You are on page 1of 21

National10 TH

BIM Report 2020


ANNUAL
The definitive industry update

BIM
REPORT
2020
Introduction 03
Richard Waterhouse, Chief Strategy Officer, NBS

The UK BIM Framework 04


Emma Hooper, Digital Information Specialist, Bond Bryan Digital

RIBA Plan of Work 2020 and specification 10


Dale Sinclair, Director of Technical Practice, AECOM

Summary of findings from the tenth annual BIM survey 14


David Bain, Research Manager, NBS Richard Waterhouse
Chief Strategy Officer, NBS
The adoption of Uniclass 2015 in Australia 30
John Gelder, University of South Australia

BIM beyond the labels


Mike Turpin, BIM Consultant and Director, Innovating Futures
36
Introduction
In 2010, we carried out a survey into an emerging new way of working:
‘building information modelling’. We published the results in spring 2011, noting that it was
the first time that 43% of the 400 people who took part in that survey had heard of BIM.

In my introduction to the first report, is not the resounding success that it should manufacturer components – and
I set out our intention to track changes be. Even now, only 40% report that BIM is create a digital environment within which
in attitudes towards BIM, as well as its the norm, with a similar figure using the BS all members of the project team can
implementation. We have done this and ISO standards processes: a true test of collaborate. As more people use platforms
annually, consulting with you, sharing BIM and connected information. Almost two like these, more technological solutions
your thoughts and experiences and thirds of small practices yet to adopt BIM emerge and familiarity with the standards
providing case studies, knowledge state that their projects are too small for grows; we hope to see a further shift in
and guidance from industry experts BIM, and over half that it is not relevant to the industry with benefits for all.
and practitioners. them, a lack of client demand remaining
the most common barrier. Whilst we do Ten years ago, the UK Government’s
The industry has made great strides over need to share these benefits more widely challenge to the industry was to deliver
the last ten years. We have gone from so that one-off clients also request BIM, efficiency through digital transformation.
limited to almost universal awareness surely these SMEs should recognize the The challenges we face now seem even
and use by 73% of professionals in 2020. benefits and promote them to their clients? greater than in 2011. COVID-19 has
It has required substantial change to The challenge now is to make BIM work for driven changes in living and working
workflows but has brought benefits: all parts of the industry. conditions; economies and construction
improved coordination of information, are experiencing the largest falls in output
reduced risk, improved productivity, greater But progress is being made. Use of seen in decades, and there are significant
efficiency, and operation and maintenance common data environments to share risks to people’s health and wellbeing.
We would like to thank the following organizations for supporting this report by circulating the survey on savings. These improvements are helping project information is becoming increasingly Before this crisis, the industry needed to
our behalf: to create a more efficient, transparent prevalent, and shows how the industry respond to the Grenfell Tower tragedy and
industry that makes fewer mistakes. The has moved from being predominantly life outside of the EU, as well as responding
Government’s response to the Hackitt paper-based. Aligned to this, the last decade to the increasing urgency of keeping rises
Report (announced in April) and the new has seen a major shift from the production in global temperature below 1.5 degrees
regulatory framework sets out a role for of 2D drawings to 3D digital models. The Celsius. These have huge implications
BIM and digital in establishing a ‘golden industry has also made huge progress in for design and construction in the UK and
thread’ of information. Survey respondents developing standards and guidance for BIM globally. As we reflect on ten years of BIM,
agree that digital technology can help with the UK playing a key role, and we’re digital transformation and the progress
here, with 70% saying that it will improve delighted to have articles in this report on that the industry has made, we may want
health and safety; 69% see its potential the new UK BIM Framework, the RIBA Plan to cast an eye to 2030 and the greater
to address sustainability; and 81% of Work and the successful application of changes needed to meet these challenges.
anticipate improvements in productivity. Uniclass 2015 in Australia.

It is hard to dispute that digital tech and At NBS, we firmly believe that well-structured
BIM have changed the industry, and that digital information can help us address the
the benefits are real. Repeat clients and challenges we face. Our new cloud-based
construction team members are likely to solutions, NBS Chorus and NBS Source,
NBS Enterprises Ltd © 2020 All rights reserved. No part of this report may be reproduced or shared in any
be the proficient users, gaining the benefits support the industry by connecting data
form or by any means, electronic or mechanical, including photocopying, recording, or by any information listed above. But scratch the surface and it between specifications, models and
storage or retrieval system, without permission in writing from the copyright holder.

The content of articles contributed by external authors and published in this report are the views of those
authors and do not represent the position of NBS Enterprises Ltd, NBS or its affiliated companies.

2 National BIM Report 2020 The definitive industry update 3


The UK BIM Framework
Many of you will be aware of the work that the UK has progressed over the past decade
Emma Hooper in relation to building information modelling standards, and the 1192 series in particular.
Digital Information The 1192 series became popular not just here in the UK but overseas as well,
Specialist, as clients saw the benefit of its adoption. Following on from this, the decision was made to start
Bond Bryan Digital
to elevate the British Standards to an international level, and this process began in 2014.

The ISO 19650 series


December 2018 saw the first release of The new International Standards combat
these International Standards in the form of: this by providing a framework where
information is considered from the outset
• BS EN ISO 19650-1 – the concepts and
of a project, using the following principles:
principles of information management
using building information modelling. • Information requirements are defined
before information is created, to aid
• BS EN ISO 19650-2 – the delivery phase
selection of delivery teams.
of information management using
building information modelling. • The delivery of information to meet
the requirements is planned and tested.
These standards build upon the groundwork
• The delivery of information is carefully
of some of the 1192 series, as BS
managed within a common data Andy Boutle, Head of BIM
1192:2007+A2:2016 and PAS 1192-2:2013
environment. Kier Construction (guidance author)
have now been superseded. It is now
much clearer that we are focusing on the • The delivered information is checked
’It is a real privilege being a
management of all information (whether against the original requirements, and
contributing author to this guidance,
it’s a report, a drawing or a model, etc.). either accepted or rejected accordingly.
to be able give back to industry
Parts 3, 4 and 5 of the 1192 series are These measures are there to help and help to facilitate the consistent
currently going through the same process reduce the risk and waste associated practical implementation of the
of being developed into International with information – which is commonplace ISO 19650 series across the built
Standards. The current timetable for throughout the design, construction, environment. We have a fantastic
publication is as follows: operation and maintenance of an asset. team of practitioners from varying
roles and disciplines working on a
• ISO 19650-3 – due for publication in Q4. pro-bona basis. My hope and belief
Going forward, the ISO 19650
• ISO 19650-5 – due for publication in Q2. framework provides the foundations to is this ongoing guidance will help
enable machine-interpretable information industry to reach a business as usual
• ISO 19650-4 – currently in the early
to be exchanged by technology in state for modern day information
stages of development.
a much more efficient way, improving management practices, building
In this age, information underpins interoperability. the vital foundations for the path
everything we do. We require more ahead to digital transformation’.
information than ever before, and our
technology creates more than ever before.
However, these two developments aren’t
in sync, and our exchange of information
is often executed poorly.

In this age, information underpins everything we do.


We require more information than ever before, and our
technology creates more than ever before.

4 National BIM Report 2020 The definitive industry update 5


Top left: Physical assets need to be specified. Below Left: Guidance Part 1. Guidance Part 2.
Bottom left: Information is also an asset, and therefore it needs to be specified. Below: Section 3, about information requirements.

John Ford,
BIM & Digital Delivery Director
Galliford Try (guidance author)

‘Not too many people are familiar


with ISO 19650. It’s now the
responsibility of those few to help
expand and explain ISO 19650 into a
digestible, contextualised guide that
everyone can understand. This is
where the collaborative guidance
comes in published on the UK BIM
Framework website, where dozens
The ISO 19650 guidance
of contributors offer their time for
free to help industry grasp ISO The development of the ISO 19650 Like the standards, the guidance is split The second part, now in its third edition,
19650`s information management guidance is a live project which started into two parts: is much more detailed. It currently contains
and modelling principles so that we 18 months ago. It’s supported by a team these sections:
• ‘Guidance Part 1: Concepts’.
can all move forward, together!’ of passionate individuals from different 1.0 ‘About ISO 19650 parties, teams
industry sectors and organizations, • ‘Guidance Part 2: Processes for and resources’.
volunteering their time and sharing their Project Delivery’. 2.0 ‘About the common data
experience and knowledge. The guidance
environment (CDE)’.
The UK BIM Framework project is open to anyone who is willing
to help, and I’ve been fortunate to work The first part was first released in April 2019, 3.0 ‘About information requirements’.
Learning from the many interpretations and It also plays an important role in dispelling However, we are less certain on how
on the initiative from the start. and is a high-level overview of all the key 4.0 ‘About the BIM execution plan’.
contradictions of the 1192 series, the UK the myths and rumours about building to specify information, then to manage,
activities and principles associated with
BIM Alliance, the Centre for Digital Built information management and modelling deliver and check it. These standards are 5.0 ‘ISO 19650-2 clause 5: analysis
The aim of the guidance is not to replace information management in the ISO 19650
Britain (CDBB) and the British Standards which have caused confusion so far. so important because they give us a and activities’.
the standards but to add insight, clarity series. It should be read by anyone within
Institution (BSI) have collaborated to provide platform from which to do this. 6.0 ‘Information management
The UK BIM Framework replaces the term and tips for practical implementation. the industry, to gain a general understanding
one joined-up approach and one unified process summary’.
‘BIM Level 2’. It is no longer to be used – It’s therefore helpful to read the guidance of the standards and the wider digital
message across industry. As a result, the Information is the one true asset
the reason being that it was stated as the and the standards side by side. transformation of the built environment. 7.0 ‘Summary’.
UK BIM Framework (ukbimframework.org) to rule them all
was launched in October 2019. information requirement on many projects.
On its own, BIM Level 2 is a vague reference: The UK BIM Framework replaces the
The UK BIM Framework should be the it doesn’t specify precisely what information bim-level2.org website and consolidates
first stop for anyone who is responsible is required, when it is required or which the knowledge resources in one place.
for specifying, delivering or managing party should generate it. This includes:
information throughout an asset’s life • Links to all the standards which make up
(which includes the design and construction Let’s put this into context. We understand
the UK BIM Framework.
activities). This applies to those of you how to specify the performance outcomes
who are familiar with the 1192 standards, required for physical assets like a door, • Guidance for those transitioning from
and those of you who may be new brick or even an entire building. the superseded 1192 standards to the
to the subject.
However, when it comes to the associated
ISO 19650 series. The UK BIM Framework replaces the term ‘BIM Level 2’.
The UK BIM Framework website sets out information, this is an asset in its own right
• Soft landings information.
It is no longer to be used – the reason being that it was stated
the concept of the information landscape,
as well as providing links to all the relevant
too, and should be specified with similar
attention to detail.
• The ISO 19650 guidance.
as the information requirement on many projects.
standards and freely available guidance. On its own, BIM Level 2 is a vague reference.

6 National BIM Report 2020 The definitive industry update 7


In addition, there are some key messages The guidance is an evolving resource.
which are addressed through the standards It is updated every quarter, with more
and guidance, as follows: sections being included. In the future,
additional guidance will be released to
• Information management activities
support the publication of new standards.
are, in the main, appointment-based,
not project work stage-based. There are also plans to make the guidance
• The client has a significant (and much more interactive and connected,
arguably the most important) role so that it is easier to navigate.
to play within the information
management ecosystem. I started my digital transformation journey
a decade ago. I remember spending hours
• Understanding and defining the scrutinizing standards and publications –
purpose for each piece of information only to find that they would contradict
is fundamental to determining each other.
Sarah Davidson,
information requirements.
Associate Professor
We don’t want you to be subject to the
University of Nottingham • Exchange information requirements
same experience, and hope that, through
(guidance co-editor) (EIRs) are a means of specifying what
the guidance, you have a useful and
information is required, and are one of
reliable point of reference.
‘Progression of the ISO 19650 the resources used to aid the selection
guidance is wholly reliant upon a of delivery teams. They are appointment- The guidance is available to everyone.
dynamic collaborative team and specific, so there can be many EIRs It’s jam-packed with useful information,
feedback from industry. Guidance across one project. and above all it’s free. All feedback is
co-editors Dr Anne Kemp, David • The common data environment (CDE) welcomed and encouraged. If you have ideas
Churcher and I are incredibly grateful is a combination of technical solutions for content, or you want to contribute, please
to the individuals who have been underpinned by workflows. The workflows complete the feedback form on the UK BIM
involved and to their organizations should be planned first, and the solutions Framework website. We want to make this
for supporting them. They have been selected to facilitate them. guidance the best that it can be, and we all
sharing their knowledge and expertise need to work together to achieve it.
• The outputs of the information
and volunteering their time in the
activities are resources and not To download/ view the guidance, go to
creation of the guidance thus far.
separate, unconnected documents. ukbimframework.org/standards-guidance
We are looking forward to its ongoing
development as more insight is The message is very much about
gained, more feedback is shared managing information like we’ve done Emma is a digital information specialist
and more standards within the previously, whilst recognizing that we at Bond Bryan Digital. She is also part
ISO 19650 series are released. It is need to use structured information of the BSI committee that develops the
also great to see the UK BIM Alliance, where possible to enable technology standards for digital construction, an
CDBB and BSI working in partnership to understand it. This means being more author of the ISO 19650 guidance, an
to facilitate the development of the systematic and precise in our approach, ambassador for the UK BIM Alliance
UK BIM Framework’. and understanding that information and on the buildingSMART UK &
needs to be broken down in different Ireland committee.
ways around a consistent framework.

The guidance is an evolving resource.


It is updated every quarter, with more sections being included.
In the future, additional guidance will be released
to support the publication of new standards.

8 National BIM Report 2020 The definitive industry update 9


RIBA Plan of Work 2020
Dale Sinclair
and specification
Director of Technical
Practice, AECOM The specification is the backbone of any project. Products must be researched,
selected and agreed with the client, with finishes and facades requiring careful consideration
and discussions with clients, planners and other stakeholders.

The specification drives the look and feel construction; with the latter, the design To phrase this another way, the decision
of a project, and heavily influences its team will issue the information used to use a prescriptive or descriptive
cost plan. New design review tools such on-site for construction. For descriptive specification is driven less by procurement
as virtual reality (VR) place even more specifications, design responsibility and more by topics such as the value
importance on illustrating the right lies with the contractor, although this proposition. The descriptive-to-prescriptive
products at the right time. responsibility is likely to be passed journey on any project will vary. Some
on to a specialist subcontractor carrying clients may have a range of products used
With this in mind, the RIBA Plan of Work professional indemnity insurance. throughout their portfolio of projects,
2020 (reproduced overleaf and highlighting On a design and build contract, design which might be included in the project
the requirements for exchanging responsibility rests with the contractor, brief. Other clients may wish the design
specification information) places emphasis regardless of who designs: whether the team to specify anything that is visually
on the role of the specification during the design team or a specialist subcontractor. important, allowing the contractor to
design and construction stages. The outline select concealed products. There is no right
specification is a crucial design tool during A common misconception is that or wrong decision; however, it’s essential to
stages 2 and 3, allowing specification procurement drives this decision-making. recognize that the decision must be made
decisions to be captured in a document This is not correct: specifications can be at the outset of the project. This allows
that can be shared with and agreed on by all. prescriptive or descriptive, regardless of the appointment documents and the building
procurement route. Traditional contracts contract to be prepared accordingly, and
A key inclusion in the RIBA Plan of Work have had the ability to facilitate descriptive procurement discussions to be framed
2020 is the acknowledgement that the specifications, via the contractor design appropriately. The RIBA Plan of Work 2020
stage 4 information from the design team portion (CDP), for years. Similarly, prescriptive has, however, been designed in a manner
needs to be geared to manufacturing or specifications can be used where a planning that helps ensure that the complexity
construction for each building system, consent has stringent conditions relating of this crucial project interface is clear
with this information being descriptive or to materials, or where the client wishes to from the outset.
prescriptive, depending on the approach. ensure that specific design aspects will be
With the former, a specialist subcontractor provided as imagined by the design team,
will pick up the design baton, completing meaning that they are commonplace on
the information for manufacturing and/or design and build contracts.

The specification drives the look and feel of a project,


and heavily influences its cost plan.

10 National BIM Report 2020 The definitive industry update 11


Above and right: RIBA Plan of Work 2020 The RIBA Plan of Work The RIBA Plan of Work
Template, reproduced courtesy of the Royal organises the process of
briefing, designing, delivering, 0 1
organises the process of
briefing, designing, delivering, 02 1 3 24 35 46 57 6 7
Institute of British Architects. RIBA maintaining, operating and
using a building into eight
maintaining, operating and
using a building into eight
The RIBA Plan of Work
Plan of Work 2020
01 12 23 34 45 56 67Use 7
The RIBA PlanThe RIBA Plan of ItWork
0 1 2 3 4 5 6
of Work stages. is a framework for stages. It is a framework for

0
organises organises
process of process of
the
Overview organises the process ofthe
all disciplines on construction
Strategic
all disciplines on construction
Preparation Strategic
Concept Preparation
Spatial Concept
Technical Spatial
Manufacturing Technical Manufacturing
RIBA briefing,
briefing, designing,
RIBA
briefing,
projects
designing,
delivering,
and designing,
should
delivering, be delivering, projects and should be
used solely as guidance for Definition usedand Briefing
solely as guidance for Definition
Design and Briefing
Coordination Design Design Coordination
and ConstructionDesign Handover andUseConstruction Handover
Plan of Work maintaining,
maintaining, operating Plan of Work
maintaining,
andtheoperating
preparationand
using
operating
of detailed
and the preparation of detailed
using
using a building into aeight
building intoaeight
2020 stages. It is a framework for 2020
professional building
services andinto eight professional services and
stages.
building It is a framework for
contracts. building contracts. Projects span from Stage 1 to Stage 6; the outcome of Stage
Projects
0 may
span
be from
the decision
Stage 1to
toinitiate
Stage 6;a project
the outcome
and Stage
of Stage
7 covers
0 may
the be
ongoing
the decision
use of the
to initiate
building.
a project and Stage 7 covers the ongoing use of the building.
stages. It is a framework for
all construction
disciplines on construction
all construction
disciplines on
Strategic Preparation Concept Spatial constructionAllTechnical BuildingManufacturing
RIBA RIBA RIBA Strategic Preparation Concept Spatial Technical
allStage
disciplines on
Boundaries: StageTheBoundaries: handed over,Manufacturing
projects
Stages 0-4 and projects
will should
generally
Stage Strategic
Outcome
projects
beandatshould beand should be
Stages
the0-4
best means
generally Preparation
of achievingStage
willRequirements
Outcome
Project Brief approved by the
The best
Concept
Architectural Concept
means of achieving Project Brief
Spatial
Architectural
approved
and by the Architectural
engineering All design Concept
and Technical
information Architectural
Manufacturing,
and engineering
Manufacturing
design
Building information Manufacturing, used,
construction
operated andBuilding handed over, Building used, operated and

for one Definition accommodated onand Briefing Design Coordination Design and Construction Handover
Client at theclient and stage that it the Client
theconfirmed Requirements
approved by the client and client information Spatially
and confirmed that it approved
required
by the toclient
manufacture and Commissioning
information Spatially Aftercare
required to manufacture
initiated and and Commissioning
maintained efficiently Aftercare initiated and maintained efficiently
Definition can be and Briefing Design Coordination completedDesign and and Construction Handover Use
the end of the stage end of
asused solelyforas guidance
WorkofPlan
Workof Work Definition and Briefing Design Coordination Design and Construction Handover Use
used
after solely guidance
Plan ofPlan
be undertaken
used solely asoneguidance for be undertaken
confirmed after confirmedaligned to the Project Brief can beCoordinated
accommodated on aligned to the Project
and construct theBrief
project Coordinated Building
constructContract
the projectconcluded
completed Building Contract concluded
detailed the ofpreparation
detailed of detailed
the other. the other. the site the site completed completed
the preparationthe ofpreparation If the outcome determines that The brief
If the outcome remains “live”
determines thatduring The brief remains “live” during

2020 professional
and services aand
Stages 4 and 5 will overlap Stages 4 and 5 will overlap

2020 2020
Stage 7 starts concurrently with Stage 7 starts concurrently with
professional professional
services
in the Project Programme and services
building is the best means of
Project the
in theachieving Programme
Client Requirements,
Stage 2 and is derogated
a building is the best means of
achievingresponse to the
the Client
in
Architectural
Requirements,
Stage 2 and
Stage
response
is derogated
4 will
to the
in
overlap with Stage 5
Architectural
There is no design work in Stage 5
other than responding to Site Stage 4 will overlap with Stage 5
There is no
Stage
other than
design work in Stage 5
6 and laststo Site
responding for the life of the Stage 6 and lasts for the life of the
building building
contracts. contracts. proceeds to Stage 1 Projects span from Stage 1 toConcept
Concept Stageon most 6; the
projects outcome of Stage
Queries 0 may be the decision
on most projectsto initiate a project Queries and
building Stage 7 covers the ongoing use of the building.
building
Projects span Projects span from Stage 1 to outcome
Stage 6; the outcome ofbe Stage 0 may betothe decision to initiate a project and Stage 7 covers theofongoing use of the building.
the client proceeds to Stage 1 the client
building contracts.
for most projects. for most projects.
from Stage 1 to Stage 6; the of Stage 0 may the decision initiate a project and Stage 7 covers the ongoing use the building.
Stage 5 commences Stage 5 commences
Stagewhen
Boundaries:
Stage Boundaries:
Stage Boundaries:
the contractor takes
of theStage
Core Tasks
Stage Outcome
whenPrepare Client Requirements
the contractor takes
The best
CorePrepare
means
TasksProject Brief
ofstage
achieving
Prepare
Project
ClientArchitectural
Prepare
Brief
Requirements Prepare
approved
Project Brief
Undertake
byincluding
Design Studies, Prepare
Architectural
theEngineering Concept
Architectural
Develop
Architectural
Finalise
architectural and Undertake
and
Site Logistics
Design Studies,
engineering
Handarchitectural
Develop
AllPlan
over buildingand
design
in line with
Useinformation
Finalise Site Logistics
Implement Facilities
Manufacturing,
Hand over building in line with Implement Facilities
construction Building handed over,
Stage Outcome
possession site Outcome
during The
the best
stage The
means best
ofDevelopofmeans
achieving
possession the site
Business of achieving
Project
Case Brief
for during Project
including
theapproved Brief approved
Project Outcomes
by the Concept
Architectural
Develop Business Architectural
by incorporating
the
CaseConcept
for Concept
Project Outcomes
Analysis and
Architectural Architectural
Concept
and engineering
engineering and
incorporating
technical engineering
Engineering
design
All design AllBuilding
information
Manufacture design
Analysis and information for technical
engineering Strategy
Manufacturing, Manufacturing,
design
constructionManagementconstruction
and
Building
Manufacture Building
Plan
handedBuilding
forover, handed
Use Strategy over,Management
Building Building ua
used,and
operated
Stages 0-4 willStages Stages
0-4 will
generally generally0-4
and will at
finishes generally
Practical
at thetheend Client of the and
stage
Requirements Clientatoptions
thefinishes the
Requirements
Practical Client
client Requirements
and Sustainability Outcomes,
andQuality
confirmedclient and it client
confirmed
thatand and
thatconfirmed
Strategic
approved itEngineering thatand
approved itand Cost approved
Sustainability
by Exercises
the client andby theSpatially
Outcomes,
to test client
Strategic and
Engineering information
information Spatially Cost Spatially
Exercises to test
required required
to manufacture toreview
manufacture
Commissioning Systems andand
Asset Management
and Commissioning Commissioning
Aftercare Aftercarereview initiated Aftercare
and initiated
Asset Management and
maintaine
requirementsby andthe client information requirements and aligned torequired to manufacture and initiated and maintained efficiently
at the end of the stage feasible including feasible options including Prepare and coordinate Systems and construct Undertake
Prepare and coordinate of Project construct Undertake of Project
at the endone
Completion. of the stage Completion. Aspirations aligned toQuality Aspirations
Architectural Concept
and Architectural Concept
be undertakenbe one after beone
undertaken undertaken
after
Stage 6 starts with
after
the confirmed Stage
review of Project
confirmed 6 starts with
confirmed
the
Risks and
can be Spatialcan
accommodated be accommodated
Requirements on can
review be ofaccommodated
Project
aligned to
Risks and
on Project
Cost Plan, the on
aligned to
Project
Strategies Brief
Spatial the aligned to
Project Brief
inCoordinated
Requirements
resulting Spatially
the Project
Cost
Briefteam Building
design
Coordinated Coordinated
Plan, Project Strategies and
building and constructdesign
construct
resulting the
in Spatially project and
the construct
Performance
team
project
completed
Buildingthecompleted
project building
Undertake completed
Post OccupancyPerformance
Building Contract Building
concluded Contract Building Contract
Undertake
concluded concluded
Post Occupancy

the other. the other. the other. Project Budget


tothe theFeasibility
site Studies
Project Budget
the site
and Outline Specification
Systems information
Coordinated design alignedand Outline Specification completed Monitor design
Coordinated completed
progress against
aligned
Systems information
completed
Undertake seasonal
Evaluation of building
Monitor progress against Undertake seasonal
Evaluation of building
handover of the building to handover of the building
If the outcome
Ratify If the
optiondetermines
that best
site determines
outcome
that Undertake that The briefUndertake
remains The brief
Feasibility
“live” duringremains “live” during
Studies
Construction Programme Commissioning
performance in use
Construction Programme Commissioning
performance in use
Stages 4 client
the and immediately
5 will overlap after If the outcome determines the client that
immediately afterdelivers Ratify The
option thatremains
brief best delivers
“live” during to updated Cost Plan, Project Prepare and integrate to updated Cost Plan, Project Prepare and integrate
Stages 4 and 5Stages 4 and 5
will overlap will overlap
Practical Completion and a building
Project Strategies mightisinclude:
the best a building
Client
means
Practical is the
Requirements
of
Completion
a
best building
means
and
is
of the best
Agree
Project
means
Project
Strategies
ofBudget
might include:
Agree Project Brief Stage 2 and is derogated
ClientStage 2
Requirements and is derogated Agree
Stage 2
Project Budget
in Strategies inand
and Outline
is derogated
Agree in
Project Brief
specialist subcontractor Strategies and Outline
Inspect Construction Quality There
specialist
Rectify
There
is no design work in
subcontractor
defects
is no design
Stage 5
There
work
Verify Project Outcomes
Inspect Construction
inis no
Quality
design
Stage 5 work
Rectify
in Stage 5
defects
Stage 7 starts
Verify Project Stage 7 star
concurrently
Outcomes with
in the Project Programme in the Project
in the Project Programme Programme achieving Client
theend achieving the–Client
Requirements, Requirements, Derogations response to the
the Architectural response
Architectural to the Architectural
Derogations
Stage 4 will overlapStage 4 will overlap
with Stage Stage
with
5 Building other4 will
Stage overlap
than5 respondingwith Stage
other 5
thanincluding
to Site responding other than
to Site responding to Site Stage 6 andSustainability
lasts for Stage 6 and
the life of
Reviewresponse
Feedbacktofrom
finishes at the end of the achieving
– Conservation the Client
(if applicable) Requirements,
finishes at the ofthe
the Conservation (if applicable) Specification Building Systems Specification Systems Sustainability including
Review Feedback from
client proceeds Sourceto Site Information
Stage 1 Concept Source Site Concept
Information on most projects on most projects Queries Queries building
for most
for most projects. for most
projects. projects.
Defects Liability Period.


Cost
Fire
the
Safety
client proceeds theto
Defects client
Stage
previous
proceeds
1
Liability Period.
projects
to Stage 1 –

Cost
including
Fire Safety Site Surveys previous
Concept
Undertake
projects
Design Reviews
including Site Surveys
Initiate Change Control
Undertake Design Reviews on most Resolve
information projectsSite Queries as information
Initiate Change Control
Queriesinitial Aftercare Resolve
Complete Site Queries as
Outcomes Complete initial Aftercare building Outcomes
– Health and Safety – Health and Safety with client and Project with client and Project required tasks including light touch required tasks including light touch
RIBA Stage 5 commences
Stage 5 commences Stage Stage 7 starts concurrently
5 commences – Inclusive Design
Stage 7 starts concurrently
Undertake Site Appraisals – Inclusive Prepare DesignProject Programme Undertake Site Appraisals
Stakeholders Prepare Procedures
Project Programme
Prepare stage Design
Stakeholders
Procedures Prepare stage Design
Post Occupancy Evaluation Post Occupancy Evaluation
Plan of Work www.ribaplanofwork.com
when the
when the contractor whenCore
contractor
takes
with Stage 6 and lasts for
the
takescontractor
the life Tasks
of Core
the building.takesTasks Core
– Plan forPrepare
– Planning
Use
Tasks with Stage 6 and lasts
Prepare
Clientthe lifeRequirements ClientPrepare for
Requirements
of the building. Prepare
Client Requirements
Project
– Planning
– Plan
Prepare Project
BriefExecution
for Use Project
Prepare
Prepare
Brief
Prepare Project
Prepare stage
Brief
Prepare
Architectural
Design Prepare PreparePrepare
Architectural
Project
Architectural
Undertake
stage Design
Execution Design
ProgrammeDesign
Undertake
Studies,
Prepare stage Design
Undertake
Studies,
Develop
PrepareDesign
ofarchitectural
Commissioning Programme
UndertakeStudies,
Develop
stage Design
building and Develop
architectural Finalise andarchitectural Finalise
Site Logistics
Undertake Commissioning
and Site Logistics
of building Hand Site
Finalise overLogistics Handinover
building line with Hand
building inover
Implement building
line with Facilities in line wi
Implemen
ofpossession of the site during the stage including Project including
Outcomes including
Project OutcomesConcept Project Outcomes
Concept
incorporating Concept
Planincorporating
Programme incorporating
Engineering Engineering
Analysis and Engineering
Analysis Programme
engineering Analysis
andPreparetechnical and
engineering design engineering
technical design technical design Plan for Use Plan for Use Strategy
Strategy Plan for Use Strategy
Management Managem
and
possession of possession the site – Procurement – Procurement
the site during the stage during the stage
– Develop Business Case for
Sustainability Develop Business Develop Case Business
for

Plan Case
Sustainability for Programme Programme Building Manual Manufacture Building Manufacture
Prepare Manufacture
Building
Building Manual Building
finishes atand finishes
Practical at Practical Sustainability Planand Sustainability
Outcomes, and Sustainability
Outcomes,
Strategic Outcomes,
Strategic
Engineering Strategic
Engineering Engineering Cost Exercises Cost Exercises to test
todesigns
test Asset Man
and finishes atandPractical Planning Note: See RIBA Plan of Work 2020 Planning
Overviewfeasible options feasible No design
including Note:
options feasible
team required and
including
for options
Stages See
0 andRIBA including
1. Client of Work
advisers 2020
may be appointedNo design team required for Stages 0 and 1. Client advisers mayCost Exercises
be appointed toSpecialist
test subcontractor
Prepare and Prepare and coordinate
coordinate Prepare
Specialist andand
subcontractor
Systems coordinate
Systems
designs
construct and
AdaptationSystems
construct
of a building (at
Undertake and
the construct
reviewUndertake
ofoutProject review Asset Management
Undertake
of Project review
Adaptation of Project
of a building (at the

Completion. Completion. Completion.


for detailed guidance to the client team to provide strategicOverview
Quality advice and
Aspirations Quality
fordesign
detailed guidance
thinking
and Quality
Aspirations to the client Aspirations
before Stage
and and
team to provide strategic
requirements and advice and designrequirements
requirements
aligned to thinking before Stage and aligned
and aligned
Architectural to Architectural
are prepared
Concept Architectural
to and reviewed
Concept during Concept
Building are 5prepared
handover tasks bridge Stages and 6 asand
setreviewed
out in theduring
Plan end
for Use Building of its useful
handover life)
tasks triggers
bridge a new
Stages 5 and 6 as set in the Plan for Use end of its useful life) triggers a new
Planning Applications
review
on Project Strategies
of Project
Planning
reviewRisks
2 Applications
of Project
and
commences. reviewRisks ofandProject Risks and
on Project Strategies 2 commences. Stage 4
design Strategy design team Building
team Building design
Stage
building
4 team Building building Stage 0 building
Strategy
Performance Performance Performance
Undertake
Stage 0
Post Undertake
Occupan
Spatial Requirements Costresulting
Plan, Project Strategies resulting in Spatially
Budget Spatial Requirements CostStrategies
Plan, Project Strategies resulting in Spatially
are generally submitted are generally submitted Spatial Requirements Cost Plan, Project in Spatially
Stage 6 startsStage 6 startsStage
with the6 starts with the Project BudgetatProject Stage Project
Budget Systems Systems information Evaluation
with the
handover handover
at the end of Stage 3 and
oftoonly
thebebuilding
submittedto Core Statutory
the end of
Strategic appraisal of
3 and
CoreSource Statutory
pre-application Strategic Obtain
and appraisal
pre-application
Outline Outline
andStudies
of Specification Source and Outline
Specification
pre-application
Review design againstSpecification
Coordinated Coordinated
ObtainSubmit
design Buildingdesign
pre-application
aligned
Systems
Coordinated
aligned
Regulations Review information
design
Carry alignedinformation
Construction
out against
design Submit Monitor
Comply withprogress
Building Regulations
Planning Monitor
against
Carry progress Monitor
out Construction
Comply with against
Undertake
Planning progress Complyagainst
Undertake
seasonal with Planning seasonal Evaluation
Undertake Comply ofPlanning
seasonal
with building
handover of the buildingof tothe building
should should only be submitted
Ratify Undertake
option that Undertake
Feasibility
best Studies
delivers
Undertake
Feasibility Feasibility
Studies Prepare and integrate Construction
as required Programme performance
as required Commissioning Conditions asin performan
use
the clientafter the clientafter
immediately immediately after
earlier when the threshold Processes Ratify option Ratify
that
earlier Planning
best option
when considerations
delivers
the that
threshold best delivers Planning Advice
Processes PlanningPlanning Advice
considerations Planning Advice
Building Regulations
to updated to Application
Planning Advice
updated
Cost Plan, Project Cost to updated
Plan, Project
Prepare Cost
Phase
Building
and Plan,
Plan
Regulations
Prepare
integrate Project and Application
Conditions
integrateConstruction as required
Programme Phase
Construction Conditions
Plan Programme
Commissioning Conditions
Commissioning required
the client immediately Agree Project Project
Agree Initiate
Brief Agree
Brief Project Brief
Practicaland Practical
Completion
of information required
Completion
and
hasStrategies
andinclude:
Project during the stage:
Project Strategies
Client Requirements
might include: of
might information
Client include: required
Requirements Clienthas Requirements
during
Agree Project Initiate Agree
the stage:
Budget of health Agree
collation Project Budget Project
Agree route Budget
to Building Prepare
collationandof submit
health
Strategies and Agree Discharge
route
Strategies
Outline to Building
pre- Strategies
and Outline Prepare
specialist and
Comply
andOutline
specialist
with
submit
subcontractor Planning specialist
subcontractor
Discharge pre- subcontractor Comply with Planning
Verify Project Outcomes Verify Proj
Practical Completion Project
been met.Strategies might
If a Planning been met. If a Planning and safety Pre-construction Derogations Regulations compliance Derogationsand safety Derogations
Pre-construction
Planning Application Regulations compliancePlanning Planning Application
commencement Conditions related to InspectSystems
commencement Construction
Planning Inspect Construction
Quality
Conditions Inspect
relatedRectify Construction
to Quality defects Rectify Quality
defectsRectify defects
at thefinishes at the end of–the
Conservation – Conservation (if applicable)
(if applicable) Specification Specification Specification
Buildingconstruction
Systems Building Systems Building including Sustainability including S
finishes at the finishes
end of the end of–Application
the
Conservation (if applicable)
is made Planning
Review Feedback Application
Review is madeReview
Feedback from Feedback
Planning from
InformationSource
Site Information Site Source
Information Site Information Information Conditions Conditions construction
Defects Defects
Liability –during
Period.Cost
Liability
Stage 3,Period. – Cost
a mid- – Cost
Building Regulations duringfrom Stage 3, a mid- Source Building Regulations
Option: submit outline
Undertake DesignUndertake
Reviews DesignUndertakeReviews Design Option: submit outline
Reviews information information Prepare information
Resolve Site QueriesResolve asSite Queries Resolve
Complete asSite initial
QueriesCompleteas initialComplete
Aftercare Aftercare
Outcomes initial Aftercare
Outcomes
Defects Liability Period. – Fire
be Safety Health – Fire Safety projects
previous previous projects previous
be including projects Site including
and Surveys
including
(CDM)Site Surveys
Planning Site Surveys
Application Initiate Change Initiate
Planning
Prepare
Control Change Initiate
Construction
Application Control Change Control Construction
–stage
Fire gateway
Safety should

and
Health
Safety (CDM) stage
and Safety
gateway should Health Safety
with client and with
Projectclient and with
Project client and Project required required required
tasks including tasks
light includingtasks
touch including light touch
light touch
Stage 7 starts Stage
concurrently Stage 7
7 starts concurrentlystarts concurrently
– Health and Safety
determined and it – Health
should and Safety determined and it should Phase Plan
Note for guidance on Procedures
See PlanningProcedures Procedures
Prepare stage Prepare
for guidancestage
Design Prepare stage Design
Phase Plan
Design
–beInclusive
clear team Design– Inclusive
– Inclusive Undertake DesignSite Undertake
Appraisals SiteUndertake
Appraisals
Prepare Site Appraisals
Project Prepare
Programme Project Prepare
Programme Project Programme
Stakeholders Stakeholders Stakeholders See Planning Note on
Post Occupancy Post Occupancy
Evaluation Post Occupancy Evaluation
Evaluation
with Stage 6 andwithlasts
Stage withlasts
for6 and Stage 6toand
fortasks the project
Design
lasts for
– Planning – Planning
be clear to the project team submitting a Planning Application Submit form F10 to HSE if submitting a Planning Application
earlier than at endProgramme
Programme Programme
Submit form F10 to HSE
Undertake ifUndertake Commissioning
Commissioning Undertake Commissioning
In some instances, descriptive Another important stage 4 decisionthe life of the building. –which
Planning
the life–will
of the
and deliverables which tasks and deliverables earlier than at end of Stage 3
Prepare stage Prepare
Design
applicable Prepare
stage Design stage Design of Stage 3
applicable
the life of the building. be
Plan forbuilding.
Use – Plan for Use – Plan for Use
required. will be required. Prepare Project Prepare
Execution Project Prepare
Execution
Prepare Project stage Execution
Prepare stage Prepare
Design Design stage Design of building of building of building
specifications are used to clearly assign is the point at which stage 4 information –See Overview guidance
Procurement – Procurement
. – Procurement
Procurement See Overview guidance.
Plan Procurement Plan Traditional PlanProgramme Programme Programme Programme ProgrammeTenderProgramme Appoint Appoint
– Sustainability – Sustainability Route – Sustainability Traditional
Route
contractor Tender contractor
Prepare Building Prepare
Manual Building Prepare
Manual Building Manual
design responsibility to the contractor – is produced. Design and build procurement Planning Note: Planning Note:
Planning Note: See RIBA
Procurement: See RIBA
Plan of Work See
2020Plan of Work RIBA
2020
No
Design
Overview
&Plan
Buildof
design 1Work
team 2020
No design
Procurement:
required
Stage for Stages Noand
0 design
team required 1.for team
Stages
Client required
0 andmay
advisers
Design 1.for Stages
&Client
be
Build 0 andmay
1advisers
appointed
Stage 1. Client advisers may be appointed
be appointed Appoint
ER CP contractor Specialist subcontractor Specialist subcontractor
designs
Appoint
ER Specialist subcontractor designs
designs
CP contractor Adaptation of a building Adaptation
(at the
specifying the fire, acoustic and durability may draw down stage 4Planning
information for Applications Overview Overview
for detailed for detailed
guidance to thefor
guidance detailed
client teamTheguidance
to provide
to the client team toadvice
strategic the client
provideand team
strategic
designtoadvice
provideand
thinking strategic
design
before advice
thinking
Stage and design
before thinking before Stage
Stage are prepared and reviewed are prepared during are Building
prepared
and reviewed during and reviewed
handover during
Building
tasks handover
bridge Stages Building
tasks 6handover
5 andbridge outtasks
Stages
as set in5 the
andbridge Stages
6 asfor
Plan set out in5 the
Use andPlan
6 asof
end set
for out
itsUse
useful life)Plan
in the end foritsUse
of
triggers ausn
Planning
Applications PlanningThe Applications
on
RIBA Plan of Work
Project Strategies on Project on
Strategies Project Strategies
2 commences. 2 RIBA
commences.Plan
Appoint of Work
2 commences. Appoint Appoint Appoint Appoint Stageagreement
Stage 4 Pre-contract services 4 Stage 4
Appoint
CPStrategy
Appoint Facilities
Strategy
Management
Strategy and Asset Management teams, and Stage
Appoint Facilities
and0Asset Management
Management
Stage 0 and
is procurement neutral – Design & Build 2 Stage is procurement
client team neutral – Design & Build 2 Stage ER Pre-contract design
servicesteam
agreement CP contractor ER contractor teams,
criteria for partitions, for example. However, inclusion in the employer’s requirements,
are generally are generally
are generally submitted
submitted submitted
See Overview guidance for See Overview guidance for
design team
client team
strategic advisers as needed strategic advisers as needed

at the3end of Stage 3 and Management Contract Management Contract Appoint Appoint


the design team might specify products with residual stage 4 information at the3end
at the end of being
Stage andof Stage a and
detailed description of a detailed description of
should
should only be submitted only be should Core
submittedonly
how eachStatutory
be Core
submitted
stage might be Statutory Core
ConstructionStatutory
StrategicManagement Strategic
appraisal
how eachof stage Strategic
appraisal
might be of appraisal
Source Constructionof Management
Source
pre-application Source
pre-application pre-application
Obtain
contractor
Obtain
pre-application Obtain
pre-application Reviewpre-application against design Review
design Review
contractor
against
Submitdesign against
Building Submit
RegulationsBuilding CarryBuilding
Submit
Regulations Regulations
Carry out Construction
out Construction CarryComplyout Construction Comply with Planning
with Planning Comply
Comply withwithPlanning Comply w
Planning
agnostically, taking design responsibility completed by the contractor’s design Processes Processes
Planning Planning
considerations Planning
considerations considerations
Planning Advice Contractor-led Planning Advice
Planning Advice Planning Advice Planning Advice Planning
PreferredAdvice
Building ER Building
Regulations
Appoint
Building
Regulations Regulations
Application Application Application
Appoint
Phase Plan Phase Plan Phase Plan as required
Conditions Conditions as requiredConditions
Conditions as required
as Condition
required
earlier when
earlier when the threshold earlier
the Processes
adjusted to accommodate
when
threshold the threshold
the requirements of the
Contractor-led adjusted to accommodate
the requirements of the
ER bidder CP contractor Preferred bidder CP contractor

but allowing the contractor to propose a team or the novated design team. of information
of information required has of information
required has required
during the stage:
Procurement during
Strategy. hasthe stage:during
Information the stage: Client RequirementsInitiate
Procurement Strategy. ProjectInitiate
collation
Information of health
Brief Initiate
collationClient of Agreecollation
health
Project route
Requirements
Brief of health
to Agree
Building
Derogations Project Agree
to Building
routeSigned
Brief route
off Prepare
Stage Report to Building
Prepare
andProject
submit and submit
Brief Derogations
Manufacturing Prepare and
Discharge
Information submit
offpre-
Building
Signed StageDischarge
ManualReportincluding pre- Discharge pre-
ComplyonInformation
Feedback
Manufacturing with Comply
Planning
Project with
Feedback
Building Comply
Planning
Manual from Post
includingwith Planning
Feedback on Project Feedback from Post
supplier for certain products. For example, This interface needs to bebeen met. If a been
considered met. If a been
Planning If a Planning
met.Employer’
Planning s Exchanges Employer’
Business Cases and safetyExchanges
Pre-construction
Feasibility and
safety Pre-construction
andStudies Businesssafety Pre-construction
Regulations
Case
Signed off Regulations
Stagecompliance
Report Feasibility Regulations
compliance
Project
Studies compliance
Planning Application
Strategies Planning Application
SignedConstruction
off Stage Report Planning Application
Health and
commencement
Information Project Strategies commencement
Safety File and commencement
Planning Planning
Performance
Conditions
Construction Planning
Conditions
related
Information toHealth Conditions
related
Occupancy
and Safety to and related
Evaluation
File to
Performance Occupancy Evaluation
ER ER Fire Safety Information Fire Safety Information
Application is Application
made Application
is madePlanning is made
Requirements Planning at the Planning
end of the stage Requirements at the end ofInformation
Information the stage Information Conditions Conditions Conditions
Final Certificate
construction construction Updatedconstruction
Building Manual Final Certificate Updated Building Manual
the architect may specify a certain type carefully at stage 1. The during
clientStage
must a mid-Stage 3,during
3,during a mid- Stage 3, a mid-
Site Information Project Strategies
Option: submitOption: Site
outline submit Option:
Updated outlinesubmit outline
Information Outline Project
Final
Strategies
Specifications Updated Outline
Practical Completion
Final Specifications
Practical Completion
including Health and including Health and
Building Regulations
Contractor’ Building Regulations
s Building Regulations Contractor’s Specification Specification Feedback from light touch Feedback from light touch
of brick that is referenced in the planning decide whether the information issued
stage gateway stage
should be stage
gateway should
CP
gateway
be andshould
Proposals be
CP
Proposals Project Budget Planning Planning
Outline Specification
Application Planning
Application
Project Budget Application Outline Specification
Residual Project Strategies
Prepare Construction
certificate including Construction
Prepare Prepare
Residual Construction
Project Strategies Safetyincluding
certificate File and Fire Safety Safety File and Fire Safety
Health Health
Safety and Safety
(CDM) Health and Safety (CDM)
(CDM) Updated Cost Plan Updated Cost Plan
Defects List
Post Occupancy Evaluation
Information
Defects List as necessary
Post Occupancy Evaluation
Information as necessary
determined determined
and it should and determined
it should and it should Project Programme Cost Plan Project Programme Building Regulations Phase Plan
Cost Plan Phase Plan Building Phase Plan
Regulations
consent whilst allowing the contractor by the design team will be descriptive See Planning Note for
Planning Application See Planning
guidance on
Application Note See
for Planning
guidance Note
on
Planning
Asset for guidance
Application
Information on Application Asset Information
be clear to thebeproject to thebe
clearteam clear team
project to the project team Procurement Strategy Procurement Strategy
submitting a Planning submitting a Planning
Application submitting a Planning
Application
Submit form F10 Application
Submit to HSE form if F10 Submit
to HSE formif F10 to HSE if
to select walls ties and lintels, or specify or prescriptive, and whether this which
which tasks and tasks and
deliverables which tasks and deliverables
deliverables Responsibility Matrix Responsibility Matrixearlier than at end of earlier
Stage 3 at end earlier
than of Stage than
3 at Ifend of Stage
Verified 3
Construction If Verified Construction
applicable is required, verification applicable
Informationapplicable Information is required, verification
a specific partition build-up, allowing information will be produced before will be required.
will be required. will be required. Information Requirements Information Requirements tasks must be defined tasks must be defined

the contractor to propose an alternative. See Overview


or after the building contract is signed. See Overview
guidance . See Overview
guidance .
Procurement guidance .
Procurement CoreProcurementof Work terms areTraditional
Appoint
Tender
Appoint
are includedTender
Appoint
Traditional Traditional
RIBA Plan defined in the RIBA Plan of Work 2020 Overview
Core RIBA Plan
glossary
of Workandterms Bold
set inare Type. in the RIBA Plan of Work 2020 Overview Further
defined glossaryguidance Bold
and set inand Type. stage descriptions are included in the RIBA
detailed Plan of
Further Work Tender
guidance 2020 Overview.
and detailed stage descriptions
contractor contractor in the RIBA Plan of Work 2020 Overview. © RIBA 2020
contractor © RIBA 20
Route Route Route
Appoint Appoint Appoint
For some aspects, a descriptive specification Finally, during stage 5 and construction,
Procurement: Procurement: Procurement: 1 Stage& BuildDesign
Design & BuildDesign 1 Stage& Build 1 Stage ER CP ER CP
contractor ER CP
contractor contractor
can be the key to unlocking design innovation. the final specifications continue to be
The RIBA
The RIBA Plan of Work Plan The
of RIBA
Work Plan of Work Appoint Appoint Appoint Appoint Appoint Appoint Appoint Appoint F
Appoint Facilities Managem
Appoint Appoint
For example, by issuing design intent of importance as they are used to isneutral
is procurement – is neutral
procurement – Design
procurement neutral – Design
& Build 2 Stage& BuildDesign
2team
client & Build
Stage client2team
Stage client team design team design team design team ER ER services
Pre-contract ER services
Pre-contract
agreement Pre-contract
agreementservices agreement
CP contractor CP contractor CP contractor Left: Highlighting the points where
and Asset Managementand Asset
teamsM
strategic advisers asstrategi
neede
See  Overview See  Overview
guidance for Overview
guidance
See  for guidance for
Management Management
Contract Contract
Management Contract 2. Concept Design Appoint 3. Spatial coordination 4. Technical Design
information and a descriptive specification, determine whether work is being Appoint Appoint specification information needs
a detailed
a detailed description of description of descriptionManagement
a detailed
Construction of
Construction Management Management
Construction Information Exchanges
contractor contractor contractor
Information Exchanges Information Exchanges
the design team allows the cladding undertaken to the required quality to be exchanged during stages
how each how
stage eachbestage
might might
how eachbestage might be Appoint
Appoint Appoint 2, 3 and 4.
contractor to propose a unique design and that any testing andadjusted adjusted to accommodate
to accommodate
certification Contractor-ledContractor-ledContractor-led
adjusted to accommodate ER ER ER Preferred bidder Preferred bidder
CP Preferred CP
bidder
contractor contractor CP contractor
the of
the requirements requirements
the of the
the requirements of the
proposition that meets the goals of a project to confirm this is received.
Procurement Procurement
Procurement Strategy. Strategy. Strategy.
Information InformationInformation Client Requirements
Client Requirements Client
Project Brief Project Brief Project
Requirements Project Project Brief Derogations
BriefBrief Derogations Project Signed
BriefoffDerogations
Signed Stage off Stage
Report Report
Signed Manufacturing
off Stage Report
Manufacturing Information
Information Manufacturing
Building Manual Building
Information Manual
including including
Building
FeedbackManual Feedback on Project
including
on Project Feedback
Feedback Feedback
Project
on from Post
cost-effectively. The other notable anomaly Health and SafetyHealth
Fileand
andSafety
Health andSafetyPerformance
Fileand
Performance File and Performance Occupanc
Occupancy Evaluation
Exchanges
Employer’s Employer’s Employer’ s ExchangesExchanges Business Case Business Case Business Case
Feasibility Feasibility
Studies Studies
Feasibility
Signed Studies
off Signed
Stage off
Report Stage Report
Signed off
Project Stage Project
Report
Strategies Strategies
Project Strategies
Construction Construction
Information Information
Construction Information
to the prescriptive specification process is ER ER ER
RequirementsRequirementsRequirements Fire Safety Information
Fire Safety Information Fire Safety Information
at the
at the end of the end of the
stage stage
at the end of the stage Final CertificateFinal Certificate
Final Certificate
Updated Building ManuaB
Updated
the preparation of shop drawings. For Dale is director of technical practice at Site Information
Site Information Site Project
Information Project Strategies
Strategies Updated
Project Updated Outline
Outline
Strategies Outline Final Specifications
Final Specifications
Updated Final Specifications
Contractor’s Contractor’s Contractor’ s Practical Practical Completion
Completion Practical Completion including Health and H
including
AECOM. He is also an RIBA Ambassador Specification Specification Specification Feedback from Feedback
light fromFeedback
touch light touchfrom light touch
example, a supplier might produce drawings CP CP CP
Proposals Proposals Proposals Project BudgetProject BudgetProjectOutline Outline Specification
Specification
Budget Outline Specification Residual
Residual Project Project
Strategies Strategies
Residual Project
certificate Strategies
certificate including
including certificate including Safety File andSafety File
Fire Safet
Post Occupancy Post Occupancy
Evaluation Evaluation
Post Occupancy Evaluation
for toilet cubicles or a roller shutter which for Collaboration and Technical and is Updated Cost Updated
Updated Cost Plan Plan Cost PlanBuilding Regulations
Defects List Defects List Defects List Information as Informatio
necessary
Project Programme
Project Programme CostProgramme
Project Plan Cost Plan Cost Plan Building Regulations Building Regulations
aids manufacturing, and would be based on on the Construction Industry Council Planning Application
Planning Application Application
Planning Application Application
Application Asset InformationAsset InformationAsset Information
Procurement Strategy
Procurement Strategy Procurement Strategy
the design team’s prescriptive information. In (CIC) Board.
ResponsibilityResponsibility
Matrix Matrix
Responsibility Matrix If Verified Construction
If Verified Construction If Verified Construction
many instances, it is not issued for comment. Information
Information is required, is required,
verification verification
Information is required, verification
Information Requirements
Information Requirements Information Requirements tasks must be defined
tasks must be defined tasks must be defined

Core RIBA Plan ofCore


Work terms
RIBA areof
Plan defined
Work
Core in Plan
RIBA RIBA
theare
terms Planterms
ofdefined
Work of
in Work
theare2020
RIBA Overview
Plan
defined of Work
in the 2020
RIBA Overview
glossary
Plan and
of set in
Work BoldOverview
Type.
glossary
2020 in Bold Type.
and set glossary and set in Bold Type. Further guidance Further
and detailed stage
guidance descriptions
and detailed
Further areand
stage
guidance included in the
descriptions
detailed RIBA
are
stage Plan ofinWork
included 2020
RIBA
theare
descriptions Overview.
Plan
includedofinWork 2020
the RIBA Overview.
Plan of Work 2020 Overview. © RIBA

12 National BIM Report 2020 The definitive industry update 13


Summary of findings
David Bain
from the tenth annual
Research Manager, NBS
BIM survey
This survey marks the tenth consecutive year that we have asked
design and other construction professionals about BIM.
During that time, there has been much discussion about: the benefits or otherwise of BIM;
what it is; what it isn’t; and (in particular) how many people are ‘doing’ it.

Even after almost ten years of carrying out In this summary of the results, we On a final note: we began gathering
this survey, people are still keen to share present this year’s findings – alongside responses for this survey in December
their views on BIM: we have had one of the some comparisons with previous years. last year. No one had heard of COVID-19,
largest responses, with over 1000 people We revisit the first survey that we carried and the survey closed well before the
completing the survey. We thank them all out at the beginning of the last decade, lockdown began in the UK. It’s unlikely
very much for taking the time to do so. which highlights some interesting changes. that the pandemic has affected the results
Over the time that BIM has become part of this research much, if at all. We report
Over the years, we have also seen of our industry, and partly because of the results as we find them, but are very
growing interest from professionals BIM, many new technologies and ways much aware of the virus’ huge impact
working in countries around the world of working have emerged. Some of these on people working in construction, and
– looking at what the UK has been doing. provide an insight into what the future of on society as a whole. We hope that
In recent years, this has resulted in a construction might be like, and help us what we learn from this research can
considerable number of responses from look ahead to the next ten years. provide some useful knowledge to help
people based outside of the UK: the support the industry working during this
majority come from within the UK, but this For this survey to be a success, we rely unprecedented time, and in the recovery
year we have people representing every on the support of the many organizations that follows.
continent (except Antarctica!). We highlight that help to promote the survey. These
some interesting differences, depending organizations are listed on the inside front
on whether or not people are based in the cover of this report, and we thank them
UK. Within this summary you will find three for working with us.
inserts where we focus on some differences
in findings by respondents' location, age
and organization size.

Over the years, we have also seen growing interest


from professionals working in countries around the world
– looking at what the UK has been doing.

14 National BIM Report 2020 The definitive industry update 15


BIM awareness and ‘use’ 2011 vs 2020 To pick up the first point: lack of Therefore, the most common types These findings suggest that the industry has
momentum following the Government’s of projects using BIM are: developed its own momentum for driving
BIM mandate. This year, we asked a new BIM forward: with projects in the private and
1% • private sector new building projects
question to find out whether there were third sectors being commonplace, it is not
for repeat clients (62% of those doing
13% differences in the adoption of BIM in terms just about people adopting BIM to meet the
private sector new building work used
of the sector or type of work being carried requirement on central government projects.
BIM with repeat clients); and
26% out. Here, we see that survey respondents
are as likely to have adopted BIM on private • public sector new building projects ‘ I can see the benefits of BIM when working
2011 2020 sector projects as on those in the public for repeat clients (67% of those doing with new-build projects when using fairly
43% public sector new building work used standard details (as in BIM objects, wall
just 13% were 73% are now sector. In fact, if we total up new build
and refurb projects (for repeat and one-off BIM with repeat clients). types and roof types which are available
using BIM using BIM
clients, for each sector), we find that more within the software without user
73% 50% of professionals working on private configuration) however for renovation
45% respondents have used BIM on private
new builds said that they had used BIM works or smaller domestic schemes, the
Aware and using projects (77%) than on public (62%).
on these types of project for one-off additional time spent modelling existing
BIM is more commonly used by repeat
Just aware clients. The equivalent figure in the public buildings or working out how to model
clients, especially in the public sector.
sector was 40%. Refurbishment BIM non-standard details (such as complex
Unaware In the private sector, BIM projects are also
projects for one-off clients were slightly existing roof details or unusual bay
more common among repeat clients, but
less likely in both sectors: 44% for private windows) undermines any potential
respondents report that they are more
jobs and 33% for public sector. productivity gains, especially when there
likely to have applied BIM to projects for
BIM adoption: then and now one-off clients in the private sector than would be a loss of productivity associated
BIM principles were also applied in work
We first carried out this survey in 2010/ 2011, Almost a quarter (23%) of those ‘using’ from the BIM Task Group to support the in the public sector. BIM is also more likely with learning the software and an
for other sectors, such as charities. They
publishing the inaugural report in spring BIM state that they do so on all projects. delivery of the Government’s Digital Built to be used on new build projects as increased liability of mistakes are made’.
were slightly more likely to be used for
2011. So, almost a decade later, have things Additionally, almost half (46%) do so for Britain strategy. In addition, BIM is perhaps opposed to refurbishments. one-off clients: 44% on new build and
changed? Back then, 43% of respondents the majority of projects so, for those that typical of other innovations and ways of 40% on refurbishment projects.
were not aware of BIM and 13% said that have adopted BIM, it is becoming part of working in that once a majority of people
they had adopted it. Using the same metric how they work. have adopted it, the uptake then slows.
as that used in 2011, our survey indicates The reasons for this slowing can perhaps
that 73% of the industry is now aware of Last year, we reported a slight drop in be found by analysing the characteristics In the last 12 months, on which of these types of project, and with which types
and using BIM: 60 percentage points higher BIM adoption. This may have reflected a loss of the people and organizations yet to of client, have you used BIM?
than at the beginning of the last decade. of momentum from government, following adopt BIM. In this section, we explore
its 2016 mandate for BIM. There were also Private sector – new build 50%
This is also an increase on 2019, and marks these three themes.
changes in the support framework, such as 62%
the highest level of adoption that we have 7%
seen to date. the Centre for Digital Built Britain taking over
Private sector – refurbishment 44%
53%
20%
BIM adoption over time
Public sector – new build 40%
67%
2020 73% 26% 1%
5%
2019 69% 29% 2%
Public sector – refurbishment 33%
2018 71% 28% 1% 57%
23%
2017 62% 35% 3%
Other sector e.g. charity – new build 44%
2016 54% 42% 4% 43%
20%
2015 48% 48% 5%
Other sector e.g. charity – refurbishment 40%
2014 54% 41% 5% 30%
39%
2013 39% 54% 6%

2012 31% 48% 21%


Used BIM for ‘one-off’ client Used BIM for ‘repeat’ client
2011 13% 45% 43%
Did not use BIM on this type of project

Aware of and currently using BIM Just aware


Note: Percentages in the above chart are based on the number of respondents doing that type of
Neither aware of nor using work, e.g. out of the number of respondents said they did private sector new build, 50% used BIM
for a ‘one-off’ client. See page 29 for a breakdown of respondents by project type. Considerably
more respondents carry out private or public sector work, compared with work in other sectors.

16 National BIM Report 2020 The definitive industry update 17


In terms of the second theme introduced likely to turn to are NBS, BSI, the UK BIM In October last year, the UK BIM Alliance, BSI
above (the BIM support framework): there is Alliance and the RIBA. Considerable and CDBB launched the UK BIM Framework
now a highly developed, cross-industry numbers of people also mention (ukbimframework.org), designed to be the
Focus: too small for BIM?
network of support organizations, experts BuildingSMART (especially those outside first stop for anyone who is responsible Over the years that we have been it successfully – although those medium and 44% of large organizations).
and reference documents to help people the UK), BRE and the Centre for Digital Built for specifying, delivering or managing carrying out this survey, we have heard small practices yet to adopt BIM are Small practices are no more likely to
adopt BIM in a consistent way. We look at Britain (although these results suggest information for an asset. Initiatives like about the particular challenges that less convinced of its benefits than cite lack of training and expertise as
the standards in the next section, but in that CDBB still doesn’t seem to be as this should make it easier to find out smaller practices face in adopting any larger companies. Despite this, among a barrier; in fact, more of the larger
terms of support and information sources well known as the BIM Task Group was). about BIM and to facilitate construction new ways of working or new tools. the smallest practices who have not organizations highlight this.
about BIM, we see a similar picture to last These organizations are working to provide professionals adopting it on their projects. This is reflected in their use of BIM: adopted BIM, over half (55%) do intend
to do so. So, a lot of this is about small
year. The organizations that people are most practical advice on BIM to the whole industry. 62% of practices with 15 members
organizations’ perceived suitability of
of staff or fewer have adopted BIM,
When we explore the barriers stopping BIM for small projects. Can the success
compared with 80% of those with
small practices from moving ahead stories from the smallest practices be
Which of the following are you likely to turn to for information about BIM? over 50 employees. The figure for
with BIM, there are some differences shared with their contemporaries to
small practices has improved
compared with larger companies. help them realize the benefits of BIM?
NBS 65% compared to last year, where it was
Almost two thirds (66%) of small And can BIM be applied in such a way
BSI (British Standards Institution) 45% 56%. The group most affected are
organizations say that their projects as to improve information management
The UK BIM Alliance 41% the smallest micro-practices: only
are too small (compared with 26% on small projects?
45% of those with one or two staff
RIBA 35% of large organizations) and, similarly,
state that they have adopted BIM.
A BIM consultant 35% 52% say that BIM is not relevant to ‘ Nothing I have ever seen about BIM
A software vendor 32% However, the small practices that their projects (compared with 17% overcomes the barriers to very small
BuildingSMART 30% are using BIM are as likely as bigger of large organizations). This is a bigger companies using it i.e. – no client
organizations to recognize its benefits, issue than cost, although the latter is demand, unsuited to small projects,
BRE 24%
reporting that it has made them more more likely to be a challenge for small time, cost and lack of interest and
Centre for Digital Built Britain 20%
productive and that they have adopted practices (49%, compared to 39% of ability for small contractors to use it’.
A software reseller 13%
RICS 2%

In terms of the third point (why momentum This is the case again this year, with 80% been carried out using BIM, these are still But what does ‘doing’ or ‘using’ BIM really mean?
has slowed now that the majority state that of organizations that have more than 50 less common. To manage information There has been much debate about what process: either following the BS and ‘ BIM is still seen by many as just 3D
they have adopted BIM): we can take a look employees having adopted BIM, compared digitally for an existing building, there are BIM is in practice, and the extent to which PAS 1192 series, previously known as models used by designers, PMs and
at those who have not yet done so. Logic to 62% of those with 15 staff or fewer. costs associated with scanning it to gather people are implementing it consistently. BIM Level 2 (37%), or the newer BS EN construction teams must get on board
would dictate that they have not adopted We also find this year that younger that data. As a key benefit of BIM is to Sometimes people have confused BIM with ISO 19650 standards (26%). If we just take for BIM to be a success, it is the biggest
BIM either because there isn’t a real need professionals are more likely to say that improve the supply of information over an simply creating 3D models. We asked those those respondents in the UK, the figure blocker in our business’.
to do so or because the barriers are too they have adopted BIM than older asset’s lifetime, it is unsurprising that repeat who said that they’ve adopted BIM to select associating the use of BS and PAS 1192
great. We have previously highlighted the respondents. We explore these themes clients who have been able to review past the one listed statement that best describes with ‘doing’ BIM rises to 41%. This is
differences between larger and smaller further in the insert opposite and on page projects are more likely to recognize the their organization’s overall approach to BIM. encouraging, in that more people identify
organizations, where BIM adoption has 21. We also see above that while many benefits of BIM and to ask for it. A quarter do still think of BIM as working with BIM as a process rather than using
been much greater among the former. refurbishment and one-off projects have with 3D parametric models; however, a particular type of technology.
the majority describe it as a standardized

Thinking about your organization’s overall approach to BIM, which of the following
would you say best describes what you do?

Following the process defined in standards, such as the 37%


BS 1192 and PAS 1192 series (known as BIM Level 2)
We follow the process defined 26%
in the BS EN ISO 19650 standards
We work with 3D parametric models 25%

The organizations that people are most We approach BIM differently 10%

likely to turn to are NBS, BSI, the UK BIM Alliance Don’t know 3%

and the RIBA.

18 National BIM Report 2020 The definitive industry update 19


However, anyone can tick a box to state that However, this is evidence that a number of is suitable for (61%), and nearly half are Why adopt BIM?
they adhere to the latest standards. What the tangible things that are part of the BIM highlighting amended information through
Over the years of carrying out this survey More than half of BIM users have experienced It is unsurprising, therefore, that almost
does this mean in practice? We dug a little process are taking place. And if two thirds of the use of revision codes (46%).
and speaking to architects, engineers, increased profitability due to BIM, with 40% two thirds of BIM users (66%) expect
deeper by asking which tasks or documents organizations are using BIM execution plans,
technologists, contractors and manufacturers, of non-users anticipating this if they were clients to insist on BIM. Here, though, there
(as outlined in the BS EN ISO 19650 series) this should bring some consistency and The use of BIM should not be dependent
it’s been clear that implementing BIM properly to adopt it. As well as benefiting individual is a disconnect between those who have
respondents have been involved in. We find standardization as large numbers of people on having particular software platforms
is a major task. It requires considerable organizations, BIM can aid the management adopted BIM and those who have not.
that many of these things are common on become aware that this is ‘how to do BIM’. but should enable interoperability between
investment of time and resources. Workflows of projects: the vast majority of users and Only just over a third of non-users say that
BIM projects in particular: BIM execution them, using data formats such as Industry
and processes need to change. So why do it? non-users say that BIM increases coordination clients will insist that they adopt BIM.
plans (67%), common data environments BIM is about managing information and Foundation Classes (IFC) and Construction
of construction documents (85% and 76%,
(67%), information standards (58%), doing so in collaboration with others. The Operations Building information exchange ‘ BIM methodologies are incredibly useful
While adopting BIM is challenging, it respectively). 72% of BIM users and 64%
exchange information requirements (56%) way that information is shared is therefore (COBie). 62% stated they exchanged in terms of co-ordination between different
provides benefits to the organizations of non-users agree that it reduces the risk
and information production methods and important, and it needs to be done in a way information in IFC format and a third in disciplines. It speeds up the process and
that use it. The majority (71%) of those who of problems arising. These are all positive
procedures (54%). Some of these things so that all parties understand what they are COBie. Finally, we see that over a third aids in communication as well as
have adopted BIM report that it has made outcomes for the companies completing
seem to be happening less often, such as reviewing or working on. It’s encouraging (38%) of those using BIM are classifying production of information’.
them more productive. Over half (57%) of construction projects, and also for the
master information delivery plans (32%); to see that over two thirds (68%) follow a information using Uniclass 2015.
those yet to adopt BIM also agree. clients commissioning them.
therefore, perhaps, one might argue that the naming convention for all information that
full BIM process as outlined in the BS EN is shared. Almost as many are clearly
ISO 19650 series isn’t happening all the time. indicating what the shared information
From your understanding of BIM, how strongly do you agree or disagree with
the following statements?

Thinking in more detail about BIM, in the last 12 months, which of the following things Adopting BIM has increased/ would increase 85%
have you been involved with, in some way, on BIM projects you have worked on? coordination of construction documents 76%

BIM execution plans 67% BIM has reduced/ would reduce the risks 72%
of problems arising on projects 64%
Common data environments 67%
Information standards 58% Adopting BIM has made/ would 71%
make us more productive 57%
Exchange information requirements 56%
Information production methods and procedures 54% Clients will increasingly insist 66%
on us using/ adopting BIM 35%
Information protocols 46%
Detailed responsibility matrix 42% Adopting BIM has increased/ would 51%
increase our profitability 40%
Task information delivery plans 38%
Master information delivery plans 32%
Agree: Adopted BIM Agree: not adopted BIM
None of these 7%
Don’t know 2%

Focus: is it an age thing?


Thinking about the projects where you have adopted BIM, which of the following tools) is more straightforward for There is a more mixed picture in terms
It can be tempting to assume that the
approaches has your organization adopted with respect to sharing information? of use of new technologies: age appears
older someone is, the less likely they younger professionals.
are to embrace new ways of doing to have limited influence on things like
Following a naming convention for 68%
things. Sometimes this is unfair, and The survey data bears this out: 80% cloud computing. However, in some
all information that is shared
there are many examples of experienced of those under 35 state that they have cases, younger professionals are more
Exchanging information in IFC format 62%
professionals who are innovators, and adopted BIM, compared with 75% of likely to use new technologies: for
see the potential in new technologies. those aged between 35 and 54, and instance, 46% of under-35s use virtual,
Clearly indicating what the shared information is 61%
However, the more experienced 60% among those over 55. Among augmented or mixed reality, compared
suitable for (e.g. for information, for review, as a record)
generations have to actively change those who have yet to adopt BIM, only with only 25% of those over 55. Attitudes
Highlighting amended information through 46%
the use of revision codes how they do things, whereas many 7% of under-35s say that they will never to the transformative potential of
‘millennials’ who began reaching do so; this rises to 19% for over-55s. digitization also differ considerably by
Classifying information using Uniclass 2015 38%
adulthood around the turn of the There are some links between age and age. This time, the difference is most
century have grown up with the internet, other factors. Younger professionals pronounced between those under 54
Exchanging information in COBie format 33%
mobile devices and touchscreens. are more likely to work in larger and those over. Over 80% of the former
Working with digital information is organizations, and they are also more believe that digitization will transform
None of these 5%
what many have always known. So, one likely to be in architectural technologist the whole construction industry,
could argue that embracing BIM (which or BIM manager roles. This suggests compared with just 63% of the latter.
Don’t know 4%
has at its heart well-managed, digital that decisions about BIM adoption are
information, and uses a range of digital influenced by a combination of things.

20 National BIM Report 2020 The definitive industry update 21


How strongly do you agree or disagree with the following statements Intent to adopt BIM Currently use BIM
about BIM?
In 2020, the proportion of those who have
2019 22% 44% 34%
adopted BIM for all or the majority of projects
We need manufacturers to provide
81% 12% 7% is slightly higher than it was last year. And 2020 23% 46% 31%
us with BIM objects
over 90% do expect this to increase so that,
Using BIM results in operation
74% 19% 7% in the next five years, they are using BIM for
and maintenance savings For all projects For a majority of projects
all or the majority of their work.
BIM is now the norm for project information For a minority of projects
40% 22% 38%
‘ BIM will form the basis of all large construction
The UK is the world leader in BIM projects in the next few years, and most
38% 43% 19%
construction projects within 5 years’.

Agree Neither agree nor disagree Disagree However, ever since we started asking this In five years’ time, we will use BIM... (those NOT using BIM)
question almost a decade ago, much of the
profession has been saying that it will adopt 2019 13% 21% 27% 9% 29%
BIM for more projects within the next five
While it is clearly a good thing that BIM Interestingly, many of these figures have Despite the UK being a key player in 2020 6% 27% 39% 12% 16%
years. The stated intention and what is
leads to more productive and profitable not varied greatly since we started asking developing the standards for BIM globally,
actually achieved can be quite different.
organizations and projects, it also needs the industry about BIM in 2010. Back then, it isn't always business as usual here.
Also, when we look at those yet to adopt For all projects For a majority of projects
to contribute to improved outcomes for many felt that BIM improved productivity, This might go some way to explaining why
BIM, there remains a significant group of For a minority of projects Never Don’t know
those who own, manage and use the asset. profitability and coordination of documents. only 38% see this country as the world
professionals who do not intend to use
This is the case: respondents to this survey The challenge for many has been to make leader in BIM (although this is an increase
BIM (12%) or are unsure (16%).
have consistently agreed that BIM results in the investment of adopting BIM and there from 30% last year). The insert on page 25
operation and maintenance savings, with being a sufficient driver from clients explores some of the differences in findings
74% saying so in 2020. to encourage this. More on this in the depending on whether or not people
next section. are based in the UK. Now, though, let's
‘ I see BIM improving efficiencies significantly address some of the reasons why BIM isn’t
when an asset is in use. There will be Some things have changed, however. further embedded after ten years of the
good communication and clear task Over the last decade, we have seen We have adopted BIM successfully | 68% I'd rather we had not adopted BIM | 5%
Government and others promoting its use.
briefing between facilities managers and manufacturers providing their information If we don’t adopt BIM, we’ll get left behind | 58% I'd rather not adopt BIM | 14%
operatives who carry out repairs and as digital objects. The use of these objects ‘ Perhaps more focus on the main benefits
maintenance of the assets’. has grown to the point where 81% of of BIM would lead to its more widespread
respondents to this survey now state that adoption i.e. clash detection/clash
‘ I think a major benefit is the accuracy they need manufacturers to provide them. avoidance, the coordination between
and reliability of our information’. the disciplines and the 3D visualisation. For Against
Does this requirement for digital objects
‘ The evolution of the construction industry and the increase in adoption of BIM mean
The rest is either box ticking or showing off.
It is a shame that there are not graduated
using BIM using BIM
has been accelerated by BIM processes that it’s now the norm? 40% think that it is standards for small works, medium works,
and technologies’. (three percentage points higher than last large works, and mega works. It does
year) but a significant proportion (38%) still not appear right or necessary for all the
disagree. So, while many organizations are standards to be applied in the same
familiar with BIM, have adopted it and are manner over different scale of works’.
seeing benefits, it does not affect how
all projects are managed all of the time.

Of those who have embraced BIM, over two In the past, we have seen that lack of The support network, standards, guidance
thirds (68%) report that they have done so in-house expertise, lack of training and and training programmes that have grown
successfully, up from 63% last year, and only cost have all been significant barriers to up around BIM would appear to be making
5% wish that they hadn’t. Over half (58%) organizations that might wish to adopt BIM. a difference, as people’s knowledge has
of those yet to adopt BIM are concerned They still are, but the number citing them increased. While cost remains an issue,
that they’ll get left behind, but 14% do still has dropped for each of these. Since last many will now have made investments in
say that they would rather not do so. year, lack of expertise has fallen from 63% new technology platforms (even if they are
to 56%, training from 59% to 48%, and not all using them to apply BIM principles).
cost from 51% to 46%. More people are
Despite the UK being a key player aware of BIM, what it means and which

in developing the standards for BIM globally,


tasks are involved.

it isn't always business as usual here.

22 National BIM Report 2020 The definitive industry update 23


Lack of client demand, cited by 64% of this there is still a big difference. Finally, ‘ Clients are the main driver as main
year’s respondents, remains the greatest project size and type continues to play a contractors and suppliers won’t bear
Focus: outside looking in
barrier among those yet to adopt BIM. role. While we see this year that BIM is used the increased cost just for their own
Over the years that we have carried support network that has developed, Maybe those taking the trouble to
Aligned to this, 45% say that the projects on many refurbishment projects, it is not benefit, despite the positive ROI BIM has
out this survey, a growing number of and its central role in developing complete a survey in other another
they work on are too small (this figure has as straightforward as in new builds. And shown to provide in recent years’.
professionals based outside the UK standards such as the ISO 19650 series. country may well have a stronger-than-
actually increased since last year), or that for small projects, the BIM outputs need
have completed it. For the last two Perhaps this has led to interest from average interest in BIM. This may be
BIM is not relevant to their projects (36%). to be simple and applicable to smaller ‘ I work on a Government site and there
surveys, around a quarter of respondents professionals in other countries to follow true: adoption is higher among this
jobs; otherwise, small clients, developers is NO demand for it on projects. This isn't
There may be several explanations for were based in other nations. There could the UK’s progress and take part in the group, with 82% of those outside of the
and builders are unlikely to view it as an setting a good example’.
this perceived lack of impetus from clients. improvement in managing information. be various reasons for this. Some may survey? Certainly, respondents outside UK stating that they use BIM, compared
Our BIM surveys over the last few years well have strong connections to the UK, of the UK are much more likely to think with 70% of UK professionals. However,
‘ I think the cost of BIM and the need for
have highlighted a loss of momentum ‘ The real world is still built with actual perhaps working for global companies of the UK as the leader in BIM: 48% non-UK professionals are more likely to
full collaboration is one of the main issues.
from government in driving forward and materials which are described in 2D Small firms cannot justify the expense, with UK HQs. The UK’s professional compared to 27%. The difference here is describe BIM adoption as working with
enforcing the mandate for BIM on central drawings which are published from the training, computers etc. and clients institutes, like the RIBA, are also mainly accounted for by a high proportion 3D models (34% compared to 22%)
government-procured assets. This has likely BIM models, printed on paper and read generally are not requesting it’. active overseas. of UK professionals neither agreeing nor rather than as a process. Unsurprisingly,
reduced the demand for BIM on projects in on dirty construction sites… models disagreeing about the UK being a leader use of ISO 19650 is similar to in the UK,
the public sector. Secondly, smaller practices have serious limitations, and we must The UK has played an active role in in BIM, or not knowing. It implies that while following the process outlined
have highlighted the difficulties of juggling detail a great deal in 2D, even to the driving forward BIM adoption: through those outside the UK have a clearer in BS and PAS 1192 is lower: 26%
day-to-day business development and extent of transferring 2D views of the government initiatives, the strong view about this. compared with 41%.
project delivery with upskilling and investing 3D model into purely 2D plans, sections
in BIM. While it is encouraging to see and elevations, just so we can get the
signs that the gap between large and drawings to be published as reliable
small practices’ uptake of BIM is decreasing, construction contract documents’.
The tools that enable BIM and digital transformation
As has been stated many times When we asked, at the beginning of In 2020, we see that things have shifted
What are the main barriers to using BIM? before, BIM is not a technology and not the last decade, which main digital design to the most popular tool being Autodesk’s
dependent on one technology provider. tool people used, none of the tools geared Revit: used by exactly half of this year’s
No client demand 64% However, to enable BIM and further digital to creating 3D models were used by respondents. This is followed by Graphisoft’s
transformation, the industry needs effective more than 10% of respondents. Tools ArchiCAD, with 16% saying that this is their
Lack of in-house expertise 56% tools. In recognition of this, we seek to used primarily to produce 2D drawings main design tool.
understand which digital platforms were far more popular, with Autodesk’s
Lack of training 48% construction professionals are using AutoCAD being used by 55% of those
to help manage project information. using design software.
Cost 46%

The projects we work on are too small 45%


Which of the following do you use as your primary design tool? *

Differences in expertise among collaborating 41% Autodesk Revit – (Architecture / Structures / MEP) 50%
parties in a project
Graphisoft ArchiCAD 16%
BIM is not relevant to the projects we work on 36%
Autodesk AutoCAD 13%

Not time to get up to speed 33% Autodesk AutoCAD LT 7%


Vectorworks 4%
No established contractual framework 28%
for working with BIM * The five most used design tools
Lack of collaboration 28%

Lack of standardized tools and protocols 27%

Operating system-specific software 20%

Don’t see the benefit 15%


When we asked, at the beginning of the last decade,
We are unsure of the Government’s
commitment to BIM
14%
which main digital design tool people used, none of the
Liability concerns 11% tools geared to creating 3D models were used by
Other 8% more than 10% of respondents.

24 National BIM Report 2020 The definitive industry update 25


In 2020, there is now a whole set of new A key aspect of BIM is the information the use of Microsoft’s online version of A digital future?
digital tools used to help construction associated with the 3D model and the Office (365) is used by more people than
BIM and good information management It can also include more straightforward ‘New technology and innovations will
professionals check, share and review specification is a key part of this. A majority its desktop counterpart. This marks a key
are the foundations for the introduction tasks such as using online storage and file always seek to improve the industry, I see
models and associated project data. (59%) of users in the UK use NBS to develop moment in the progression towards of new digital tools and ways of working. transfer, or online word-processing packages BIM as the foundation to the technologies
While vendors like Autodesk, Nemetschek specifications. Within NBS, there is also a cloud-based ways of working. These technologies go hand-in-hand with such as Microsoft Office 365. It is likely that which are or will be available’.
and Solibri provide a number of solutions move to the cloud with almost a quarter BIM to improve the visualization of designs people’s perception of cloud computing
that are widely used, there are many of NBS users already using NBS Chorus. ‘There are new and useful tools coming
for clients, the sharing of technical data varies: it is possible that some who may be ‘ Absolutely agree that full integration of
other platforms that have entered the From our own analytics we can see that, out every day to help us automate and
with other project team members, and using it in some way may not have classed technology and BIM is essential but this
market. For instance, while Viewpoint as of May 2020, there are over 1500 create smart design through algorithmic
the connection of different types of data themselves as doing so. needs momentum and someone to drive it’.
is the most popular common data organizations subscribing to NBS Chorus, programs and software. Exciting to watch
across the project and within an asset.
environment (CDE), cited by half of with this number growing each month. as things progress’. Architects and other designers have
The technologies used by most people This survey was carried out before the
respondents, construction professionals been using virtual reality to bring designs
now relate to cloud computing (42%) COVID-19-induced lockdown began in the
collectively use at least 18 different Most of us work with word-processing ‘ I think the biggest problem is getting to life for clients for some time. Others,
and immersive technologies, including UK. It would be reasonable to think that
providers. Also noticeable is the use documents and spreadsheets, and for many the smaller sub contractors on board. such as those managing buildings, have
virtual, augmented and mixed reality the use of these technologies has increased
of more generic solutions from the tech years the most common approach has by Once many of our own have been showed been applying augmented reality to do
(38%). Cloud computing can include since then. Nonetheless, 80% of survey
giants, with GoogleDrive and Microsoft’s far been the use of Microsoft Office on a the physical benefits they are completely things like overlay instructions and
quite a range of things, such as carrying respondents anticipate using cloud
SharePoint and OneDrive featuring. desktop or laptop. In 2020, for the first time, sold on the idea’. maintenance data to assist those
out major tasks like writing specifications computing within five years, and 78%
or sharing models over the internet carrying out repairs. immersive tech. We may now see the
via a common data environment. move towards these numbers accelerate.
Which project extranets or common data environments do you use?

Viewpoint/4projects 50% Please tell us about your current and expected use of the
Autodesk 360 range 39% following technologies
Dropbox 38%
Cloud computing
42% 15% 12% 10% 4% 16%
Microsoft SharePoint 36%
Aconex/Conject 36% Virtual/augmented/mixed reality
38% 15% 15% 10% 5% 17%
Asite 32%
Microsoft OneDrive 30% Drones
32% 11% 12% 11% 13% 21%
Google Drive 23%
Bentley Projectwise 18% Design for Offsite Construction
30% 12% 13% 11% 7% 27%
Deltek/Union Square 11%
3D printing of building components
Clearbox BIMXtra 6% 11% 5% 16% 19% 16% 33%

Procore 5%
Analytics and Big Data technologies
10% 12% 16% 15% 9% 37%
Huddle 5%
Group BC 4% Digital Twins, sensors,
9% 11% 14% 14% 12% 41%
Causeway Livelink 2% machine-to-machine communication

Newforma 2% Artificial intelligence or machine learning


6% 7% 16% 17% 16% 38%
Documentum 1%
ShareFile 1%
Other 12% We use now We will use in one year’s time

We will use in three years’ time We will use in five years’ time

We will never use this Don’t know


What tool(s) do you use when working with documents and spreadsheets?

Microsoft Office 365 69%


Microsoft Office Desktop 55%
Adobe InDesign
Google Docs
22%
16%
This survey was carried out before the
Apple Pages/Numbers 6% COVID-19-induced lockdown began in the UK.
Open Office
Other
4%
5%
It would be reasonable to think that the use of these
technologies has increased since then.

26 National BIM Report 2020 The definitive industry update 27


Almost a third of respondents are using at present, although around half expect ‘I believe the biggest barrier to adopting How we did the research and who took part
drones for surveying and scanning sites to be utilizing these in five years’ time. these technologies are attitudes and a lack
We carried out an online survey between However, other members of the project team People of all ages were well represented.
for instance, especially for difficult-to-reach of sharing the benefits to the client. If these
Most respondents to this survey December 2019 and the beginning of also participated, including: contractors, Individuals were engaged in a variety of
places such as bridges. Around two thirds are overcome, we already know the other
(89%) believe that the digitization of March 2020. We received responses project managers, cost consultants, roles that covered tasks from developing
expect to use drones within five years. benefits in terms of time, cost and quality
the construction sector will transform from 1061 construction professionals. manufacturers, surveyors and clients. Those drawings and models to writing
A similar proportion of professionals (30%) and I think it will significantly improve the
the way they work. 78% believe that it will All organization sizes were represented, doing private, public and work in other sectors specifications, coordinating information
report that they are designing for off-site way we work and the assets we produce’.
from micro-practices of one or two people were well represented, as well as those and sourcing or creating digital objects.
construction. The advantages of these transform the whole construction industry.
to large practices with over 500 staff. doing new build and refurbishment work. Working with digital information has
technologies, as well as 3D printing, may They see real potential and new ways of We have posed similar questions to designers
As previously, responses came primarily become commonplace, with almost
come into play during a time where physical working in digital transformation, improving: and other construction professionals in
from the design community, with 27% Respondents came from across the UK, two thirds viewing models, 55% creating
distancing needs to be maintained, allowing productivity (78%), speed of delivery (74%), recent years, and the response is consistent:
being architects. Engineers were also and almost a quarter were working outside drawings or models using 3D tools,
fewer people to spend less time on-site. health and safety (70%) and ability to meet they see digitization as a means of improving
well represented. Over a quarter were of the country. There were respondents over half checking models and 41%
Big data, digital twins and artificial sustainability challenges (69%). These are the way that people work and achieving
architectural technologists or BIM managers. based in six of the world’s continents. producing digital objects.
intelligence are at the early adopter stage some of the major challenges of our time. better outcomes for the built environment.

Thinking about the digitization of the construction sector, how far do you agree Including yourself, approximately how many people are employed
or disagree that digitization will do the following? in your organization?

Transform the way we work 89% 1–2 9%


3–5 8%
Improve the productivity of the construction sector 81%
6 – 15 15%
16 – 25 6%
Transform the whole construction industry 78%
26 – 50 10%
Improve the speed of delivery 74% 51 – 100 11%
101 – 250 10%
Improve construction health and safety 70%
251 – 500 6%
501+ 24%
Help the construction sector meet the 69%
challenges of sustainability
Help us export more 46%

Which age range do you fall into?

Under 25 4%
Final thoughts 25 – 34 23%
The growth in the awareness and But only 40% say that BIM is the norm ISO 19650 will also have been in
35 – 44 29%
use of BIM is indisputable. Its benefits for project information. While many use and helping to standardize BIM
45 – 54 24%
are widely recognized: it increases recognize the benefits, and plan to adopt processes for over a decade.
BIM and to use new technologies, there 55 – 64 15%
productivity; it improves the operation
are challenges holding people back. Key The industry’s leaders will be digital
and maintenance of buildings; it 65 – 74 4%
themes that continue to be present each natives, with an approach to information
reduces risk; it can help make management that is likely to be ‘digital 75 or over 0%
organizations more profitable. There time we carry out this survey are: the role
that clients have to play in encouraging first’. The attraction of using exciting
are internationally recognized standards digital tools will mean that organizations
BIM use on projects; and (aligned to this)
for people to follow, and cross-industry will need to structure their data in digital
the need to enable BIM in a way that In the last 12 months, which of the following project types have you been involved in?
organizations ready to provide advice formats. External legal, economic and
improves outcomes for all types of
and training. Product manufacturers environmental drivers will continue to
project. Many professionals state that Private sector – new build 73%
are increasingly providing information exert their influence, such as the new
it is not appropriate for small projects. Private sector – refurbishment 53%
in digital formats, moving away from regulatory framework for building safety,
For BIM to be truly universal, and to be
printed literature and trade shows which stipulates the establishment Public sector – new build 53%
business as usual across the industry,
towards standardized, structured of a digital thread of information. Public sector – refurbishment 39%
these issues need to be addressed.
data delivered in the cloud. All of this These sorts of drivers make it ever Other sector e.g. charity – new build 10%
seems to suggest significant progress. So, fast-forward another ten years: more likely that the adoption of BIM and
Other sector e.g. charity - refurbishment 11%
There is a plethora of new tools to aid what will things look like in 2030? of digital technologies will only continue
digitization, and these have made a Perhaps the new UK BIM Framework to increase over the next decade but
significant difference to how people will have helped to provide the processes and tools need to be applicable
work compared to ten years ago. The practical guidance that organizations to all project types, organization sizes
industry has definitely changed. of all sizes need to move ahead. and roles across the industry.

28 National BIM Report 2020 The definitive industry update 29


Introduction from NBS
Since the launch of Uniclass 2015, Furthermore, it has been fantastic to see content that we publish and classifying
we at NBS have been delighted with its its adoption internationally. This article it to the Uniclass 2015 structure. We are
adoption by industry. We have updated from John Gelder explores how Uniclass pleased to say that this exercise is now
the system quarterly now for the last 2015 is becoming the classification of complete, and users of the NBS Chorus
five years, and have received thousands choice across Australia. It is either specification platform and the NBS
of new classification suggestions recommended or required for work for Source manufacturer product platform
from industry. We are grateful for the the Office of Projects Victoria, Transport can now benefit from it.
engagement and suggestions from for New South Wales, the Rail Industry
large clients such as Highways England, Safety Standards Board and Austroads. A number of different countries around
Transport for London, the Environment the world are following the UK's approach
Agency and the Metropolitan Police. Clearly, the industry needs support in to BIM. It will be interesting to see how
A recent interoperability report terms of working with and producing many follow Australia by also embracing
well-structured information. At NBS, Uniclass 2015 for classification.
John Gelder by the Centre for Digital Built Britain
recommended continued use we have been working through all of the
University of South
of Uniclass 2015 within the UK. specification and manufacturer product
Australia

The adoption of Uniclass


2015 in Australia
Classification is needed in the construction industry.
It was needed in a pre-BIM environment (an early example being the Swedish
Samarbetskomittén för Byggnadsfrågor, SfB, which was launched in 1950),
and it is needed even more in a BIM environment where the benefits of digital
interoperability are likely to be huge.

Over the years, this need for classification Classifications have three levels of use. and others who use the classifications
has resulted in a multitude of classifications There are those who design, develop and assigned to the objects that they are
– in different countries, across different maintain the classifications. There are dealing with without knowing or caring
disciplines, and even for the same purpose those who apply the classifications to where they came from. The author has
in the same place. This has reflected and information about particular objects, such operated at all three levels. But for most,
reinforced professional and other information as manufacturers and model software object classification is ‘under the hood’.
silos, frustrating efforts to coordinate, and developers. And then there are designers, That does not mean that it is not important,
now stymying digital integration. specifiers, builders, maintenance workers and that an appreciation of it isn’t useful.

A classification system is needed –


one comprising multiple tables, each for objects of different
classes. Just one table, covering one object class, is not
enough to serve many needs along the project timeline and
across the various disciplines.

30 National BIM Report 2020 The definitive industry update 31


Table 1: ISO 12006-2 and three classification systems

ISO 12006-2 OmniClass CoClass Uniclass 2015 Classification systems


A classification system is needed – one None of the tables mentioned are part of a As for Australian BIM tools, NBS Chorus
A2, Construction information Information - Form of information
comprising multiple tables, each for objects classification system of the kind outlined in uses Uniclass 2015 as its ‘native’
A3, Construction products Products Components Products of different classes. Just one table, covering ISO 12006-2:2015.10 Current classification classification system (others can be used).21
Materials - - one object class, is not enough to serve systems include OmniClass from North The new NBS Source product – for
A4, Construction agents Organizational roles - Roles many needs along the project timeline America,11 CoClass from Sweden12 and proprietary objects, their geometries and
and across the various disciplines. The Uniclass 2015 from the UK.13 Table 1 shows properties – also uses it as the ‘native’
Disciplines - -
NCC’s partial ‘Entities’ classification is how they correlate to the ISO and to each classification system.22 Autodesk Revit,
A5, Construction aids Tools - Tools and equipment useful at certain stages and to certain other. Only two might be regarded as Graphisoft ArchiCAD and Vectorworks 2020
A6, Management Services - Project management users (e.g. architects and other designers, coherent – CoClass and Uniclass 2015. SP3 embed Uniclass 2015 for objects linked
building control authorities), but not to to NBS Chorus.23 Both NATSPEC and NZ
A7, Construction process Phases - - Since Australia has no such system of
manufacturers and installers. The NCS is, Masterspec included a requirement that
A8, Construction complexes - Construction complex Complexes likewise, useful at certain stages and to its own, the question is which of these ‘BIM objects shall have a Uniclass 2015
A9, Construction entities Construction entities by function Construction entity Entities certain users (e.g. specifiers, quantity classification systems should be adopted classification assigned’ in the 2018 draft
surveyors, subcontractors) but is not of here, if any? The answer so far has been of the Open BIM Object Standard (OBOS),
Construction entities by form - -
much interest to planners or manufacturers. Uniclass 2015, although this adoption is in but this has been dropped in the published
User activity 14
- - Activities its early stages. Among major clients, the version.24 However, its use is supported
The system must be coherent. An integrated Office of Projects Victoria recommends it.15 (after a fashion) in the NATSPEC BIM
- Maintenance activities Process activities (in development)
sequence of coordinated tables is needed Transport for New South Wales (TfNSW) ‘Properties Generator’, along with
A10, Built spaces Spaces by function Built space Spaces/locations to create a coherent object hierarchy. requires it, and is actively engaged with OmniClass and the NCS.25
Spaces by form - - This is especially the case for BIM, in which NBS in its ongoing development.16 The Rail
modelling essentially maps big things to little Industry Safety Standards Board (RISSB)
A11, Construction elements Elements Functional systems Elements/functions
things. For example, it maps buildings to recommends it.17 The use of Uniclass 2015
- Constructive systems Systems elements, elements to systems, and systems was recommended to Austroads in 2018.18
A12, Work results Work results Work result Redundant in Uniclass 2015 (see below) to products (and vice versa). Since each Client adoption means that their supply
of these object classes will have its own chains will also use it for civil works and for
A13, Construction properties Properties Property -
classification table, it would make sense if architectural works. However, most States
they were designed with each other, and have no requirements for classification
modelling, in mind. An incoherent collection in their BIM implementation guidelines.
Classification tables of unrelated tables is not good enough. For example, SA does not stipulate an
Individual unrelated classification tables are • The property classification used to so Australian specifications could ‘talk to’ approach to classification, leaving this
not enough. Current classifications in use in structure the Australian Building Codes bills of quantities, and vice versa. This was to the contractor.19 The relevant
the Australian construction industry include: Board ‘National Construction Code’ suite.5 the case in the UK some years ago. The NBS Queensland document makes no
and NES national building specification mention of classification.20
• The National Classification System (2019), • The property classification used to
systems and the RICS standard method of
published by NATSPEC.1 structure the Green Building Council
measurement used the same classification
of Australia ‘Green Star’ suite.6
• The classification used to structure the (Uniclass 1997, Table J, ‘Work sections for
ANZ Standard Method of Measurement • The buildings classification given in buildings’), enabling interoperability.8 But
of Building Works (2018), published the ABCB’s NCC (2019).7 this has never been the case in Australia
by AIQS and NZIQS (Australian and and, since RICS (the Royal Institution of
New Zealand Institutes of Quantity All seven classifications were developed
Chartered Surveyors) released the NRM
Surveyors, respectively).2 independently of each other and do not
(New Rules of Measurement) in 2012,
align – they were not intended to be
• The North American OmniClass, Table 22, it is no longer the case in the UK.9
interoperable. The first three concern the
‘Work results’ (2012), used by SpecPack.3
same object class; on a given project, it is
• The project phases classification used possible that all three could be used. In 10
ISO 12006-2:2015, ‘Building construction – Organization 16
TfNSW (2019), ‘Application of Uniclass 2015 for Transport 20
Department of State Development, Manufacturing,
in the Australian Institute of Architects particular, it would have been useful if the of information about construction works – Framework for NSW’, 6.2, ‘Our decision’: ‘TfNSW has selected Infrastructure & Planning (2018), ‘Digital enablement
for classification’, ISO, Geneva. Uniclass 2015, developed by the NBS… as the preferred for Queensland infrastructure: Principles for BIM
‘Client architect agreement (2019)’.4 first two aligned (NCS and the ANZ SMM), classification system. The choice to adopt Uniclass 2015 implementation’.
11
The OmniClass tables, including Table 22 mentioned
follows comprehensive analysis of the current state, and
above, are free online at: www.csiresources.org/ 21
NBS Chorus (Australia) is available to purchase at:
comparative research of available classification systems,
standards/omniclass. www.thenbs.com.au.
industry-wide, against ISO 12006.2:2015’.
1
NCS is free online at: www.natspec.com.au/resources/ 5
The NCC Volume 1 structure is: Structure; Fire Resistance; 8
NES (the National Engineering Specification) has since 12
CoClass tables are free online at: 22
NBS Source launched in the UK in April 2020:
17
RISSB (2019), ‘Digital Engineering: Code of Practice’,
national-classification-system. Access and Egress; Services and Equipment; Health and shut down. UK services engineers have largely moved https://byggtjanst.se/tjanster/coclass. www.thenbs.com/nbs-source.
part 6.3, ‘Project data classification’: ‘This Code of
Amenity; Ancillary Provisions; Special Use Buildings; to the services engineering content produced by NBS
2
ANZ SMM is available to purchase online at: 13
Uniclass 2015 tables are free online at: Practice recommends the use of Uniclass 2015 as the 23
For the various NBS plug-ins, see: www.thenbs.com/
and Energy Efficiency. and first published in 2004.
www.aiqs.com.au/imis/AIQS_Website/Shop/Books/ www.thenbs.com/our-tools/uniclass-2015. adopted classification of assets and locations during our-tools/nbs-plug-in-for-autodesk-revit.
AIQS_Website/Public/Shop/Books.aspx. 6
The Green Star ‘Design & As Built’ structure is: 9
The three volumes of RICS NRM are available to the project lifecycle’.
14
Identified in the ISO, but outside of its scope. 24
OBOS is free online at: https://bim.natspec.org/
Management; Indoor environment quality; Energy; purchase online at: www.rics.org/uk/upholding-
3
SpecPack is available to purchase at: 18
Austroads (2018), ‘Asset data harmonisation Stage III: documents/open-bim-object-standard.
Transport; Water; Materials; Land use & ecology; professional-standards/sector-standards/construction/ 15
Office of Projects Victoria (2020), ‘Victorian Digital
https://specpack.com.au. BIM IFC alignment review’.
Emissions; and Innovation. rics-nrm-new-rules-of-measurement/. Asset Strategy’, Part C Application, pp. 71-73: ‘ 25
The ‘Properties Generator’ is free online at:
4
These are: Concept Design; Design Development; The VDAS recommends using Uniclass 2015, 19
Department of Planning, Transport & Infrastructure www.propgen.bim.natspec.com.au/pages/178534.html.
7
NCC 2019 Volume 1 is free online at:
Town Planning/Development Application; Construction as it is ISO certified and a globally recognised (2019), ‘Project controls: Master specification – PC-EDM5
https://ncc.abcb.gov.au.
Documentation; Contractor Selection; and Contract and consistent system’. Digital engineering’: ‘The DEXP [Digital Engineering
Administration. Also in use for project phases is the Execution Plan] shall include the Contractor’s approach
RIBA Plan of Work 2020. to… Asset Classification Matrix’.

32 National BIM Report 2020 The definitive industry update 33


Why Uniclass 2015?
OmniClass is comprehensive, but it is The Systems table could also accommodate should be possible, which requires simple
not current – the most recent official tables 108 objects, and it currently classifies around 1:1 mapping. This means that an object in
are dated 2012. The tables are not coherent 1500. All this room is needed to ensure the existing table corresponds exactly to
– they were developed independently adequate space around each object for the an object in Uniclass 2015, e.g. they both
(e.g. MasterFormat and UniFormat) and addition of further objects in the future. have ‘clay bricks’. However, for many
then combined to make OmniClass. CoClass does not have this space objects this will not be the case. Instead,
Terminologies, sequences and groupings for expansion. we will find 1:many, many:1, 0:1, 1:0
are different where they could be the same, and many:many mappings. All require
making them difficult to use together One point to note for those who have human intervention for resolution, which
in an integrated BIM environment. looked carefully at Table 1 is that the is anti-BIM.
‘Work results’ table is considered redundant
CoClass is not comprehensive – it only has in Uniclass 2015 and will not be included. To avoid this, ultimately everyone will have
nine tables. These are quite small, so do not Mapping between object classes (e.g. to use the same classification system, to
allow for the classification of many objects. ‘Complexes’ and ‘Entities’) is properly ensure full interoperability and to maximize
The ‘Components’ table, for example, could done in BIM tools such as Autodesk Revit the benefits of BIM. National adoption of
classify 17 576 objects if full. The ‘Constructive and NBS Chorus. Conventionally, ‘Work a single classification system is good,
systems’ table could hold 67 600 objects. results’ (or work sections) are used for and international adoption is better.
This sounds a lot, but as they could never be mapping from ‘Systems’ to ‘Products’,
anywhere near full, for all sorts of practical which is done in the ‘Systems’ within Conclusion
classification reasons, it is quite a restriction NBS Chorus. Separate ‘Work results’ A coherent classification system for
on its future development. sections would only duplicate this construction is essential if we are to
mapping. In NBS Chorus, future mapping realize the full benefits of BIM. This is
Why are Australian organizations adopting
from ‘Complexes’ to ‘Entities’ would be why the UK Government ran a competition
Uniclass 2015? In terms of tables, Uniclass
done in the ‘Complexes’ ‘sections’ of for the development of such a system in
2015 is more comprehensive than CoClass
what would be a ‘lifetime’ specification... 2014, which was won by NBS with Uniclass
but less so than OmniClass, although
and so on. 2015. As a result, Uniclass 2015 is now
other tables are planned (several have
an official component of the UK BIM
been drafted). The tables themselves serve
Perhaps a significant omission in Uniclass Framework, and promoted in BS EN ISO
all sectors and disciplines – since 2014,
2015 is the ‘Properties’ table. Readers’ 12006-2:2020 (National Foreword). In turn,
NBS has been working hard to expand the
views on the need for this would be ISO 12006-2:2015 is mandated by ISO
original architecture focus to deal with
welcome. This would have to serve all the 19650-2:2018 (clause 5.1.7c), which has
transport and other sectors. Uniclass 2015
other tables, e.g. classifying properties for been adopted in Australia.27 When we
is current (most tables were updated in
‘Products’ and ‘Activities’. The properties began this work, we thought that it might
January 2020) and dynamic updates are
assigned by BIM tools (geometric and only be used by NBS. But now we see the
regular, as the NBS team liaises with users, otherwise) would all be classified, facilitating classification system being adopted very
which is important to organizations such digital searching for compliant proprietary much more widely, including in Australia.
as TfNSW and VDAS. The tables in Uniclass objects, or against attributes of interest The tables have been copied thousands
2015 are as coherent as they can be. such as flammability. Work on this table has of times worldwide. The adoption and
For example, ‘Complexes’, ‘Entities’, commenced. Proposed tables beyond the implementation of Uniclass 2015 will
‘Activities’ and ‘Spaces’ all use the ISO include ‘Districts’ (or ‘Precincts’) and expand into the future.
same basic classification – hence Co 45, ‘Regions’ (both in draft). These would allow
‘Residential complexes’; En 45, ‘Residential Uniclass 2015 to be used to support Smart
entities’; Ac 45, ‘Residential activities’; Cities initiatives.26 John is lecturer at the University of
and SL 45, ‘Residential spaces’. Finally, there South Australia and, while working
is plenty of room within each of the tables Where users insist on retaining an existing at NBS in the UK, was instrumental
for future expansion as required by industry classification table or system but others in the development of Uniclass 2015.
for current and future needs. The ‘Products’ in a project are using Uniclass 2015, then He was also on the Working Group
table, if it was full, could classify 108 objects, two-way mapping will be needed. For the for ISO 12006-2:2015.
although it currently classifies around 6800. purposes of BIM, this digital management

26
The Smart Cities Council ANZ is at: 27
AS ISO 19650.2:2019: ‘Organization and digitization of
https://anz.smartcitiescouncil.com. information about buildings and civil engineering works,
including building information modelling (BIM) – Information
management using building information modelling –
Delivery phase of the assets’, Standards Australia.

34 National BIM Report 2020


BIM beyond the labels
As a term, BIM is now well embedded in the vocabulary of the majority of people
Mike Turpin working in the construction industry, but what does it mean?
BIM Consultant
and Director,
When we talk about BIM, we are talking In more general terms, BIM is a label. It is an the cost and waste reduction targets of
Innovating Futures about building information modelling, insignia that we use to more easily define the the Government Construction Strategy
building information models or ‘better digital transformation now widely spreading or providing 3D model visualizations for
information management’ – or perhaps a its way through the construction industry like stakeholder engagement and improved
variety of other suitable explanations for concrete being slowly poured into a slab. coordination. These aims and ambitions
this acronym. Most of the time when we are Like the concrete making its way inch by inch are the drivers for change, and should be
talking about BIM, we’re more focused on (or should that be millimetre by millimetre?) at the forefront of the conversation – rather
the ‘I’ than the ‘B’ or the ‘M’: we are really across the formwork, it needs some structure than masked by the ever-changing label
talking about BIM as the improved use and and guidance to develop into the right shape. that we hang them on.
exchange of information across the ‘design’, Maybe even some assistance along the way, Does it matter that one definition of BIM is
‘build’ and ‘operate’ phases of a project. making sure that it gets into all of those different to another? Does it matter that one
But is this understanding as well embedded difficult corners for a smooth and consistent journey takes a different road to another?
as the acronym itself? finish. However, sometimes when we use As long as the collective industry is moving
labels such as BIM we end up losing focus forward towards that destination, we can
on what truly matters – and that is the end reflect on the positives of that success. We
result. That may mean meeting the handover can move our energy away from debating
aspirations of the building operator, achieving terminology and keep the vehicle moving.

Above: BIM needs structure and guidance - like concrete being poured into a slab.

Sometimes when we use labels such as BIM


we end up losing focus on what truly matters –
and that is the end result.

36 National BIM Report 2020 The definitive industry update 37


Below: CDBB: UK Digital initiative roadmap Below: Construction 2025. One potential outcome of BIM
www.cdbb.cam.ac.uk/DFTG/DFTGRoadmap is to help achieve the targets set out in the Government’s Strategy.

Lower costs Faster delivery

33% 50%
reduction in the initial reduction in the overall
cost of construction and time, from inception to
the whole life cost of completion, for new build
built assets and refurbished assets

Lower Improvement
emissions in exports

50% 50%
reduction in greenhouse reduction in trade gap between
gas emissions in the built total exports and total imports
environment for construction products and
materials

During the past ten or more years of CDBB are currently defining the direction Whilst we are still on this road to the Whatever the term BIM means BIM can be the foundation that enables How can your adoption of BIM be a part
the UK’s digital transformation journey, of the UK Digital Twin initiative and have future of our industry, it is my opinion (or whatever a person understands us to build a tower towards far greater of meeting these and other critical parts of
we have seen the many evolving facets of published the roadmap for its development that we need to refine our outputs – from it to mean), we expect BIM to meet outcomes and opportunities, but only our future? Alongside all of this, 2020 has
BIM. These include: the transition of design (as above). focusing on what we can do to focusing three key criteria. When reviewing if it is solid, complete and without defects, seen the tragic global pandemic which is
from 2D CAD drawings to 3D models; the on what we should do. We should be anything you’re doing, ask yourself before we begin to load too much on top COVID-19, and that has had an unprecedented
progression of standards from BS to PAS, Alongside all of this, we must still consider reflecting on our own selves, our own team, whether it delivers: of it. That being said, we should now be impact on every aspect of life as we know it.
and then to the International ISO; the the high-level reason why we and the or our own company’s reasons for BIM, considering the design for these future Perhaps now more than ever, we need to
introduction of COBie, and the resulting industry have adopted BIM in the first place and how it provides an outcome for us. plans and looking at all possible options push forward and deliver more; can we as
attention to data for operation; and (who – and that is to realize the benefits and That could be an increase in quality, an BETTER DECISIONS to help steer our future development in an industry use the tools that we have to
can forget?) the widespread adoption of value that its successful implementation increase in efficiency, a reduction in cost, the direction that best meets our vision achieve prosperity from catastrophe?
can deliver. In fact, we must remember that
clash detection, and the many dimensions
(4D, 5D, etc.) of BIM implemented during this was the UK Government’s driver for
more project wins or a whole host of other
goals. It’s these goals and our personal
BETTER THINKING and goals. Undoubtedly, our future will
change in ways that we could never have Mike is Director and Lead Consultant
construction. All of these identities of BIM BIM from day one: to deliver value from ambition to reach them which will ultimately predicted, and we will have to be able for Innovating Futures, a UK-based BIM
are very different, but in each case and on the cost savings and efficiencies that BIM make a success of BIM for us, our teams BETTER OUTCOMES to flex and adapt to this whilst still moving and digital construction consultancy.
each project, they are equally important can (and has) delivered on public sector and our organizations – and the wider forward as an industry. We are already Alongside this, Mike is an avid supporter
to the stakeholders who benefit from them. projects. More often now, we are seeing the industry will benefit from this. As the seeing sustainability and climate change of UK-based BIM initiatives to expand
Like eggplants and aubergines or chips and private sector following the Government’s saying goes, sometimes you have to be soar higher up the national and global the adoption of BIM, working with the
fries, these things are one and the same lead, with owners and operators of assets selfish to be selfless. agendas. We are seeing the continual CDBB International Team and the UK
to the majority of the population. As we across the country looking to BIM to demand for more housing, better social BIM Alliance Communities group.
take the next steps on the UK’s journey improve their existing processes, and help care and increased infrastructure capacity.
towards digital maturity, a traditional and them to drive better outcomes from the
notoriously analogue industry is about to assets which are handed over to them. It is
see the next phase of these discussions: the reversal of leadership throughout this
the ‘digital twin’. change (from designers across to owners
and operators) which will have the biggest
effect, and which should in turn distil the Whilst we are still on this road to the future of our industry,
essence of BIM down into a product which
will provide a wide range of positive results.
it is my opinion that we need to refine our outputs – from
focusing on what we can do to focusing on what we should do.

38 National BIM Report 2020 The definitive industry update 39


The Old Post Office
St Nicholas Street
Newcastle upon Tyne
NE1 1RH

Follow us on Twitter
@ theNBS

For enquiries about NBS


T 0345 456 9594
E info@theNBS.com
W theNBS.com

You might also like