True
the project management plan by performing the activities b. False
included in it.
Many people consider project integration management the key *a. True
to overall project success. b. False
You can use the NPV function in Microsoft Access to calculate a. True
the NPV quickly. *b. False
Net present value and cash flow mean the same thing. a. True
*b. False
An annual discount factor is a multiplier for each year based on *a. True
the discount rate and year. b. False
Payback period is the amount of time it will take to recoup, in *a. True
the form of net cash inflows, the total dollars invested in a b. False
project.
The key deliverables section of the project management plan *a. True
should describe the quality expectations for the product b. False
deliverables.
All projects can benefit from using some type of project *a. True
management information system to coordinate and b. False
communicate project information.
The ____ step in the planning process is to tie the information a. first
technology strategic plan to the organization's overall strategic
plan.
a. first
b. second
c. third
d. fourth
In the ____ information technology planning stage, the analysis b. Business Area
outlines business processes that are central to achieving Analysis
strategic goals and helps determine which ones could most
benefit from information technology.
a. Project Planning
b. Business Area Analysis
c. Resource Allocation
d. Information Technology Strategy Planning
Research shows that ____ is the number one reason cited for c. supporting explicit
why organizations invest in information technology projects. business objectives
a. providing financial incentives
b. supporting implicit business objectives
c. supporting explicit business objectives
d. keeping abreast of technological advances
Author ____, who developed the concept of the strategic value b. Michael Porter
of competitive advantage, has written several books and
articles on strategic planning and competition.
a. James Bacon
b. Michael Porter
c. Robert Cooper
d. Carol Matlack
Projects that address ____ are much more likely to be c. broad organizational
successful because they will be important to the organization. needs
a. a balanced scorecard
b. a weighted scoring model
c. broad organizational needs
d. net present value
____ analysis is a method of calculating the expected net b. Net present value
monetary gain or loss from a project by discounting all
expected future cash inflows and outflows to the present point
in time.
a. Cost of capital
b. Net present value
c. Cash flow
d. Payback
In the mathematical formula for determining the NPV, the b. the last year of the
variable n is ____. cash flow
a. the year of the cash flow
b. the last year of the cash flow
c. the amount of cash flow each year
d. the discount rate
You can determine a project's ____ by finding what discount a. internal rate of
rate results in an NPV of zero for the project. return (IRR)
a. internal rate of return (IRR)
b. required rate of return
c. payback period
d. return on investment (ROI)
A(n) ____ is a document that formally recognizes the existence d. project charter
of a project and provides direction on the project's objectives
and management.
a. balanced scorecard
b. business case
c. net present value analysis
d. project charter
A(n) ____ is a document that describes the products or services b. statement of work
to be created by the project team.
a. contract
b. statement of work
c. project charter
d. business case
A(n) ____ is a document used to coordinate all project planning a. project management
documents and help guide a project's execution and control. plan
a. project management plan
b. statement of work
c. scope statement
d. contact
The ____ section of the project plan should describe the major c. project
project functions and activities and identify those individuals responsibilities
who are responsible for them.
a. organizational charts
b. other organizational or process-related information
c. project responsibilities
d. management objectives
The ____ section of the project management plan describes b. project controls
how to monitor project progress and handle changes.
a. management objectives
b. project controls
c. risk management
d. technical processes
The ____ section of the project management plan describes d. technical processes
specific methodologies a project might use and explains how
to document information.
a. management objectives
b. project controls
c. risk management
d. technical processes
A(n) ____ is a formal, documented process that describes when d. change control
and how official project documents may be changed. system
a. integrated change control
b. change request
c. performance report
d. change control system
____ ensures that the descriptions of the project's products are c. Configuration
correct and complete. management
a. CCB
b. Correction management
c. Configuration management
d. Product description management
____ tools track the execution of business process flows and a. BSM
expose how the state of supporting IT systems and resources
is impacting end-to-end business process performance in real
time.
a. BSM
b. CCB
c. CCA
d. BSC