Professional Documents
Culture Documents
2018.04.02 HBR II Progress Report Mar 2018
2018.04.02 HBR II Progress Report Mar 2018
Works
Progress Report
March 2018
GNHM/HYD/2018-19/HBR2/PR07
Restoration of Durbar Hall at University College for Women, Koti, Hyderabad Phase II
PROJECT TEAM
2. Dismantling Works
– Removal of oil base paint from the rectangular columns in Durbar hall
3. Conservation works
– consolidation of beam in the western opening at first floor balcony inside Durbar Hall
Restoration of Durbar Hall at University College for Women, Koti, Hyderabad Phase II
PREPARATORY WORKS: PREPARATION OF FINE LIME MORTAR
Storage of lime mortar in sealed air Sieving of lime using fine plastic Grinding of mortar in small
tight bags mesh grinder
Restoration of Durbar Hall at University College for Women, Koti, Hyderabad Phase II
PREPARATORY WORKS: ERECTION OF SCAFFOLDING
STAGES OF WORK 1 2
Erected Casurina
scaffolding on the
eastern side of front
facade
Restoration of Durbar Hall at University College for Women, Koti, Hyderabad Phase II ENTRANCE PORCH
DISMANTLING: OIL PAINT FROM RECTANGULAR COLUMNS
STAGES OF WORK BEFORE AFTER
The old layers of oil paint on
Manual scraping of the
the rectangular columns in
Durbar Hall had delaminated
paint layers was resulting
from the surface. in significant damage/loss
The lime art work too was of the weakened art
found to be delaminated in work.
places and with weakened After multiple trial and
binding in other area. The consultation with experts,
reason for this was because a team of skilled painters
the lime art work on the were identified to carry
column has been glued to the out the paint removal
surface after the base plaster cautiously using diluted
had been completed thus caustic soda solutions as
Work start date: 13.03.2018
resulting in inadequate chemical to ensure
Status: Completed
binding between the two minimum loss.
surfaces.
Work start date:09.03.2018 Old paint layer on the metal railing was removed Visible old wood and metal in railing after the removal of
Status: On-going carefully by scraping it off using heat gun. deteriorated paint layers
Restoration of Durbar Hall at University College for Women, Koti, Hyderabad Phase II DURBAR HALL
DISMANTLING : WOODEN CORNICE BELOW METAL RAILING
STAGES OF WORK →
Restoration of Durbar Hall at University College for Women, Koti, Hyderabad Phase II DURBAR HALL
CONSOLIDATION: RE-FIXING OF DAMAGED DOOR FRAMES
STAGES OF WORK → 1
The wooden door frames in
Entrance porch had developed
cracks due to heavy loading and 1
had signs of water ingress.
The intervention was to use most of
the old wood that was in a good
condition. The door frames on the
eastern and western side of the
2 3
Entrance porch were consolidated
using new wood only for the
segments that were severely Mortise and tenon joint
decayed. at the junction of the
The three central door frames in post and lintel
Work start date: 27.12.2017 entrance porch were reconstructed
Status: Completed 4
using new teakwood.
25.01.2018
2 3
Fixing of wooden door frame
was a scrupulous process
involving a team of skilled
carpenters. The lintel and the
base were fixed first and the
posts were cautiously inserted
into the mortise groove.
The area around the wooden
frame was then packed with
lime mortar.
Restoration of Durbar Hall at University College for Women, Koti, Hyderabad Phase II ENTRANCE PORCH
CONSOLIDATION: GROUTING USING TRADITIONAL MIX
STAGES OF WORK
Restoration of Durbar Hall at University College for Women, Koti, Hyderabad Phase II ENTRANCE PORCH & DURBAR HALL
CONSERVATION WORKS: POLISHING DOOR PANELS
STAGES OF WORK 2
Samples of different chemicals were tested on site to achieve the
desired colour and finish to match with the original finish on
doors and which is cost efficient as well.
A patch of Asian paints premium wood finish was applied on
wood and shellac mixed with colour pigments was applied on
other. The tests were done to ensure there is no visible
difference in the old and the new polish.
Both the polish gave equally good results but Shellac with
pigments was a more cost effective approach and was hence
approved.
After testing, 3 coats of polish were applied to the wood using
fine linen cloth.
Work start date: 14.03.2018
Status: On-going The panels and frames were then scrubbed using
sand paper to achieve a uniform surface.
3 4
Polish done using Shellac mixed with color pigments which gave the
desired finish as observed on the original wood.
Polished door panels
Restoration of Durbar Hall at University College for Women, Koti, Hyderabad Phase II ENTRANCE PORCH & DURBAR HALL
CONSOLIDATION: ART WORK IN ENTRANCE PORCH
STAGES OF WORK 1 2
Restoration of Durbar Hall at University College for Women, Koti, Hyderabad Phase II ENTRANCE PORCH
CONSOLIDATION: ART WORK IN RECTANGULAR COLUMN
STAGES OF WORK 1 2
The damaged/broken
parts of the column
bases were consolidated
using niru maal or fine
lime mortar 1:2 (1 lime :
2 fine sand).
Restoration of Durbar Hall at University College for Women, Koti, Hyderabad Phase II DURBAR HALL
CONSOLIDATION: REPAIR OF WOODEN BEAM IN OPENINGS
STAGES OF WORK 1 2
The wood in beam was in a fairly good condition but
the wooden battens below it were deteriorated due to
termite infestation. These were repaired in December
2017 by the carpenter’s team, the details of which have
been mentioned in the 2017 December report.
The base of the beam was further wrapped with
chicken wire mesh and packed with rough lime plaster.
Restoration of Durbar Hall at University College for Women, Koti, Hyderabad Phase II DURBAR HALL
ART CONSERVATION: CONSOLIDATION OF COMPRESSED PAPER CEILING PANELS
STAGES OF WORK 1 2
The damaged parts of the panels were consolidated by merging different damaged
pieces together to complete the pattern, using a mix of French chalk powder, kaolin
white and adhesive.
The missing panels were replaced with new digital prints in order to differentiate
between the original panels and the new intervention. The new intervention was taken
as a conservation measure as it is reversible and can be easily replaced or repaired in
future.
Restoration of Durbar Hall at University College for Women, Koti, Hyderabad Phase II DURBAR HALL