Boiler Hydrotest Rundown

Sat, 5 Jun 21
5:00 Start filling water
Finish filling water
Check water at top vent
8:00
Final check all equipment
Toolbox meeting
Start pressurizing as per
9:00
pressure chart

Time Pressure
Pressure Chart
180 0 0 159.5
160 20 53
140 30 53
Pressure (barG)

120 45 84
100 55 84 84 84
80 80 159.5
53
60 110 159.5
40 125 84
20 135 84
0 145
0 2 2
0 20 30 45 55 80 110 125 135 145
Minutes

Check list

Ensure surrounding area is clear & barricade installed


Ensure working permit & JSA is issued & valid
Ensure all temporary facility is installed correctly
Ensure PG installed at 3 points:
Pump
Main steam line
Steam drum
Ensure no airlock by open all vent
Ensure water already comes out from all vent
Ensure no leak at all points
Ensure only related personnel enter at boiler area
Ensure no one is inside furnace/boiler
Ensure communication protocol using HT
Ensure ERT standby