HANNIBAL FACILITY – SOUR GAS PROJECT

CONTRACT REFERENCE No : 3104764

SITE INSTRUCTION

Instruction No: PIR 492 Dated: 13TH OCTOBER 2008

This Instruction is issued with reference to: Hot Oil Modifications WP-SGP-13E/20/22L
– Stage 3

Description:
WP13E - modify the pipe work at the tie in point to enable turning the valve to its true
location because of the clash with existing pipe work
WP20 - move the North-South position 150mm to the west to avoid scaffolding.
Also have a clash with existing pipe work on a different isometric

Iso 00553 & 00554

For any clarification and to discuss details contact Keith Noble of WorleyParsons

PIRECO are advised that this Instruction may constitute a Variation Order in accordance
with General Conditions of Contract.
Pireco is to provide an estimate of resources required for this Work. The Work should
continue whilst the estimate is being prepared and approved.

Signed.............................................WorleyParsons Construction Manager


M. WELLS

Signed……………………………… PIRECO Project Manager Date


C. TURKI