2.

WORK SCOP

The followings main works will be carried out to construct Ground Reservoir prior to
Start Excavation work.
• Root removing
• Site Clearing and top soil removing

3.TIME FRAME AND DURATION

Estimated time duration for the cleaning work of P. Ground Reservoir land is 04 Days.

4. SEQUENCE OF WORKS

4.1 SITE CLEARING


Machinery and tools use for the work.
01. J.C.B Machine
02. Small tools (Mamotee, knife, crowbar etc.)
03. Lorry (or a Boom truck)

4.2 MANPOWER REQUIRED FOR THE WORK


No Person Nos Responsibilities Full Time/ Part
Time
1 Site Engineer 01 Ensure Safety, Progress and Quality of Part Time on Site
the work and communication with the
Engineer and respond to the Engineer’s
requirements.
2 Assistant 01 Ensure Safety, Progress and Quality of Part Time on Site
Engineering the work.
3 Site Safety 01 Ensure Safety, Progress and Quality of Part Time on Site
Officer the work.
4 Skilled labours 01 Progress and Quality of the work. Full Time
5 Un-Skilled 02 Progress, Quality of the work and help Full Time
labours to Skilled labours.
6 Heavy Vehicle 02 Ensure Safety and Progress of the Full Time
Drivers & Work.
Operators