Software project management

Project Cost Estimation

Group members:
Aafaq ali
F2109027075
Zeenat Rafiq
F2019027078
Mishaal hajra
F2019027048
Sultan Umar Cheema
F2019027086

Submitted To:
Prof.atif iqbal

University of management and technology


Units/Hou Cost/Unit Subtotals WBS % of
rs Total total
1. Location 750$ 10%
Research 50 100$ 150$
Floor Plan Layout 3 200$ 600$
2. Design 370$ 10%
Architecture 2 150$ 300$
Logo 1 70$ 70$
3. Renovation 3880$ 40%
Flooring 10 100$ 1000$
Walls 5 70$ 350$
Painting 8 50$ 400$
Electrical 8 60$ 420$
Plumbing 6 60$ 360$
Furniture 9 150$ 1350$
Finished 3880$
4. Food & Hospitality 1550$ 20%
Food Preparation 20 100$ 200$
Arrangements for Menu 5 100$ 500$
Product Selection 5 50$ 250$
Supplies 4 150$ 600$
5. Licenses and 1000$ 15%
Permits
Business Permits 3 200$ 600$
Health and Safety Authority 2 200$ 400$
Permits
6. Advertisement 150$ 5%
Commercial ads 1 50$ 50$
Banners 1 55$ 55$
Online Ads 45$ 45$

Total Project Cost Estimate $7700