Preventive Maintenance Programs


GAS ENGINE & COMPRESSOR AJAX, SUPERIOR & COOPER BESSEMER
BAKER HUGHES, A GE COMPANY (BHGE)

1st Year 2nd Year 3rd Year 4th Year 5th Year

COOPER BESSEMER TYPE GMVH-6

Maintenance Program : 5K 10 K 5K 20 K 5K 10 K 5K 40 K
Total Running Hours : 5.000 10.000 15.000 20.000 25.000 30.000 35.000 40.000

Remarks :

: Routine Maintenance every 500 Hours

: Sparepart Order for Preventive Maintenance (PM) 5K : Schedule of Preventive Maintenance (PM) 5K

: Sparepart Order for Preventive Maintenance (PM) 10K : Schedule of Preventive Maintenance (PM) 10K

: Sparepart Order for Preventive Maintenance (PM) 20K : Schedule of Top Overhaul (TOH) 20K

: Sparepart Order for Preventive Maintenance (PM) 40K : Schedule of General Overhaul (GOH) 40K

0 5000 H 10000 H 15000 H 20000 H 25000 H 30000 H 35000 H 40000 H

th th th th th th th th
18 week 44 week 77 week 99 week 136 week 162 week 196 week 214 week
th th th th th th th th
2900 hour 7300 hour 12900 hour 16600 hour 22900 hour 27300 hour 32900 hour 35900 hour

PM 5K PM 10K PM 5K PM 20K PM 5K PM 10K PM 5K PM 40K


30th week 60th week 89th week 119th week 149th week 178th week 208th week 238th week

: Sparepart Order for Preventive Maintenance (PM) : Schedule of Top Overhaul (TOH) 20K

: Schedule of Preventive Maintenance (PM) 5K : Schedule of General Overhaul (GOH) 40K

: Schedule of Preventive Maintenance (PM) 10K