You are on page 1of 12

COSTRUCTION PLANNING AND

CONTROL

1 MW SOLAR POWER
PLANT INSTALLATION PROJECT SCHEDULING AND TRACKING

Presented By: Ajay Kumar Singh


Atul Raj
Contents
1. WBS
2. Gantt Chart
3. CPM Techniques
4. Crashing
WBS
1 MW SOLAR
POWER PLANT
INSTALLATION

PROJECT PRE- POST


CONSTRUCTION INSPECTIONS
MANG. CONSTRUCTION CONSTRUCTION

SITE SURVEY
ASSEMBLING CLOSEOUT
DOCUMENTATION
CONTRACT
INITIATION

PERMITS
ELECTRICAL
DESIGN SYSTEM
PACKAGE INSTALLATION
PRODUCTS DATA
PLANNING SHEETS
HAND OVER
FINAL WORK
PROCUREMENT PANEL TESTING INSPECTION
DURATION
ACTIVITY REPRESENTATION IPA (DAYS)
A - 10
Site Survey
B A 15
Area Cleaning
C B 90
Procurement
D B 40
Excavation
E D 40
Foundation
F E 60
Erection
G C 60
Assembling
Electric System H F,G 90
Installation
Installation of I F,G 45
Control System
J I,H 15
Inspection & Testing
K J 15
Grid Synchronisation
Gantt Chart
CPM Technique
Crashing
∆d= ∆c=
Activity IPA Nd Nc Cd Cc (Nd-Cd) (Cc-Nc) ∆c/∆d
(DAYS) (Rs.) (DAYS) (Rs)
A - 10 40K 9 45K 1 5K 5K
B A 15 125K 13 130K 2 5K 2.5K
C B 90 8000K 88 8100K 2 100K 50K
D B 40 500K 39 510K 1 10K 10K
E D 40 1000K 38 1050K 2 50K 25K
F E 60 500K 59 505K 1 5K 5K
G C 60 500K 58 515K 2 15K 7.5K
H F,G 90 1500K 89 1525K 1 25K 25K
I F,G 45 4000K 44 4050K 1 50K 50K
J I,H 15 200K 13 210K 2 10K 5K
K J 15 1000K 14 1100K 1 100K 100K
Total Direct Cost= 1,73,65,000 \-

Overheads=25000/day

Total indirect cost= 25000*295= 7375000 \-

Total Cost= DC+IDC = 2,47,40,000 \-

Step 1: Crash B by 2 days

TC=(17365K+5K)+(293*25K)= 2,46,95,000 \-

Step 2: Crash A by 1 day

TC=(17370K+5K)+(292*25K)= 2,46,75,000\-

Step 3: Crash J by 2 days

TC=(17375K+10K)+(290*25K)= 2,46,35,000\-
Step 4: Crash G by 2 days

TC=(17385K+15K)+(288*25K)= 2,46,00,000 \-

Step 5: Crash H by 1 day

TC=(17400K+25K)+(287*25K)= 2,46,00,000\-

Step 6: Crash C by 1 day

TC=(17425K+50K)+(286*25K)=2,46,25,000 \-

Optimum Cost= 2,46,00,000 \-


Optimum Duration= 287 days

You might also like