National Oil Corporation

Project of development the Oil Clinic in Tripoli


Construction of X-ray and emergency building
PROGRESS PAYMENT (NO.2) FOR COMPLETED WORKS UNTIL 13.06.2021
The executing Part : Elengaz Al Tam company for contracting and real estate investment

Persentage of item
no Discription of Works Unit/M Item Amount Percentage of work completed Amount LYD
from total value
Previous Current Total
Ground Floor
First : Preliminary works for raft foundation

Preliminary works below the reinforcement concrete include backfilling, leveling and
1 compaction,and the item including pouring lean concrete below the foundation and also % 10% 634,920.00 100% 0% 100% 634,920.00
includes external building works for the necessity of raft foundation concrete boundaries

Second: Raft Foundation work

supplying and casting of reinforced concrete of grade C30, the necessary for raft foundation,
2 including steel reinforcement and additional materials necessary to reduce permeability and all % 23% 1,460,316.00 0% 100% 100% 1,460,316.00
that is necessary to work according to the drawings and standard specifications

Third: Cloumns work

supplying and casting reinforced concrete of grade C-30 for Cloumns including addition of
3 suitable plasticizer cas per manufacturer's recommendation and reinforcing steel according to % 10% 634,920.00 0% 0% 0% 0.00
the drawings and specifications.

Fourthly: Building works

Supplying and constructing of hollow concrete bricks (MCU) for interior and exterior walls,
4 % 6% 380,952.00 0% 0% 0% 0.00
according to drawings, designs and instructions of the supervising engineer

Fifthly: Slab works

supplying and casting reinforced concrete of grade C-30 for Slab including addition of suitable
5 plasticizer cas per manufacturer's recommendation and reinforcing steel according to the % 15% 952,380.00 0% 0% 0% 0.00
drawings and specifications.

Sixthly: Establishment work for electricity and plumbing

Earth line (grounding) and establishing the necessary basics for electrical and sanitary works
6 according to the principles of workmanship, technical specifications and instructions of the % 2% 126,984.00 0% 0% 0% 0.00
supervising engineer

First Floor
Seventh: Cloumns work

Supplying and casting reinforced concrete of grade C-30 for Cloumns including addition of
7.1 suitable plasticizer as per manufacturer's recommendation and reinforcing steel according to the % 6% 380,952.00 0% 0% 0% 0.00
drawings and specifications.

1 of 2
National Oil Corporation
Project of development the Oil Clinic in Tripoli
Construction of X-ray and emergency building
PROGRESS PAYMENT (NO.2) FOR COMPLETED WORKS UNTIL 13.06.2021
The executing Part : Elengaz Al Tam company for contracting and real estate investment
Eighth: Building works

Supplying and constructing of hollow concrete bricks (MCU) for interior and exterior walls,
8.1 % 6% 380,952.00 0% 0% 0% 0.00
according to drawings, designs and instructions of the supervising engineer

Ninth: Slab works


supplying and casting reinforced concrete of grade C-30 for Slab including addition of suitable
9.1 plasticizer cas per manufacturer's recommendation and reinforcing steel according to the % 9% 571,428.00 0% 0% 0% 0.00
drawings and specifications.
Tenth: Establishment work for electricity and plumbing

Establishing the necessary basics for electrical and sanitary works according to the principles of
10.1 % 2% 126,984.00 0% 0% 0% 0.00
workmanship, technical specifications and instructions of the supervising engineer

Eleventh: Roof insulation


Supplying and making a insulation two layer for roofs (Sheet Membren) from modified bitumen
strips from an approved sample and conforming to the technical conditions and affixed
11.1 according to the specifications after cleaning the surface well and making a skirting on the % 8% 507,936.00 0% 0% 0% 0.00
parapet and all that is needed to work is according to specifications, workmanship assets and
instructions of the supervising engineer

Supplying and casting concrete of rainwater slopes on surfaces and the price includes making
11.2 the necessary inclines and all that is needed to work is according to specifications, workmanship % 3% 190,476.00 0% 0% 0% 0.00
assets and instructions of the supervising engineer

Total value of Completed works up to date 2,095,236.000


Total value of previous Completed works 0.000
Total value of Completed works for the Current Payment 2,095,236.000

Submitted by Second Party Sub-contractor Approved by First Party CONTRACTOR


Elengaz Al-tam Co. General Construction Company Mest Group
Project Manager Project Manager
Name Name
Date Date
Signature Signature

2 of 2