COVER STORY
Two pipelines have been installed under the
i + using Horizontal Directional
Drilling technology to minimise surface
disruption. The under-river crossing conquered
the major challenge of providing critical
infrastructure beneath ecologically sensi
areas as part of the southeast Queensland
Water Grid.
Chechen ta eetHORIZONTAL DIRECTIONAL DRILLING
southeast Queensland Water Grid has passed a major
[ cone with two pipelines installed under the Brisbane
River bed. Specialist drilling teams used Horizontal
Directional Drilling (HDD) co install ewo pipelines as part of
the largest water recycling project in the southern hemisphere
Both pipes were installed in early May, the frst of which was
installed in a single five-hour operation.
‘The pipes connect the Luggage Point Advanced Water ‘eat-
ment Plant near the mouth of the river into the Western Cor
ridor Recycled Water (WCRW) project. The major river erossing
follows the completion of two sections beneath Brisbane River
tributaries, Bulimba Creek and Aquarium Passage, whieh also
used the HDD method. These connect the WCRW project to
the Gibson Island Advanced Water Treatment Plant.
‘All HDD sections have been completed by the Eastern Pipeline
Alliance comprising AJ Lucas, Transfcld Services, GHD and
SunWater,
Faced with an almost kilometre-wide crossing ofthe Brisbane
River, project managers decided that the trenchless method of
HDD provided the best option of constructing a pipeline under
ecologically sensitive areas and critica infrastructure.
‘The optimised pipeline rou for the project crossed the Doboy
‘Wetlands, a habitat fora range of fish, crabs, birds, reptiles, am-
pphibians and other animals that lies atthe edge ofthe tidal and
freshwater areas ofthe Brisbane River mouth. HDD allowed the
pipeline o be installed beneath the ecologically sensitive welands
area without any impact to the surface.
‘Western Corridor Recycled Water chief executive officer Keith
Davies said dling 5m below the ground surface and 20m below
the river bed ensured minimal impact on the environment,
“Traditional trenching is inappropriace where waterways and
cnvironmentally sensitive areas ate concerned so we looked to
trenchless technology solutions and HDD was the most cost-
fete solution,” said Davies. We've brought in leading experts
from the US and New Zealand to oversee this operation.”
Crossing the river using HDD avoided the alternative of con-
structing 45m deep shalt at either side ofthe river and building
large platforms to support construction and storage, as well as
related safety issues
Davies continued: “The use of HDD isa positive one forthe
project. Apart from the environmental and added safety benefits,
HDD significantly reduced the cost fo tis section ofthe WCRW
project. It isa great example of using innovative technology to
reduce construction times, costs and environmental impacts.”
Project manager Shane Gaudin said HID was far more com
plicated than simple trenching and laying pipe in a trench, Ic
involved extensive skill and experience tobe succesful
He said HDD superintendents Gary Hunter and Stephen
Booth were two of the world’s leading authoritis with more
than 50 years’ combined global experience. Gaudin, Hunter and
Booth ail work for AJ Lucas, a principal partner of the Eastern
Pipeline Alliance.
“They havea wealth of down-hole’ drilling, formation and tool-
ing knowledge and are the ‘engine room’ ofthe whole operation,”
‘cepa fh pron ws ene a pp wall nh beng “breakover” structure
~ a series of cranes with roller cradles that train the pipe into a ruitable radius,
4
Pro: Che Lee oreo
WATER ENGINEERING AUSTRALIA JUNE 2008he pre geoal cont of ead
tcclon end one stightcecion a tga JefHORIZONTAL DIRECTIONAL DRILLING
‘The Bulimba Creek stringing area was « 1400m radius along which the pipeline was fabricated. Aquarium Passage and Brisbane
River stringing arcas were considerably more restricted and requited special roles and temporary structures like the barge
(pictured) to fabricate the pipelines around a 760m radius.
Gaudin ssid. “To achieve this crossing took weeks of thorough
planning on the challenging ste the right machinery and teams
who understood the importance of the operation.”
Before dling started, a series of vertical bores were dug to verify
the nature of the formation to be drilled. The geotechnical data
‘was incorporated into borehole profile design to selec the mast
appropriate formation ot layer through which to drill as well as to
also avoid any other obstacles such as power or ga lines
The results of the formation testing determined the design
depth forthe crossings at 20m below the bed of the river. On each
of the boreholes, che entry angle is berween 12° and 15* and the
exit angle is et at 6° so the profile generally consists of two bend
sections and one straight section at design depel,
Gaudin said precision in HIDD was paramoune and a prede-
termined process based on testing and experience was used for
the river crossing
Likewise, the quality of communication between the HDD
superintendent and the driller is essential. The drill cab from
where the drill ig is controlled is the centre ofthe operation and
effectively drives all other tasks. In cis type of formation, where
speed and accuracy are mitigation measures in themselves, there
is little room for error in execution,” Gaudin said. “Timing is
ctitical. The pilot hole took about two weeks 10 complete but
the pullback operation had to be completed within six hours.
This is because the material the eam was drilling through is soft
and here was a very real risk the hole could collapse, or the pipe
could get stuck in the pull-back operation,
‘The pilot hole (311.15mem), the only “steered” hole, was the
first hole to be drilled, The profile was replicated by having
special down-hole steering tools which register electromagnetic
signals calibrated to known positions on the surface to ensure
precision,
WATER ENGINEERING AUSTRALIA JUNE 2
Preo: Come Lee Phoroome
A all vies, the driller and steeter knew the exact position,
inclination, depth or length of the pilot hole, Once the pilothole
had been dried, reaming progressively opened up che piloc hole
to the desired borehole diameter
The hole was gradually enlarged by pulling backwards increas
ingly large reamers — cutting tools used in machinery co enlarge
holes. The diameter of the tunnel increased with each backward
pull and when che desited diameter ofthe tunnel was achieved,
string of pipes was attached to the reamer and pulled through
the tunnel co the other side of the waterway.
“The entice dling process is guided by a computer from the
surface. The computer allawed the driller to precisely locate the
drill bit and guide ic along the predetermined path.
WCRW project personnel said the accuracy of the technology
is extraordinary. The subterranean pipeline travels almost 1km
across the river before the deiler engineer steers the bore head to
within 200mm ofthe target on the other side ofthe river
Various types of formation, including clays, sand, gravel and
weathered rock sections, were encountered during the driling
‘The swelling nature ofthe clays presented considerable challenges
during the cours ofthe dling, but witha sound drilling pro-
zgram and correct rooling, any potential issues were overcome.
“To power the drilling and to lubricate the drilling head and
consolidate the walls of the eunnel, a drilling fuid was pumped
down che hole. This fluid is a mix of bentonite (environmentally
safe natural clay) and wate. Ic also carries mud out of the hole,
which is eaprured, filtered and recycled.
Four boreholes, each about 800m in length (Aquarium Passage,
Bulimba Creek and twin lines under the Brisbane River) were
requited for the crossings.
The crossings used three sections of pipe, one section 666mm
wide and the other two sections 760mm in diameter. The vari
arthe pipe.
ation in che diameters was calculated to allow for the different
flows and pressutes to which the underground pipeline will
subjected. The pipe supplier was Pacific Special Steel, a South
East Asia based company.
Pipe sections quvalent tothe fall length ofeach borehole was
laid our for up to Thm across vacant land.
The full length was then welded progressively. The continu
cous welding was undertaken by Energy Works, a New Zealand
company. The pipeline was welded ina single continuous length
asa ey risk mitigation measure in soft, unstable formation dr
ing isto minimise the borehole being let “open’. The fastest
insallation is achieved when the pipe sting i fully welded and
ready to pall chrough in a continuous manner. On the surface
the welded string of pipes is pulled onto rollers “training” the
Pipeline into a curve
“To give the pipeline the best opportunity to achieve its design
life, che joints between the pipes were welded and scaled, the
internal lining and external pipe coated and exthodic protection
applied to protect against corrosion. Hydro testing was carried
out prior co the drilling commencing.
‘While the welded pipeline is nor flexible in the rea se
the word, it has & minimum bending radius, which enables
pipeline to be pulled into the borehole. ‘The engineering team
designed the borehole and the stringing temporary structures 0
sno more than 80% of the yield stress on the pipe.
This ensured the pipeline was not damaged during installation
and, with good profile design, no residual stresses wil affect the
pipeline.
‘Gaudin said critical phase of che operation was when the
fabricated pipeline was pulled into the borehole through a "break
“The break overis a series of cranes with roller cra
the pipe into a suitable radius as itis pulled into the borehole.
Tes purpose isto ensuee che pipeline maximum yield stres is not
‘exceeded so that the pipeline does not sustain any permanent
deformation,” he said
f
“The engineering tam designed the borehole and the singing temporary structures to no moce chan 80% of the yield
‘rom: Ore Lise Peron’
‘The Bulimba Creck stringing area (right-of-way) wasa 1400m
radius along which the pipeline was fabricated. This was con-
sidered a gentle radius. The situation for Aquarium Passage and
the Brisbane River rightof-way arcas were considerably more
restricted and required special rollers and temporary structures to
fabricate che pipelines around a 760m radius. Regarded asa very
tight radius, ir correlates to about 80% yield stress.
Lack of available open space meant that a straight section be-
hind the borehole was not available and innovative alternatives,
‘were sought. One section was put together in curved sections to
‘obtain the required length and, for the Brisbane River section, the
ream built a small tunnel under a detour road to ensure there was
enough space to weld the string in a continuous section,
Project CEO Davies said a huge effort went int the planning,
and execution of the HDD operation.
‘Through the HDD operations, some 3km of steel piping
connects the WCRW project pipeline berween Pinkenba, 12km
northeast of Brisbane CBD, and Gibson Island, then from Gibson
Island under Lytton Road ar suburban Hemmant and through 10
Matacic, located 8km east of the CBD.
‘The pipeline is part of che $2.4 billion water supply network
that features more than 200km of large-diameter underground
pipe. Ie will carey purified reeycled water to power stations in-
dustry and agriculture, as well as to the region’s main reservoir,
Wivenhoe Dam, to supplement drinking supplis.
“The projet also involves three advanced water treatment plants
cight storage tanks and nine pumping stations
‘Ac che time of writing, more chan 150km of the pipeline has
been lai, the second stage of the Bundamba Advanced Water
“Treatment Plane nea Ipswich isall buccomplete and the advanced
water treatment plants at Luggage Point and Gibson Island ate
both about half way finished. The Luggage Point and the Gibson
Island treatment plants ate scheduled to come online by the end
of October.
‘When complete the projet will ave the capacity to deliver up
to 232MLid of purified reeyeled water to end users. @
WATER ENGINEERING AUSTRALIA JUNE 2008