A detailed de-
However, there have been only a lim- terior beam-to-column connections. scription of the test program and test
ited number of studies on the perfor- This scale was selected as a result of results may be found in Reference 4.
mance of precast concrete connections the size limitations imposed by the test
and into a lesser extent on moment re- facility at NIST. The experimental
LITERATURE REVIEW
sistant precast concrete beam-to-col- program consists of three phases.
umn connections. This is true even The first phase of the experimental In recent years, several studies have
though precast concrete construction program included the tests of two been conducted on the behavior of
has been in use in the United States monolithic concrete beam-to-column precast beam-to-column connections
since the 1950s. connections designed in accordance designed to resist earthquake loads.
Due to the limited data available, it with 1985 UBC Seismic Zone 4 crite- This section will briefly describe the
has been presumed that precast con- ria and two monolithic beam-to-col- connection details and results. More
crete structures tend to be less ductile umn connections designed in accor- detailed information on each of these
and tend to have a less stable inelastic dance with UBC Seismic Zone 2 crite- studies is available in the references
response than cast-in-place structures. ria. The design was based on the 1985 listed at the end of the paper.
This is primarily due to the concentra- instead of the 1988 UBC requirements
tion of inelastic strains in the connec- because the former edition was in use New Zealand Studies
tion regions. Consequently, only gen- at the time the test program was initi- A study on the behavior of ten
eral provisions for the design of pre- ated. Results from these tests were in- monolithic interior concrete beam-to-
cast concrete structures have been in- tended to provide a reference for com- column connections was conducted by
cluded in American building codes parison with later precast concrete Park and Thompson at the University
[e.g., the Uniform Building Code connection tests. In addition, two post- of Canterbury. 5 Of the ten specimens,
(UBC)]. Since the UBC is the most tensioned precast concrete specimens one specimen was conventionally re-
commonly used or referenced code in designed similarly to the monolithic inforced, five specimens had fully pre-
seismically active areas in the United Zone 4 specimen were tested. Zone 4 stressed concrete beams, and four
States, precast construction is less will be taken to mean UBC Seismic specimens had partially prestressed
prevalent in these regions. Zone 4 and Zone 2 will be taken to concrete beams. The amounts of pre-
The need for a more comprehensive mean UBC Seismic Zone 2 throughout stressed and nonprestressed steel were
guideline for precast concrete struc- this paper. variables in this study. The specimens
tures has been recognized by both de- The second phase of the project will were designed so that hinging oc-
signers and researchers. '- 3 A workshop involve testing of three sets of post- curred in the beams at the column
conducted by the Applied Technology tensioned beam-to-column specimens. face. The columns were subjected to
Council on the design of prefabricated Each set will consist of two identical an axial load and the beam ends were
concrete buildings for earthquake specimens designed to investigate the subjected to reversed vertical loads.
loads 1 was held in 1981 to determine effects of location and distribution of Results from these tests showed that
current knowledge of precast concrete the prestressing tendons and to deter- the flexural strength of the beams ex-
structures and to identify research mine if any difference in performance ceeded the theoretical strength by an
needs. Forty research areas were iden- results from using prestressing strands average of 7 percent. A reduction in
tified and the topic receiving the high- instead of post-tensioning bars. strength and stiffness was more pro-
est priority was one which called for Phase III of the program will con- nounced in the specimens with the
the development of a recommended sider methods of improving the hys- fully prestressed concrete beams than
practice for moment resistant beam-to- teretic behavior of the precast concrete in the specimens with the partially
column connections.' specimens and the presence of precast prestressed beams due to the presence
In response to these needs, a study concrete slabs on the strength and duc- of nonprestressed steel in these speci-
of the behavior of precast concrete tility of the connections. Some areas in mens. Performance of the connection
beam-to-column connections subject- this phase will be coordinated with the regions was better for the fully pre-
ed to cyclic inelastic loading was initi- Precast Seismic Structural Systems stressed specimens. The presence of a
ated at the National Institute of Stan- (PRESSS) project which is part of the prestressing tendon at mid-depth of
dards and Technology (NIST) in 1987. U.S.-Japan large scale testing program the beam was found to improve the
The goal of the experimental program funded by the National Science Foun- performance of the connection region.
was to develop recommended guide- dation and by the Precast/Prestressed Bull and Park6 tested three full-scale
lines for the design of precast beam- Concrete Institute (PCI). In brief, the exterior precast beam-to-column con-
to-column connections in seismically intent of PRESSS is to develop com- nections at the University of Canter-
active regions. Emphasis was placed prehensive design recommendations bury. The specimens were composite

May-June 1991 57
connections consisting of a precast plates was used to resist flexural tested at the University of Minnesota
prestressed beam shell with a cast-in- stresses and the other to resist shear by French et al. 11 •12 The connection de-
place (CIP) concrete core. Specimens stress. Flexural reinforcement in the tails varied from post-tensioning with
l and 3 were detailed for seismic loads beam was welded to the beam flexural two post-tensioning bars (BMA), a
while Specimen 2 was not. The differ- plates. connection using four threaded rein-
ence between Specimens 1 and 3 was In these three studies, the connec- forcing bars (BMB), a composite con-
the bonding of the interface between tions were subjected to an axial load nection (BMC) consisting of a CIP
the beam shell and the CIP concrete in and to cyclic loading. Comparisons of topping and a precast concrete beam
the plastic hinge region. Specimen 3 the welded connections with similar connected with a post-tensioning bar,
was debonded over a length equal to connections cast monolithically indi- a welded connection (BMD), a bolted
the depth of the CIP beam core. cated that these welded connections connection (BME), a connection with
The columns were subjected to an performed as well as the monolithic four threaded reinforcing bars which
axial load and the specimens were specimens in terms of ductility, energy were threaded into couplers anchored
tested cyclically. Satisfactory behavior dissipation, and stiffness. in the column (BMF), and a connec-
was defined as the retention of 80 per- tion similar to Connection BMF with
cent of the specimen strength after the difference being the use of ta-
four cycles at 4~y Yield displace- American Studies pered-threaded splices (BMG). Speci-
ment, ~Y' was defined as 1.33 times In a study sponsored by PCI, eight mens BMA to BMF were exterior
the displacement of the beam end moment resistant and eight simple connections and Specimen BMG was
measured at 75 percent of the theoreti- connections were tested by Stanton et an interior connection.
cal ultimate strength. al., at the University of Washington. 10 Specimens BMA to BMD were de-
Specimens 1 and 3 performed satis- The objective of the program was to signed so that the plastic hinge oc-
factorily in terms of strength, ductility identify economical and competitive curred away from the connection re-
and energy dissipation and could, methods in designing precast concrete gion. Specimens BME to BMG were
therefore, be used in ductile seismic connections. Only the results of the designed so that the plastic hinge oc-
moment resisting frames. The debond- moment resistant connections are ap- curred in the connection region. The
ed specimen (No. 3) had a longer plas- plicable to seismic design and are pre- beams were partially prestressed. The
tic hinge length in the CIP concrete sented. specimens were subjected to reversed
than Specimen 1. The precast concrete The moment connections consisted cyclic inelastic loads. The load was
shell in Specimen 3 sustained no dam- of a welded connection (BC15), a applied at the beam end.
age while the precast concrete shell in combination of a cast-in-place topping The specimens with the plastic
Specimen 1 sustained extensive crack- and a welded connection (BC16A), a hinge occurring at the conventionally
ing. Specimen 2 experienced sliding bolted column-to-column connection reinforced joint region showed better
shear displacements in the beam at the (BC25 & CCI), a precast beam con- energy dissipation characteristics than
column face and small energy dissipa- structed into a CIP column (BC26), a those with the plastic hinge occurring
tion. post-tensioned connection (BC27), a in the prestressed concrete beams.
connection grouted or partially grout- Specimens BMA to BMD achieved in-
ed to dowels (BC28 & BC29), and a terstory drifts of at least 3.3 percent
Canadian Studies composite connection consisting of a while Specimens BME to BMG
Three studies conducted at the precast beam shell filled with CIP achieved interstory drifts greater than
Royal Military College were on weld- concrete using post-tensioning bars as 4 percent. In general, the threaded re-
ed precast concrete beam-to-column a means of attachment (BC99). The inforcing bar connection with the ta-
connections. These studies were car- specimens were two-third scale mod- pered splices and the composite con-
ried out by Pillai and Kirk, 7 Bhatt and els of prototype connections. Some of nection appear to be the most likely
Kirk, 8 and Seckin and Fu! The study the specimens were tested monotoni- candidates for use in seismically ac-
by Bhatt and Kirk was a continuation cally and some were tested cyclically. tive regions.
of Pillai and Kirk's work in which the A 0.04 radian rotation was defined as A test program at the University of
connection details were modified to the minimum requirement for a ductile Michigan conducted by Soubra et al. 13
prevent a weld fracture as experienced frame. studied the characteristics of fiber re-
in Pillai and Kirk's study. The results from these tests indicat- inforced concrete (FRC) composites
In Pillai and Kirk's and Bhatt and ed that the dowel connections (BC28 and examined the use of FRC in the
Kirk's studies, beam reinforcement and BC29) could not be classified as joint between two precast concrete el-
was welded to column reinforcement moment connections, Specimens ements. The specimens were made up
and embedded beam plates were weld- BCI6A and BC27 could possibly be of two precast concrete beams con-
ed to embedded column plates. The used in Seismic Zones 1 and 2, and nected with a CIP joint. The beam was
connections in Seckin and Fu's work Specimens BC26 and BC99 could be loaded cyclically at the third points. In
were made by welding two sets of em- used in Seismic Zones 3 and 4. this study, the parameters included
bedded beam plates to two sets of em- A series of seven precast concrete fiber type, volume of fiber and matrix
bedded column plates. One set of beam-to-column connections were type- mortar or concrete. Six speci-

58 PCI JOURNAL
mens were tested cyclically. The per- Several European studies involved in this review. However, some of
formance of the FRC joints was mea- the testing of connections with embed- these methods involve welding, cast-
sured against that of a joint construct- ded structural steel sections in the pre- in-place concrete, and bolting. These
ed using regular concrete. cast concrete elements. 1618 The speci- procedures increase the construction
Failure of the specimens was initiat- mens were in general tested monotoni- costs since they require better quality
ed by a single flexure crack which led cally. The findings indicated that the control and tighter construction toler-
to the eventual fracture of one or more precast concrete specimens performed ances and therefore, make a precast
reinforcing bars in the CIP joint. Con- adequately when compared with the concrete alternative less attractive.
clusions drawn from the study were performance of companion monolithic
that FRC joints performed better than specimens. Further details of these SPECIMEN DESIGN AND
joints cast with conventional concrete tests may be found in the references
and that FRC joints with steel fibers listed. TEST PROCEDURE
performed better than FRC joints with Several methods of developing sat- The design of the test specimens
plastic fibers. isfactory moment resistant precast was guided by the project steering
concrete connections have been shown committee comprised of individuals
Other Studies
The Japanese permit the use of pre-
cast concrete connections which have 1 in. :25.4 mm
been proven to have acceptable levels
of strength, rigidity, and ductility. 14
Joint acceptance is based on unit test-
6-#4
ing and member testing methods. Pro-
cedures for these test methods and
classifications of the joints based on
0.21 in. (5 mm)
the results of these tests are outlined smth. wire
0.21 in. (5 mm)
smth. wire
by the Building Center of Japan. As a @ 2 in. (51 mm) O.C.
@ 2 in. (51 mm) O.C.
result of this qualification method,
much of the research on the precast
concrete framing system in Japan is 8 -#3
funded by the designer and/or contrac-
tor and is therefore proprietary. Some
BEAM CROSS SECTKlN ca.UMN CROSS SECTKlN
such systems are discussed in Refer-
ence 15. Fig. 1. Reinforcement details for the Zone 2 specimens.

1n .25.4fM1

1 in. (25 mm) Post-tensioning bar


1.5 in. (38 mm) Corrugated duct

1-- Sin.--..1 1---- 10 in. ___.,J


1 (203 mm) 1 1 · (254mm) 1

T
8-#3.
9 -#3

T
4 -#4

0.21 in. (5 mm)


16 in. 8- 0.21 in. (5 mm)
smth. wire
18 in. smth. wire
@ 3.33 in. (85 mm) O.C. (406 mm)
(457mm

0.21 in. (5 mm)


smth. wire
5. #3
2- #4
j @ 1.33 in. (34 mm) O.C

Monolithic Post-Tensioned

BEAM CROSS SECTION COLUMN CROSS SECTION

Fig. 2. Reinforcement details for the Zone 4 specimens.

May-June 1991 59
from the PCI, Portland Cement Asso- tant connection. The connection de- prototype were a beam 20 x 30 in.
ciation (PCA), a consulting firm, and tails would be kept as simple as possi- (508 x 762 mm) and a column 24 x 30
academia. It was determined that the ble, i.e., no welding, bolting, corbels, in. (610 x 762 rum). The beam rein-
connections to be tested have details or cast-in-place topping. It would, forcement ratio for the bottom steel, p,
typical of those normally used for re- thus, be economical due to ease of was 1.3 percent and for the top steel,
inforced concrete office buildings con- construction and rapid erection and be p', was 1.8 percent. The column rein-
structed in Seismic Zones 2 and 4. As in keeping with the objective of the forcement ratio was 2.4 percent. The
stated earlier, the 1985 edition of the test program. Steel angles bolted to the reinforcement details are shown in
UBC was used instead of the 1988 precast concrete column would be Fig. 1.
edition. For the NIST test specimens, used in actual field practice as tempo- The transverse reinforcement for the
this meant that the design base shear rary supports for the precast concrete column consisted of rectangular ties
calculated using the 1985 UBC re- beams until they were post-tensioned spaced at 2 in. (51 rum) center-to-cen-
quirements was 15 percent greater and grouted to the column. ter with two transverse and three lon-
than the value calculated based on the gitudinal cross ties. The transverse re-
1988 UBC requirements. Zone 2 Specimen Design inforcement was continued through
The subassemblage selected for test- The design criterion for the Zone 2 the connection region. Both beam and
ing was an interior beam-to-column and Zone 4 specimens was the re- column longitudinal reinforcement
connection. From the literature review quired base shear. The model beam conformed to ASTM A706/A706 M
and through discussions with the steer- was .6.7 x 10.0 in. (169 x 254 rum) requirements. The design concrete
ing committee, it was determined that while the model column dimensions compressive strength was 5000 psi (34
a post-tensioned precast concrete con- were 8.7 x.10.0 in. (220 x 254 rum). MPa). The same mix design was used
nection was a potential moment-resis- The corresponding dimensions for the for all Zone 2 and Zone 4 specimens.

Axial Load
Loading direction
North-South
1
ZONE2 ZONE4 (East-West for B-M·Z.4)_ _ _~ il"
A-M-Z2& A-M-Z4& A-P-Z4&
B-M-Z2 B-M-Z4 B-P-Z4

a 10" 18" 18"


b 10 16 16
c 40 41-3/4 37
d 46 47-3/4 43

ra1
0
I
32"

f
b 0 0
_l
L 1
26"

0 1

1 in. = 25.4 mm

Fig. 3. Interior beam-to-column subassemblage.

60 PC! JOURNAL
post-tensioning load was maintained
while the nuts were tightened.
The post-tensioning ducts were cor-
rugated and grouted with a grout hav-
ing a design compressive strength of
6000 psi (41 MPa). The 1 in. (25 mm)
wide construction joint was filled with
a fiber reinforced grout. The joints
were subjected to high compressive
loads and it was felt that the fibers
would hold the grout together. One
and a half percent by volume of
straight 0.75 in. (19 mm) long steel
fibers were added to the grout mix.
The cross section of the fibers was ap-
proximately 0.015 x 0.025 in. (0.4 x
0.6 mm). The design compressive
grout strength for the joint was 10,000
psi (69 MPa). The faces of the beams
Fig. 4. Test setup and loading arrangement. and column were roughened to an am-
plitude of approximately 0.25 in. (6
Zone 4 Specimen Design mm).
consisted of four #3 bars with one bar
The model beam was 8 x 16 in. (203 in each comer of the tie. The column
x 406 mm) while the column dimen- steel arrangement was the same as for Test Procedure
sions were 10 x 18 in. (254 x 457 the monolithic specimen. No provi- The specimens were pinned at the
mm). The corresponding prototype sions were made to move the plastic column base and roller supported at
beam dimensions were 24 x 48 in. hjnge away from the column face. the beam ends and the column top as
(610 x 1219 mm) and the column di- Two 1 in. (25 mm) diameter post- shown in Fig. 3. These boundary con-
mensions were 30 x 24 in. (762 x 1372 tensioning bars with an ultimate stress ditions were chosen to model actual
mm). of 150 ksi (I 034 MPa) were used to conditions where the moments are ap-
The bottom beam reinforcement connect the precast concrete beams to proximately zero at midspan of the
ratio, p, was 0.7 percent and the top the precast concrete column. In this beam and the column.
reinforcement ratio, p', was 0.8 per- first exploratory phase of the test pro- The vertical and lateral loads were
cent. These reinforcement ratios are gram, post-tensioning bars were used applied as shown in Fig. 3. Each spec-
lower than the ratios for the Zone 2 instead of prestressing strands because imen was first loaded axially to a level
specimens due to the larger size beams prestress losses in short strands would of 0.1 f~ Ag. This is approximately half
used for the Zone 4 specimens. The be substantial due to seating losses. of the vertical load experienced by an
column reinforcement ratio was 2.0 The initial post-tensioning load was interior column in the third story of
percent. 128.6 kips (572 kN) which resulted in the prototype structure. The specimens
The transverse reinforcement con- an initial beam stress of 1008 psi (7 were then loaded laterally in-plane to
sisted of rectangular ties spaced at 1.3 MPa). The losses in the post-tension- 75 percent of the calculated ultimate
in. (34 mm) center-to-center with six ing bars were minimal because the beam moment in the forward (south)
transverse and two longitudinal cross
ties and was contin ued through the
connection region. The monolithic
Zone 4 reinforcement details for both
the beam and column are shown in 12
10
Fig. 2. The reinforcement conformed
to ASTM A 706/A 706 M require- " 8

~
ments. ::J
>=
The criterion used for designing the ()
::::>
0
Zone 4 precast concrete connections ....z 3/4
w ·3/4
was based on the strength of the ::;
w ·2
()
monolithic Zone 4 specimens. The s
Q.
-4
Ul
beam and column dimensions for the i5 ·6

precast concrete specimens were the ·8

same as for the monolithic concrete


Zone 4 specimens. The longitudinal
reinforcement for the precast beams Fig. 5 Loading history

May-June 1991 61
75.0

45.0 45.0

u;- 15.0 15.0


0.
g !;g.
"0
ft!
-15.0 ~
0
....J
0 -15.0
....J

-45.0 -45.0

-75.0 +-----1-----1---'--..._--1-----1 -75.0 1----1----4--'--~---4----1


-2.75 -1.65 -0.55 0.55 1.65 2.75 -2.75 -1.65 -0.55 0.55 1.65 2.75

Displacement (in.) Displacement (in.)


Specimen A-M-Z2 Specimen B-M-Z2
Fig. 6. Hysteresis curves for the monolithic Zone 2 specimens.

75.0 75.0

45.0 45.0

15.0 15.0
!
;g.
!;g.

~
"0

~ -15.0 -15.0

-45.0 -45.0

-75.0 -75.0
-2.75 -1.65 -0.55 0.55 1.65 2.75 -2.75 -1.65 -0.55 0.55 1.65 2.75

Displacement (in.) Displacement (in.)


Specimen A-M-Z4 Specimen B-M-Z4
Fig. 7. Hysteresis curves for monolithic Zone 4 specimens.

75.0 75.0

45.0 45.0

15.0
i 15.0
i;g.
;g.

~ -15.0 ~
....J
-15.0

-45.0 -45.0

-75.0 -75.0
-2.75 -1 .65 -0.55 0.55 1.65 2.75 -2.75 -1.65 -0.55 0.55 1.65 2.75

Displacement (in.) Displacement (in.)


Specimen A-P-Z4 Specimen B-P-Z4
Fig. 8. Hysteresis curves for precast post-tensioned Zone 4 specimens.

62 PCI JOURNAL
direction and then in the reverse
(north) direction. The top column dis-
placements were recorded in each di-
rection. The yield displacement, !J.y,
was then defined as the average of the
two column displacements divided by
0.75 . Although this displacement is
the displacement of the column top, it
corresponds to yielding in the beam.
Fig. 4 shows the test setup and the test
facility.
The loading history (see Fig. 5)
comprised two cycles at ± 2/J.y and ±
4/J.y, three cycles at ± 611y and ± 8/J.y,
two cycles at ± 10/J.y, and finally three
cycles at ± 12/J.y The loading histories
for the monolithic Zone 2 specimens
varied slightly in that the specimens
underwent three cycles at 4/J.y instead
\
of two cycles. This was because the Fig. 9. Representative failure mode of a monolithic Zone 2 specimen.
lateral load in the second cycle at 4/J.y
fell below 80 percent of the lateral
load in the first cycle at 4/J.y Failure Fig. 9. This failure mode was most the connection region. The column
of a specimen was defined as the point likely a result of insufficient confine- crack widths were less than 0.06 in. (2
at which the applied lateral load was ment provided by the transverse rein- mrn) at failure . Fig. 10 shows one of
less than 80 percent of the lateral load forcement. The only damage observed the monolithic Zone 4 specimens at
obtained for the first cycle at 2/J.y The in the beams of these specimens was failure.
test was conducted under displace- some flexural and shear cracking. The precast concrete specimens
ment control. As expected, the failure mode of the failed as a result of their inability to
monolithic Zone 4 specimens was sustain higher loads due to localized
hinging in the beams. There were also yielding of the grouted post-tensioning
TEST RESULTS some prominent shear cracks in the bar. This yielding allowed for an
All the specimens were subjected to hinge region . These shear cracks ap- opening of approximately 0.5 in. (I 3
the basic loading history described peared at 2/J.y and widened in the sub- mm) between the beam and column at
previously. However, the loading his- sequent cycles. The columns of these failure and crushing of concrete in the
tory for the precast concrete speci- specimens were basically undamaged beams. As with the monolithic Zone 4
mens was modified due to limits of the except for flexure and shear cracks in specimens, the precast concrete col-
test facility. The stroke in one direc-
tion was limited to 811 . Therefore,
subsequent cycles after tfuee cycles at
± 8/J.y were 10/J.y or 12/J.y in one direc-
tion and 8~y in the reverse direction.
The hysteresis curves for the mono-
lithic Zone 2, monolithic Zone 4 and
precast concrete specimens are shown
in Figs. 6 to 8. The nomenclature for
the specimens was as follows: First.
character is the specimen name, sec-
ond character - M for monolithic and
P for precast, third and fourth charac-
ters - Z2 for Zone 2 and Z4 for Zone
4.

Failure Modes
The failure modes for the three sets
of specimens tested were different.
The monolithic Zone 2 specimens I r
'
~
failed predominantly in shear in the / bi . . . .J . . .
column connection region as shown in Fig. 10. Representative failure mode of a monolithic Zone 4 specimen.

May-June 1991 63
stiffer than the monolithic Zone 4
specimens. As shown in Table I, the
post-tensioned specimens were ap-
proximately twice as stiff as their
companion monolithic specimens and
five times as stiff as the monolithic
Zone 2 specimens.

Flexural Strength
The calculated and measured maxi-
mum beam moments are given in
Table 2. The calculated values were
based on an ultimate concrete strain of
0.003 and actual material properties
for the steel and concrete. A factor of
1.25 was applied to the yield stress to
account for steel strain hardening for
the monolithic specimens. However,
Fig. 11. Representative failure mode of a precast Zone 4 specimen.
no factor was applied to the yield
stress for the precast concrete speci-
mens to account for strain hardening
umns had only sustained flexure and unsymmetric loading. This value is because the yield stress of the post-
shear cracks. Fig. 11 shows one of the higher than the ultimate displacement tensioning bars was 148.5 ksi (1024
precast concrete specimens at failure. ductility, llu =6, obtained by the mono- MPa) and the ultimate stress was
lithic Zone 4 specimens. This increase 159.7 ksi (1101 MPa). Also, the four
Displacement Ductility in ductility may be a function of the #3 bars in the bea~s were neglected
steel location. The post-tensioning when computing the moment for the
The ultimate displacement ductili-
bars in the precast concrete specimens precast concrete specimens. The mea-
ties, llu and the ultimate story drifts for
were located closer to the beam center sured maximum beam moments were
all the specimens are listed in Table 1.
than was the mild steel reinforcement obtained by multiplying the peak
Displacement ductility, J..l, is defined as
in the monolithic specimens. beam load as recorded by the load cell
the ratio of the maximum displace-
Although the post-tensioned speci- by the lever arm.
ment attained at any cycle to the yield
mens achieved higher displacement The average of the four measured
displacement. Ultimate displacement
ductilities than the monolithic speci- maximum beam moments for the
ductility, llu is defined as the displace-
mens, the story drifts at failure were monolithic Zone 2 specimens is 54
ment ductility obtained when the con-
essentially equal for both sets of Zone kip-ft (73 kN-m). This value is 8.5
nection was considered to have failed.
4 specimens. This was because the percent higher than the calculated ulti-
Story drift is defined as the ratio of the
precast concrete specimens were mate moment. However, it should be
story displacement to the story height.
As shown in Table 1, the monolithic
Zone 2 and Zone 4 specimens
achieved similar ultimate displace- Table 1. Yield displacement and displacement ductility.
ment ductilities,• llu =6. The monolith-
ic Zone 4 specimens were approxi- Compressive Initial
strength Measured Ultimate elastic Story drift
mately three times as stiff as the of concrete* yield displacement connection at
monolithic Zone 2 specimens. As a re- ~~ displacement ductility stiffness t failure
sult of this and since both sets of spec- Specimen (psi) (in.) J.lu (kips/in.) (percent)
imens achieved the same ultimate dis-
placement ductilities, the story drifts A-M-Z2 6310 0.359 6 44 4.14
at failure for the monolithic Zone 2 B-M-Z2 5960 0.371 6 38 4.28
specimens were greater that those for A-M-Z4 4450 0.263 6 121 3.02
the monolithic Zone 4 specimens. B-M-Z4 4670 0.293 6 103 3.38
The ultimate displacement ductility
A-P-Z4 5890 0.160 10 204 3.07
for the precast concrete specimens was
B-P-Z4 6450 0.179 10 216 3.44
conservatively taken as 10 due to the
* Represents strengths obtained from 4 x 8 in. cylinder tests at the time of specimen testing. The same mix design
* The uhimate displacement ductility for Specimen was specified for all sets. However, each set of specimens was cast at different times.
A-M-Z2 was reponed incorrectly in Reference 4. t The initial elastic flexural stiffness was set equal to the slope of the load-displacement plot for the first cycle to
An explanation for thi s error is given in Reference 0.75/'J.y on the initial excursion.
19. Metric (Sf) conversion factors: I in. =25.4 mm; I ksi =6.895 MPa; I kip/in . =0 . 175 kN/mm.

64 PCI JOURNAL
noted that it was the deterioration of compared with the monolithic speci- monolithic Zone 4 specimens is ap-
the column connection region which mens could in part be a result of strain proximately one-third of the maxi-
led to the eventual failure of the con- hardening of the post-tensioning bars mum recommended shear stress of
nection and not beam degradation. which was not taken into account. 1:
20 {7: ( in psi). This low joint
The calculated ultimate moment for stress was evidenced by the excellent
the column using actual material prop- performance of the joint for the dura-
erties with an axial load of 5l.l5 kips Joint Stress tion of the test. The joint shear stress
(227 .5 kN) is 69 kip-ft (94 kN-m). The The experimental joint shear stress- for the precast concrete specimens is
measured maximum column moment es for monolithic Specimens A-M-Z2 approximately two-thirds of the maxi-
was 57 kip-ft (77 kN-m) at mid-col- and B-M-Z2 were 1.62 and 1.64 ksi mum recommended shear stress. The
umn. (11 and 1.64 MPa), respectively. measured value may be less than the
The average of the four measured These stresses are greater than calculated value due to slippage of the
maximum moments is 109 kip-ft (148 20 {7: U:in psi) which is the maxi- post-tensioning bar and/or duct in the
kN-m) for the monolithic Zone 4 spec- mum allowable joint stress recom- column region.
imens and 134 kip-ft (182 kN-m) for mended by ACI-ASCE Committee
the precast concrete specimens. These 352. A lack of sufficient transverse Energy Dissipation
values are 12.4 and 17.5 percent high- confinement led to joint failure in the
A comparison of the energy dissi-
er than the calculated moments for the monolithic Zone 2 specimens prior to
pated on a per cycle basis up to the
monolithic and precast concrete speci- the onset of beam failure.
third cycle at 6.1y is given in Fig. 12
mens, respectively. The higher value The calculated joint shear stress
for all the specimens. The energy dis-
for the precast concrete specimens as using actual material properties for the
sipated per cycle is defined as the area
enclosed by the load-displacement
plot. The cumulative energy dissipated
Table 2. Comparison of the flexural strengths.
at various stages in the test is given in
Table 3. The cumulative energy dissi-
Compressive
strength Calculated Measured
pated at a particular ductility level was
of concrete* ultimate maximum obtained by summing the per cycle en-
~~ moment,M1 moment,t M2 Avg.ofM2 ergy dissipated up to that point. The
Specimen (psi) (kip-ft) (kip-ft) Mt cumulative energy dissipated to the
third cycle at 6.1y is of interest be-
A-M-Z2 6310 50.0 51 & 59 1.10 cause the load histories for the precast
B-M-Z2 5960 50.0 52 & 55 1.07 concrete specimens and the monolithic
A-M-Z4 4450 97.0 109 & 106 1.11 Zone 4 specimens were identical up to
B-M-Z4 4670 97.0 109 & 113 1.14
this stage. This is also the stage at
which the monolithic Zone 4 speci-
A-P-Z4 5890 114.0 130 & 135 1.16
mens failed. The precast specimens
B-P-Z4 6450 114.0 136 & 137 1.20 did not fail at this stage and underwent
* Represents strengths obtained from 4 x 8 in. cylinders at the time of specimen testing. additional cycles until failure oc-
t Moments measured at the two column faces of the interior connection. curred.
Metric (SI) conversion factors: I ksi = 6.895 MPa; I kip-ft = 1.356 kN-m. As seen in Fig. 12 and Table 3, the
energy dissipated by the post-ten-
Table 3. Comparison of the cumulative energy dissipation. sioned specimens was closer in range
to the energy dissipated by the mono-
Compressive Cumulative energy dissipated to lithic Zone 2 beam-to-column connec-
strength Ultimate tions.
of concrete displacement On a per cycle basis, the energy dis-
J; ductility Failure M.y,Cycle3 12.1Y' Cycle l sipated by the post-tensioned speci-
Specimen (psi) llu (kip-in.) (kip-in.) (kip-in.)
mens was approximately 30 percent of
A-M-Z2 6310 6 186 165*•t -
the energy dissipated by the monolith-
ic Zone 4 specimens. The average of
B-M-Z2 5960 6 204 212t -
the cumulative energy dissipated by
A-M-Z4 4450 6 597 597 -
the post-tensioned connections was
B-M-Z4 4670 6 543 543 - approximately 20 percent lower than
A-P-Z4 5890 10 438 165 507 the energy dissipated to failure by the
B-P-Z4 6450 10 477 181 550 monolithic Zone 4 specimens.
As stated earlier, the ultimate dis-
* Cumulative energy dissipated through the second cycle at 6t.Y" placement ductility for the post-ten-
tFor purposes of comparison. the energy dissipated in the third cycle at 4t.y was not included in this summation as
the Zone 4 specimens did not undergo this particular cycle. sioned specimens was conservatively
Metric (SI) conversion factors: I kip-in.= 0.113 kN-m. considered to be 10. If the ultimate

May-June 1991 65
>. specimens was higher than 6 obtained
<l kip-in = 0.113 kN-m
CD
for their companion monolithic speci-
175 mens. However, since the precast con-
>.
<l crete specimens were stiffer than the
150
CD monolithic specimens, the story drifts
at failure for the Zone 4 post-ten-
>. sioned and monolithic specimens were
fiZI A-M-Z2

••
<l
125 almost identical. The story drifts at
CD B-M-Z2
c >.
:! <l A-M-Z4 failure for the Zone 4 specimens
'<!'

I
100 0 B-M-Z4 ranged from 3.0 to 3.4 percent. The


>.
<l A-P-Z4 post-tensioned specimens were ap-
'<!'
el B-P-Z4 proximately twice as stiff as the
75
~
w
monolithic Zone 4 specimens and five
times as stiff as the monolithic Zone 2
50 >.
>. specimens.
<l
>. <l >. '<!' 3. The flexural strength of the pre-
<l C\1 <l
cast concrete Zone 4 connections was
25
slightly greater than flexural strength
of the monolithic Zone 4 specimens.
0 The measured maximum beam mo-
2 3 4 5 6 7 8 9 ments were on the average 18 and 13
~ 1\Urrtler
percent greater than the calculated mo-
ments (as defined previously) for the
Fig. 12. Cyclic energy dissipated up to the third cycle at 6~y for all specimens. precast concrete specimens and the
monolithic Zone 4 specimens, respec-
displacement ductility was considered Results from the monolithic con- tively. The monolithic Zone 2 speci-
to be 12 instead of 10, the cumulative crete tests are used as a benchmark mens achieved measured maximum
energy dissipated up to the first cycle reference for both present and future beam moments that were on the aver-
at 12~y would be 507 and 550 kip-in. precast concrete tests. The objective of age 8 percent greater than the calculat-
(57 and 62 kN-m) for Specimens A-P- the test program was to develop an ed moment.
Z4 and B-P-Z4, respectively. The av- economical moment-resistant precast 4. When comparing the energy dis-
erage of these two values is approxi- beam-to-column connection for seis- sipated per cycle, the behavior of the
mately 10 percent lower than the aver- mically active regions. The following precast concrete specimens was closer
age of the cumulative energy dissipat- paragraphs present the conclusions to that of the monolithic Zone 2 speci-
ed by the monolithic Zone 4 drawn from the results of the Phase I mens than to the monolithic Zone 4
specimens to failure. tests. specimens. On a per cycle basis, the
1. Failure of the monolithic Zone 2 post-tensioned specimens dissipated
specimens occurred in the joint region about 30 percent of the energy dissi-
SUMMARY AND pated by the monolithic Zone 4 speci-
due to a combination of high joint
CONCLUSIONS stresses and inadequate confinement. mens. However, since the precast con-
In Phase I of the precast concrete The monolithic Zone 4 specimens crete specimens achieved higher dis-
beam-to-column connection study at failed as a result of beam hinging and placement ductilities than the mono-
NIST, six specimens were tested. Two deterioration. Failure of the precast lithic specimens, the average of the
of the specimens were monolithic con- concrete specimens was characterized cumulative energy dissipated up to
crete connections designed to UBC by plastic elongation of the post-ten- failure by the post-tensioned speci-
( 1985) Seismic Zone 2 criteria. The sioning bars and crushing and spalling mens was approximately 80 percent of
other four specimens were designed to of the concrete cover in the beams . that for the monolithic specimens. The
UBC (1985) Seismic Zone 4 criteria. Joint shear stresses for the Zone 4 average of the cumulative energy dis-
Two of the Zone 4 specimens were specimens were below the recom- sipated up to failure by the monolithic
monolithic concrete specimens while mended value of 20 {7; ( in psi) t: Zone 2 specimens was about 33 per-
the remaining two were precast con- while the shear stresses in the mono- cent of that dissipated by the mono-
crete with post-tensioned beam-to-col- lithic Zone 2 specimens were above lithic Zone 4 specimens.
umn connections. The precast concrete the recommended value.
elements were connected by two post- 2. The ultimate displacement ductil- RECOMMENDATIONS
tensioning bars. The construction joint ities for the monolithic Zone 2 speci-
between the beam and column was mens were 6. These ductilities corre-
AND FUTURE
filled with a fiber reinforced grout and sponded to story drifts of 4.1 and 4.3 RESEARCH NEEDS
the post-tensioning ducts were grouted percent. The ultimate displacement Based on the results of the NIST
after tensioning. ductility of I 0 for the precast concrete Phase I test program, it appears that a

66 PCI JOURNAL
post-tensioned precast concrete beam- precast concrete elements. The use of ACKNOWLEDGMENT
to-column connection is as strong and strands is more common than post-ten-
The authors would like to extend
as ductile as a monolithic connection sioning bars in practice. As stated pre-
their thanks to the individuals who
and is a viable connection for high viously, a means of improving the
contributed to this project. The assis-
seismic regions. However, the energy hysteretic behavior of the precast con-
tance and support of the laboratory
dissipation characteristics, per cycle crete specimens by debonding the pre-
staff for the Building and Fire Re-
and cumulative, of the precast con- stressing strands in the column con-
search Laboratory, Structures Division
crete connections could be improved. nection region will be examined in
especially that of Mr. Frank Rankin is
Further means of improving the ener- Phase III of the test program. The in-
gratefully acknowledged. Also, the au-
gy characteristics need to be explored fluence of slabs on the connection be-
thors would like to express their
as energy dissipation is an important havior will also be studied in this
thanks to the steering committee for
factor in high seismic regions. phase. providing technical guidance through-
One possible method of improving Acceptance of this type of precast
out the project. Members of the steer-
the energy dissipation capacity of the concrete connection will require more
ing committee include Dr. Robert En-
precast concrete connections is being research data and a better understand-
glekirk, Dr. S. K. Ghosh, Mr. Daniel
investigated in Phase II of the NIST ing of the connection behavior. Other
Jenny, Mr. Paul Johal, and Dr. Nigel
test program currently underway. This considerations that require further
Priestley. The assistance of Ms.
procedure involves moving the post- study include the use of prestressed
Suzanne Nakaki in providing the de-
tensioning bars closer to the beam concrete beams, ungrouted strands,
sign of the test specimens is much ap-
center. Also, in this phase, prestress- lightweight aggregate, and the influ-
preciated.
ing strands will be used to connect the ence of transverse beams.

REFERENCES
I. Applied Technology Council, "Design 8. Bhatt, P., and Kirk, D. W., "Tests on Joints," Proceedings, U.S.-Japan Sem-
of Prefabricated Concrete Buildings an Improved Beam Column Connec- inar on Precast Concrete Construction
for Earthquake Loads," Berkeley, CA, tion for Precast Concrete," ACI Jour- in Seismic Zones, V. 2, Tokyo, Japan,
1981. nal, V. 82, No. 6, November-Decem- October 1986, pp. 137-156.
2. Clough, D. P., "Design of Connections ber 1985,pp. 834-843. 15. Kanoh, Y., "Review of Japanese Pre-
for Precast Prestressed Concrete 9. Seckin, M., and Fu, H. C., "Beam-Col- cast Concrete Frame Structures Used
Buildings for the Effects of Earth- umn Connections in Precast Rein- as Building Structures," Seminar, Pre-
quake," Technical Report No. 5, Pre- forced Concrete Construction," ACI cast Concrete Construction in Seismic
cast/Prestressed Concrete Institute, Structural Journal, V. 87, No. 3, May- Zones, Japan Concrete Institute, Japan,
Chicago, IL, March 1985. June 1990, pp. 252-261. 1986, pp. 35-54.
3. Hawkins, N. M., and Englekirk, R. E., 10. Stanton, J. F., Anderson, R. G., Dolan, 16. Clarke, J. L., "The Behavior of a Pre-
"U.S.-Japan Seminar on Precast Con- C. W., and McCleary, D. E, "Moment cast Beam-Column Joint," Precast
crete Construction in Seismic Zones," Resistant Connections and Simple Concrete, (United Kingdom), October
PCI JOURNAL, V. 32, No. 2, March- Connections," Research Project No. 1978,pp.503-504.
April 1987, pp. 75-85. I !4, Precast/Prestressed Concrete Insti- 17. Reinhardt, H. W., and Stroband, J.,
4. Cheok, G. S., and Lew, H. S., "Perfor- tute, Chicago, IL, 1986. "Load Deformation Behavior of the
mance of 1/3-Scale Model Precast 11. French, C. W., Hafner, M., and Cutting Dowel Connection," Mechani-
Concrete Beam-Column Connections Jayashankar, V., "Connections Be- cal & Insulating Properties of Joints of
Subjected to Cyclic Inelastic Loads," tween Precast Elements - Failure Precast Reinforced Concrete Elements,
NISTIR 4433, National Institute of Within Connection Region," ASCE Proceedings, RILEM-CEB-CIP Sym-
Standards and Technology, Gaithers- Journal of Structural Engineering, V. posium, V. I, Greece, September 1978,
burg, MD, October 1990. 115, No. 12, December 1989, pp. pp. 197-208.
5. Park, R., and Thompson, K. J., "Cyclic 3171-3192. 18. Wilby, C. B., "Structural Behavior of a
Load Tests on Prestressed and Partial- 12. French, C. W., Amu, 0., and Special Type of Joint for Connecting
ly Prestressed Beam-Column Joints," Tarzikhan, C., "Connections Between Precast Concrete Members," Mechani-
PCI JOURNAL, V. 22, No. 5, Septem- Precast Elements - Failure Outside cal & Insulating Properties of Joints of
ber-October 1977, pp. 84-110. Connection Region," ASCE Journal of Precast Reinforced Concrete Elements,
6. Bull, D. K., and Park, R., "Seismic Re- Structural Engineering, V. 115, No. 2, Proceedings, RILEM-CEB-CIP Sym-
sistance of Frames Incorporating Pre- February 1989, pp. 316-340. posium, V. II, Greece, September
cast Prestressed Concrete Beam 13. Soubra, K. S., et al., "Fiber Reinforced 1978, pp. 489-501.
Shells," PCI JOURNAL, V. 31, No.4, Concrete Connections for Earthquake 19. Cheok, G. S., and Lew, H. S., "Perfor-
July-August 1986, pp. 54-93. Resistant Design of Precast Reinforced mance of l/3-Scale Model Precast
7. Pillai, S. U., and Kirk, D. W., "Ductile Concrete Structures," Report No. Concrete Beam-Column Connections
Beam-Column Connection in Precast UMCE 89-13, University of Michigan, Subjected to Cyclic Inelastic Loads,"
Concrete," AC/ Journal, V. 78, No. 6, Ann Arbor, MI, October 1989. Report No. 2, NIST publication in
November-December 1981, pp. 480- 14. Imai, H., and Kanoh, Y., "Standard for preparation.
487. Performance Evaluation of Rebar

May-June 1991 F.7

You might also like