Professional Documents
Culture Documents
Lumber
3
1 bd-ft = 1 ft x 1 ft x 1 in thick = 144 in
length(in ) Area(in 2 )
Volume of a lumber member (bd − ft ) =
144 in 3 / bd − ft
Rebar:
dimension - concrete clearance
Number of rebars = +1
Rebar spacing
Rebar length = dimension of cross section – concrete clearances
Material Unit
Asphalt tons
3
Concrete yd
2
Concrete forms SFCA (ft of contact area)
2 2
flooring ft or yd
3
lumber bd-ft (1 bd-ft = 144 in )
Masonry (brick) brick
nails lbs
paint gallon
pipe ft
plywood Sheet (4 ft x 8 ft)
Reinforcing rebars lbs
3
soil yd
Structural steel lbs
Weight of Structural steel within designation:
Example for W18x108 section, the weight is 108 lbs/lft
o For Paint: always round up to the next gallon… Do not use partial
gallon.
o For roofs: Gable roofs and hip roofs are assumed to use the same
amount of plywood. Do not use partial sheets of plywood.
o Concrete forming SFCA: No forms underneath are needed if
structure is built on grade directly. Also there is no need for forms
for the top surface. Include end closures for walls.
Perimeter of structures
OP = 2(Xo +Yo)
IP = OP + 4 x (2 x (- t))
MP = OP + 4 x (2 x (-t/2))
pessimistic − optimistic
2
Variance =
6
CV = BCWP – ACWP = EV – AC (CV>0 good saving)
SV = BCWP – BCWS = EV – PV (SV>0 schedule advantage)
BCWP EV
CPI = = (CPI>1.0 good saving)
ACWP AC
BCWP EV
SPI = = (SPI>1.0 schedule advantage)
BCWS PV
ETC = (BAC – BCWP)/CPI
EAC = ACWP + ETC
Part II – Means and Methods
Permanent Loads:
D = Dead Load: weight of the permanent construction in-place at the particular
time in the construction sequence. It includes non-structural loads such as
cladding, partitions, ceilings and railings.
L = Live Load: load produced by the use or occupation of a structure that is under
construction.
Construction Loads:
CD = Weight of temporary Structures
CFML = Fixed Material Load
CVML = Variable Material Load
CP = Personnel and Equipment loads
CH = Horizontal construction load
ASCE 37-14
Chemistry Coefficient
Concrete Coefficient
0.5 1 + ( w /145)
Lateral pressure on Formwork:
Minimum pressure of 600 pounds per square foot, but in no case greater than
p = w x h.
Pc
Maximum pressure in formwork is reached at depth d: d =
w
75̊ 0.966
60̊ 0.866
45̊ 0.707
35̊ 0.574
30̊ 0.500
Circular Footings
𝑞𝑢𝑙𝑡 = 1.3𝐶𝑁𝑐 + 𝛾𝐷𝑁𝑞 + 0.6𝛾𝑅𝑁𝛾
R = Radius of the Footing
Revised
Effect of Ground Water on Ultimate Bearing Capacity (Depth)
Type Of Relationship of Ultimate Bearing Capacity
Footing Depths of
footing (D) and
water (d)
OG Continuous D=0 𝑞𝑢𝑙𝑡 = 𝑐𝑁𝑐 + [𝛾𝑠𝑢𝑏 + 𝐹 𝛾𝑇 − 𝛾𝑠𝑢𝑏) 0.5𝐵𝑁𝛾
Surface Footing Footing
d≤D 𝑞𝑢𝑙𝑡 = 𝑐𝑁𝑐 + [𝛾𝑠𝑢𝑏 𝐷 + 𝛾𝑇 − 𝛾𝑠𝑢𝑏) 𝑑 𝑁𝑞 + 0.5𝛾𝑠𝑢𝑏 𝐵𝑁𝛾
d≤D B
qult =cNc 1+0.3 + γsub D+ γT −γsub d N +0.4γsub BNγ
L q
D < d ≤ (D+d0) 𝐵
𝑞𝑢𝑙𝑡 = 𝑐𝑁𝑐 (1 + 0.3 ) + 𝛾𝑇 𝐷𝑁𝑞 + [𝛾𝑠𝑢𝑏
𝐿
OG + 𝐹 𝛾𝑇 − 𝛾𝑠𝑢𝑏 ]0.4𝐵𝑁𝛾
Circular D=0 𝑞𝑢𝑙𝑡 = 1.3𝑐𝑁𝑐 + [𝛾𝑠𝑢𝑏 + 𝐹 𝛾𝑇 − 𝛾𝑠𝑢𝑏) 0.6𝑅𝑁𝛾
Footing
D
d≤D qult = 1.3cNc + γsub D+ γT −γsub d Nq +0.6γsub RNγ
HORIZONTAL CURVES
T = R tan
2
Arc Length (La):
100
La = R = = R(radians)
180 D
5729.58
D= (Arc Basis)
R
50
Sin (D ) = (Chord Basis)
2 R
1
For any sliver within a horizontal
curve:
2
Stationing: Sta. PT = Sta. PC + L
Sta. PC = Sta. PI - T
3
VERTICAL CURVES
x 2 (g 2 − g1 ) 4m( x 2 )
2
x d = Vertical distance from any point
d= = = m on the curve to tangent grade.
L/2
2
2L L
x is the distance from BVC if point is left of VPI and from EVC if the point is on the
right of VPI.
g 1 ( L)
DL = DL or DH = Distance to low or high point from BVC of the curve
g1 − g 2
100(YH − YP )
D=
g1 − g 2
x (g 2 − g 1 )
S = g1 + = g1 + r(x ) S = slope of the tangent to the curve at any point on the curve
L
4
Vertical curve through a fixed point:
Fixed point in space
g1 offset
g2
VPI
2 offset A(offset) offset 2 A
L = 2 A + +4 +
g − g 2
1
g − g 1
g − g 2
(stations)
1 2
5
TRAFFIC
Number of vehicles
q = Flow ( veh / hr ) =
Time Interval
Spacing 1
h = Headway (sec/ veh) = =
Speed Flow rate
V
PHF = V15 = maximum 15 minute-count
4 V15
1 N
ut = ui Time Mean Speed
N i =1
n
us = n
1
i =1 u i
Space Mean Speed
6
Materials 2 Equations
Part VIII - Site Development
Earthwork
Calculate earth volumes using:
( A1 + A2 ) 1yd 3
Average End Area Method: Volume ( yd ) = L
3
2 27 ft 3
( A1 + 4 Am + A2 ) 1 yd 3
Prismoidal Method: Volume ( yd ) = L
3
6 27 ft 3
Conversion unit :1 yd 3 = 27 ft 3
% Swell BCY
Volume: LCY = 1 + BCY =
100 LF
% Shrinkage
Volume: CCY = 1 − BCY
100
If soil unit weights are given: DL (loose), DB (bank), DC (compacted)
( DB − DL)
Swell % = 100%
DL
( DC − DB)
Shrinkage % = 100%
DC
Soil Piles
1/3
(h / 3)d 2 7.64V
Conical Pile: V ( Loose) = Base diameter: d =
4 tan
d
Cone height h = tan
2
0.5
1 4V
Triangular Pile: V ( Loose) = b h L Base b =
2 L tan
b
Height h= tan
2
Mass Haul Diagram Equations
Total Haul Distance = FHD + OHD
Limit of Economic Haul (LEH) = FHD + Economic OHD
Cost of Borrow
Economic OHD =
Cost of Overhaul
Haul (CY.Sta.) = Haul Volume (CY) x AHD (Sta.)
Overhaul (CY.Sta.) = OH Volume (CY) x (AOHD - FHD)
Differential Levelling:
HI = BS + Hub Elev. Back Sight
TP = HI – FS Fore Sight
Part VIII - Site Development - Safety
Excavation:
Type A are cohesive soils with an unconfined, compressive strength of 1.5 tsf or greater.
Type B are cohesive soil with an unconfined compressive strength greater than 0.5 tsf but less
than 1.5 tsf
Type C are cohesive soil with an unconfined compressive strength of 0.5 tsf or less
Egress ladders must be provided every 25 ft and excavated materials must be placed no
closer than 2’ from the excavation
Fall Protection
Each employee on a walking/working surface with an unprotected side or edge which is 6 feet or
more above a lower level shall be protected from falling by the use of guardrail systems, safety
net systems, or personal fall arrest systems
For Steel erection, the trigger elevation for fall protection is 15 feet. For workers on scaffolds,
the trigger elevation for fall protection is 10 feet.
Guardrails
Scaffolding: Horizontal ties and braces are installed at intervals as shown below:
Incident Rate
Number of injuries/ il ln esses 200,000
IR =
Employees hours worked
Work Zone
Warning signs distances
W S2
For speed limits of 40 mph or less: L=
60
For speed limits of 45 mph or greater: L=WxS
The spacing between cones, tubular markers, vertical panels, drums, and barricades
should not exceed a distance in feet equal to 1.0 times the speed limit in mph
when used for taper channelization, and a distance in feet equal to 2.0 times the
speed limit in mph when used for tangent channelization.
Delineators can be cones, tubulars or drums.
Roadside Clear Zone Distances
Backslope
Foreslope
Drainage Channel