Customer : NTT GDCI Prepared by : Ivan Rudolf

PRO-MATRIX Project Title : JKT3 NEW CONSTRUCTION PROJECT

Duration : Oct-20 to Jun-21


Construction Schedule for Electrical Last Updated : 14-Oct-18

Progress Line : 30-Nov-20


Oct-2020 Nov-2020 Dec-2020 Jan-2021 Feb-2021 Mar-2021 Apr-2021 May-2021 Jun-2021
Plan Actual Progress
No Activity ### 11/10 18/10 25/10 1/11 8/11 15/11 22/11 29/11 6/12 13/12 20/12 27/12 3/1 10/1 17/1 24/1 31/1 7/2 14/2 21/2 28/2 7/3 14/3 21/3 28/3 4/4 11/4 18/4 25/4 2/5 9/5 16/5 23/5 30/5 6/6 13/6 20/6 27/6

Start Dur. Finish Start Dur. Finish %

1 Electrical Works 11-Oct-20 252 20-Jun-21

Level 1 - Construction (High Level Works)

Chiller Room D1L101 3-Oct-20 21 24/10/20


Hanger & support Installation 3-Oct-20 7 10-Oct-20
Power Cable Tray Installation 11-Oct-20 7 18-Oct-20
Lighting Channel Installation 19-Oct-20 4 23-Oct-20
Steel Conduit for Socket Outlet Installation 19-Oct-20 5 24-Oct-20

Genset Deck D1L1D01 10-Nov-20 16 26-Nov-20


Hanger & Suport Installation 10-Nov-20 3 13-Nov-20
Power Cable Tray Installation 14-Nov-20 7 21-Nov-20
Lighting Channel 22-Nov-20 4 26-Nov-20
Socket Outlet Installation 22-Nov-20 2 24-Nov-20

Power Corridor D1L101 11-Nov-20 30 11-Dec-20


Common Support Installation 18-Nov-20 14 2-Dec-20
Power Cable Tray Installation 23-Nov-20 12 5-Dec-20
Busduct 23-Nov-20 7 30-Nov-20
Lighting Channel 4-Dec-20 7 11-Dec-20
Socket Outlet Installation 4-Dec-20 7 11-Dec-20

MV Room D1L1A01 & MV Room D1L1B01 17-Nov-20 25 12-Dec-20


Hanger & Support Installation 17-Nov-20 5 22-Nov-20
Power Cable Tray Installation 22-Nov-20 20 12-Dec-20
Lighting Channel 17-Nov-20 4 21-Nov-20
Socket Outlet & Switch Installation 22-Nov-20 4 26-Nov-20

Corridor D1L101 20-Nov-20 30 22-Dec-20


Common Support Installation 20-Nov-20 18 8-Dec-20
Power Cable Tray Installation 1-Dec-20 7 8-Dec-20
Busduct 1-Dec-20 4 5-Dec-20
Lighting Channel 12-Dec-20 10 22-Dec-20
Socket Outlet Installation 12-Dec-20 10 22-Dec-20

Corridor D1L102 20-Nov-20 32 22-Dec-20


Common Support Installation 20-Nov-20 18 8-Dec-20
Power Cable Tray Installation 1-Dec-20 5 6-Dec-20
Busduct 1-Dec-20 4 5-Dec-20
Lighting Channel 12-Dec-20 10 22-Dec-20
Socket Outlet Installation 12-Dec-20 10 22-Dec-20

Corridor D1L103 & Fire Lift Lobby D1L101 20-Nov-20 31 21-Dec-20


Common Support Installation 20-Nov-20 14 4-Dec-20
Power Cable Tray Installation 1-Dec-20 12 13-Dec-20
Lighting Channel 14-Dec-20 7 21-Dec-20
Socket Outlet Installation 14-Dec-20 7 21-Dec-20

TX Room D1L1D01 & TX Room D1L1D02 25-Nov-20 9 4-Dec-20


Hanger & Support Installation 25-Nov-20 4 29-Nov-20
Power Cable Tray Installation 29-Nov-20 5 4-Dec-20
Lighting Channel 25-Nov-20 3 28-Nov-20
Socket Outlet Installation 29-Nov-20 1 30-Nov-20

LV Room D1L1A01 26-Nov-20 12 8-Dec-20


Hanger & Support Installation 26-Nov-20 5 1-Dec-20
Power Cable Tray Installation 1-Dec-20 7 8-Dec-20
Lighting Channel 26-Nov-20 4 30-Nov-20
Socket Outlet Installation 1-Dec-20 1 2-Dec-20

PDU Corridor D1L1A01 & PDU Corridor D1L1B01 27-Nov-20 17 14-Dec-20


Hanger & Support Installation 27-Nov-20 7 4-Dec-20
Power Cable Tray Installation 3-Dec-20 7 10-Dec-20
Busduct Installation 1-Dec-20 7 8-Dec-20
Lighting Channel 11-Dec-20 3 14-Dec-20
Socket Outlet Installation 11-Dec-20 3 14-Dec-20

UPS Room D1L1D01 & UPS Room D1L1D02 27-Nov-20 7 4-Dec-20


Hanger & Support Installation 27-Nov-20 4 1-Dec-20
Power Cable Tray Installation 1-Dec-20 3 4-Dec-20
Lighting Channel 27-Nov-20 2 29-Nov-20
Socket Outlet Installation 30-Nov-20 1 1-Dec-20

Battery Room D1L1D01 & Battery Room D1L1D02 28-Nov-20 5 3-Dec-20


Hanger & Support Installation 28-Nov-20 4 2-Dec-20
Power Cable Tray Installation 2-Dec-20 1 3-Dec-20
Lighting Channel 28-Nov-20 2 30-Nov-20
Socket Outlet Installation 1-Dec-20 1 2-Dec-20

Store D1L1D02 29-Nov-20 4 3-Dec-20


Hanger & Support Installation 29-Nov-20 4 3-Dec-20
Lighting Channel 29-Nov-20 2 1-Dec-20
Socket Outlet Installation 2-Dec-20 1 3-Dec-20

PAHU Room D1L1D01 4-Dec-20 4 8-Dec-20


Hanger & Support Installation 4-Dec-20 2 6-Dec-20
Lighting Channel 4-Dec-20 2 6-Dec-20
Socket Outlet & Switch Installation 7-Dec-20 1 8-Dec-20

MCC Room D1L1D01 12-Dec-20 13 25-Dec-20


Hanger & Support Installation 12-Dec-20 5 17-Dec-20
Busduct Installation 18-Dec-20 5 23-Dec-20
Power Cable Tray Installation 18-Dec-20 7 25-Dec-20
Lighting Channel 12-Dec-20 2 14-Dec-20
Socket Outlet & Switch Installation 15-Dec-20 2 17-Dec-20

MDF Room D1L1A01 & MDF Room D1L1B01 18-Dec-20 7 25-Dec-20


Hanger & Support Installation 18-Dec-20 3 20-Dec-20
Power Cable Tray Installation 21-Dec-20 3 23-Dec-20
Customer : NTT GDCI Prepared by : Ivan Rudolf

PRO-MATRIX Project Title : JKT3 NEW CONSTRUCTION PROJECT

Duration : Oct-20 to Jun-21


Construction Schedule for Electrical Last Updated : 14-Oct-18

Progress Line : 30-Nov-20


Oct-2020 Nov-2020 Dec-2020 Jan-2021 Feb-2021 Mar-2021 Apr-2021 May-2021 Jun-2021
Plan Actual Progress
No Activity ### 11/10 18/10 25/10 1/11 8/11 15/11 22/11 29/11 6/12 13/12 20/12 27/12 3/1 10/1 17/1 24/1 31/1 7/2 14/2 21/2 28/2 7/3 14/3 21/3 28/3 4/4 11/4 18/4 25/4 2/5 9/5 16/5 23/5 30/5 6/6 13/6 20/6 27/6

Start Dur. Finish Start Dur. Finish %


Lighting Channel 24-Dec-20 1 24-Dec-20
Socket Outlet & Switch Installation 25-Dec-20 1 25-Dec-20

Cooling Corridor D1L101 2-Dec-20 16 18-Dec-20


Common Support Installation 2-Dec-20 7 9-Dec-20
Power Cable Tray Installation 6-Dec-20 7 13-Dec-20
Lighting Channel 14-Dec-20 4 18-Dec-20
Socket Outlet Installation 14-Dec-20 2 16-Dec-20

Cooling Corridor D1L102 10-Dec-20 16 26-Dec-20


Common Support Installation 10-Dec-20 7 17-Dec-20
Power Cable Tray Installation 14-Dec-20 7 21-Dec-20
Lighting Channel 22-Dec-20 4 26-Dec-20
Socket Outlet Installation 22-Dec-20 2 24-Dec-20

Cooling Corridor D1L103 18-Dec-20 16 3-Jan-21


Common Support Installation 18-Dec-20 7 25-Dec-20
Power Cable Tray Installation 22-Dec-20 7 29-Dec-20
Lighting Channel 30-Dec-20 4 3-Jan-21
Socket Outlet Installation 30-Dec-20 2 1-Jan-21

LEGEND Plan Actual % Complete Actual Beyond Plan % Complete Beyond Plan