PROJEK MASS RAPID TRANSIT LEMBAH KELANG -JAJARAN SG BULOH - KAJANG PROJECT MASTER PROGRAMME

Activity ID Activity Name Year


1 2 3 4 5 6 7 8 9

PROJECT MASTER PROGRAMME


ADVANCE WORKS / LAND ACQUISITION PROCESS
A1000 Land Acquistion Process
A1010 Advance Works
A1020 Commencement of Works
CONTRACT PROCUREMENT
A1030 Civil Works
A1040 Railway System
CIVIL CONSTRUCTION
A1050 Depot Construction
A1060 Viaducts Construction
A1070 Elevated Station Construction
A1080 Multi Storey Carpark Construction
A1090 Underground Station Construction
A1100 Tunnel Works
RAILWAY SYSTEM INSTALLATION
A1120 Track Works Installation
A1130 System Works Installation
TESTING AND COMMISSIONING
A1150 System Acceptance Test, Integration Test, Trial Operation for Phase 1
A1160 System Acceptance Test, Integration Test, Trial Operation for Phase 2
FINALISATION AND HANDOVER
A1180 Phase 1 Completion (Sg Buloh to Semantan Portal)
A1190 Defects Liability Period
A1200 Phase 2 Completion (Semantan Portal to Kajang)
A1210 Defects Liability Period

Remaining Work Milestone DLP Page 1 of 1 Revision 8.0