You are on page 1of 2

TURBINE GENERATOR

NO Item Picture
1 Turbine
Turbine model: SST-300
Current status:
- Ongoing levelling on turbine
side refer to SITP point 3.4
- Ongoing lube oil flushing with
150 micron wiremesh

2 Inspection status
- Bluematching for foundation
bolt already accepted
- Levelling value for turbine will
be sent to ISGEC by today,
waiting for approval
TURBINE GENERATOR
NO Action Item
1 Refer to document IHEL AC PT Muria Sumba SITP point 3.26, erection works shall be
witnessed by Siemens Turbine Engineer
2 Target grout for foundation bolt by W3 June and shall require witness from Siemens
Turbine Engineer

You might also like