QUARTERLY PROGRESS REPORT FOR THE FIRST QUARTER FOR CALANDER YEAR 2021
Department/Cadre Telecommunication
1. Minimizing detention to trains on 1. An estimate of underground 1. No TLA staff is available for the
account of PLC due to overhead cable has already been efficient maintenance of Overhead
lines faults forwarded to HQs Office, LHR Lines with this office. Moreover,
2. Restoration of Control for approval. Moreover, HQs outside interference is causing
Communication system over the office has already been misc cutting of overhead lines.
stations requested for TLA staff for the 2. Same as 1.
3. Efficient maintenance of Telecom maintenance of Overhead Lines 3. Staff available is below sanctioned
System i.e. Ufone, VHF, Public till the replacement of overhead strength so facing difficulty in
Addressing System, Solar Panel wires with underground cable. maintaining the installed system.
Quarter - I installed over stations 2. Same as 1.
4. Provision of 50 GSM Sets, 500 3. Telecom staff available is
KG SWG Wires and 70 Telephone carrying out maintenance on
Sets for Stations, DS Office & reception of complaints from
control/ block lines stations and control office, DS
Office etc.
4. Tender case has been finalized
and the material supplied by the
contractor has been received by
FOTs/PSC&KDA.
(Muhammad Nasir) (Saad Faraz)
Divisional Superintendent Divisional Assistant Telecom Engineer
Pakistan Railways, Peshawar Pakistan Railways, Peshawar