Professional Documents
Culture Documents
2. Preliminary Design
2.1. Design appraisal
2.1.1. Safety
During Construction
Crane and additional mechanized equipment’s should be used for hauling, lifting and positioning timber
frames and large timber elements.
Brick layering needs to be done by qualified workers. Scaffolding need to be installed for working at
heights. Other measures for working on heights are to be set in place
Roofing needs to be installed considering the prevention measures for working on heights
During Use
Wood is particularly sensitive to moisture and is subject to cracks, so preliminary treatment with special
compounds and impregnations is required
As the brick will stay exposed engineered bricks are therefore suggested.
Structure is designed for a 60 min fire resistance.
Maintenance and Refurbishments
Easy to maintain, however due to height of some timber elements trained staff might be required, that
has a permit to work on heights.
Treatment against thermites and other insect might be periodically required.
Demolition
2.1.2. Economy
Costs will vary depending on type and strength of masonry used, timber frame shape, quantity of timber used or
timber type
2.1.3. Buildability
As the timber frames will come partially assembled it will be quite straight forward to be erected on site.
The other timber beams, joist or rafters should be easy to install and connect
Masonry layering should be done by qualified labours
2.1.4. Robustness
The timber frames are manufactured from glulam GL24h. Currently glulam is a material quite robust in some
cases being a viable alternative to steel.
Masonry is also a consider a robust material. There are many types of masonry with different compressive
strength properties. The robustness of the structure is influenced by the masonry block used
2.1.5. Durability
Again, the properties that glulam can achieve lately are quite amazing. Life spans of 100-150 years are by
manufacturers.
Masonry is already known as a durable material, with masonry building exceeding 200 years lifespan
Two solution are proposed based on the floor plan and section provided.
2.2. Proposal 1
2.2.1. Functional Framing
A timber frame as in the Figure 1 was considered. The same frame can be used for lower and upper floor of the
building to the symmetry, with the specification that additional concrete piers might need to be build as there is
at least a 5m difference in between the toe of the arch and the foundation of the structure especially on the left
side of the upper floor. Additionally, transfer beams are needed to connect the ridge point of the top frame to the
ridge point of the lower ground floor, and to support the roof in between the two ridge parts
This geometry was considered because of the aesthetical aspect that an arch can give, structural reliability
provided as a three-pin arch can withstand high loads over large spans (Holger Gross, Gross Produktion AB,
2013)
A preliminary sizing of the glulam elements was assessed as follows:
Glulam arch:
h =b ≃ 250 mm for 3500mm high (L/15 (Holger Gross, Gross Produktion AB, 2013))
h =b ≃ 450 mm for 8500mm high (L/20 (Holger Gross, Gross Produktion AB, 2013))
All the dimensions were rounded up to the nearest 50mm
The proposed roof layout is presented in Figure 3. The overall shape is a saltbox roof with the highest ridge
beam on top of upper floor sloping for 6500mm to the front (entrance) and 1950 towards the back of the
building, to the lower floor.
The structure is quite symmetrical therefore the loads distributed to its structural elements should be roughly
similar for the most of them (half for the elements constituting the perimeter)
The frames used are spanning transversally and diagonally through the structure. As the geometry used is similar
for all the frames, the dimensions will vary as the diagonal frames will span over a larger distance (15621mm).
Figure 7 Transversal Frame (12mmm span)
As per the scheme in Figure 11 the dead and live loads are initially taken by the timber rafters which spans in
between the primary beams and transferred to those. From the primary beams the loads are transferred to the
inclined beams of the frame which is further to the columns and further to the foundation
2.3.3. Lateral stability
Again, horizontal stability is accomplished by preventing angular changes between elements that are prone to
collapse. (Swedish Wood, 2016)
In this case, the connections between members are such that, under any loading, the angle of intersection between
members remains constant. Those are frequently referred to as rigid connections or rigid joints (Swedish Wood,
2016).
Figure 13 Three-pin arch conditions (Holger Gross, Gross Produktion AB, 2013)
As bracing the structure can prove quite challenging additional post and beam structure needs to be built between
the frames, with rigid connections to act like moment frames (Figure 5). The sole purpose of those is to provide
horizontal stability as the tangent beams can have their end supported on the masonry wall instead.
The trusses system proposed in the second option is able to provide lateral stability in four directions which is an
advantage while the moment frames can be easily created by connecting the top of the columns with beams, and
the connection made rigid by a stiffening member.
While using more timber the second option provides a better load transfer because of the way the trusses are
interconnecting, providing a more sound and robust design.
3. Calculations
An imposed load of 1𝑘𝑁/𝑚2 was considered. For permanent loads Structural Engineering Pocket Book (Cobb
F, 2003) suggest a load in between 0.06 and 0.08 𝑘𝑁/𝑚2 for roofing metal sheets. Therefore, considering the
additional insulation a value of 0.1 𝑘𝑁/𝑚 2 was used.
On 26.6° slope:
@600mm cts
Partial safety factors for each action: (ISE Manual, 2007) Table 3.1
𝛾𝐺 = 1.35;
𝛾𝑄 = 1.5
Partial safety factors for material: (ISE Manual, 2007) Table 3.19
Solid timber 𝛾𝑚 = 1.3
150 0.2
𝐾ℎ = ( ) or 1.3 for h<150 (ISE Manual, 2007) Table 3.20
ℎ
𝐾ℎ = 1.08
𝐾𝑠𝑦𝑠 = 1.1
Consider ULS
50 ∗ 1002
𝜎𝑚,𝑦,𝑑 = (0.043 ∗ 106 )/( ) = 0.52 𝑁⁄𝑚𝑚 2
6
1.08∗1∗1.1∗0.6∗24
𝑓𝑚,𝑦,𝑑 = = 13.16 𝑁⁄
1.3 𝑚𝑚 2
𝜎𝑚,𝑦,𝑑 ≤ 𝑓𝑚,𝑦,𝑑 OK
𝜎𝑚,𝑦,𝑑 ≤ 𝑓𝑚,𝑦,𝑑 OK
𝜏𝑑 ≤ 𝑓𝑣.𝑑. OK
𝜏𝑑 ≤ 𝑓𝑣.𝑑. OK
𝐹𝑐 = 𝐹𝑣 = 0.08 𝑘𝑁𝑚
0.08 ∗ 103
𝜎𝑐,90,𝑑 = = 0.014 𝑁⁄𝑚𝑚2
50 ∗ 100
𝑘𝑐,90 ∗ 𝑘𝑚𝑜𝑑 ∗ 𝑓𝑐,90,𝑘
𝑓𝑐,90,𝑑 =
𝛾𝑚
𝐹𝑐 = 𝐹𝑣 = 0.91 𝑘𝑁𝑚
0.91 ∗ 103
𝜎𝑐,90,𝑑 = = 0.18 𝑁⁄𝑚𝑚2
50 ∗ 100
𝑘𝑐,90 ∗ 𝑘𝑚𝑜𝑑 ∗ 𝑓𝑐,90,𝑘
𝑓𝑐,90,𝑑 =
𝛾𝑚
𝑈𝑓𝑖𝑛 = 0.3 ∗ (1 + 0.6) + 2.73 ∗ (1 + 0.3 ∗ 0.6) = 3.7 mm (EN 1995-1-1, 2014)
A preliminary sizing of h=L/15 and b=h/3 was used, rounded up to the nearest 50mm. Therefore, a section of
400 x 150mm GL24h was considered.
Loading can be taken either as point load every 600mm from the joist’s reaction load, either, for simplification,
as UDL. UDL method was preferred.
@2050mm cts
Partial safety factors for each action: (ISE Manual, 2007) Table 3.1
𝛾𝐺 = 1.35;
𝛾𝑄 = 1.5
Partial safety factors for material: (ISE Manual, 2007) Table 3.19
Glulam 𝛾𝑚 = 1.25
600 0.1
𝐾ℎ = ( ) or 1.1 for h<150 (ISE Manual, 2007) Table 3.20
ℎ
𝐾ℎ = 1.04
𝐾𝑐𝑟𝑖𝑡 – used for lateral buckling (ISE Manual, 2007) Table 3.21;
𝐾𝑐𝑟𝑖𝑡 = 0.8 Figs 3.2 – 3.4, Table 4.2
𝐾𝑠𝑦𝑠 = 1.1
Consider ULS
150 ∗ 4002
𝜎𝑚,𝑦,𝑑 = (14.9 ∗ 106 )/( ) = 3.71 𝑁⁄
6 𝑚𝑚 2
1.04∗0.8∗1.1∗0.6∗24
𝑓𝑚,𝑦,𝑑 = 1.25
= 9.6 𝑁⁄𝑚𝑚2
𝜎𝑚,𝑦,𝑑 ≤ 𝑓𝑚,𝑦,𝑑 OK
𝜏𝑑 ≤ 𝑓𝑣.𝑑. OK
𝐹𝑐 = 𝐹𝑣 = 0.8 𝑘𝑁𝑚
0.8 ∗ 103
𝜎𝑐,90,𝑑 = = 0.053 𝑁⁄
150 ∗ 100 𝑚𝑚2
𝑘𝑐,90 ∗ 𝑘𝑚𝑜𝑑 ∗ 𝑓𝑐,90,𝑘
𝑓𝑐,90,𝑑 =
𝛾𝑚
𝐹𝑐 = 𝐹𝑣 = 9.9 𝑘𝑁𝑚
9.9 ∗ 103
𝜎𝑐,90,𝑑 = = 0.66 𝑁⁄𝑚𝑚2
150 ∗ 100
𝑘𝑐,90 ∗ 𝑘𝑚𝑜𝑑 ∗ 𝑓𝑐,90,𝑘
𝑓𝑐,90,𝑑 =
𝛾𝑚
𝑈𝑓𝑖𝑛 = 0.36 ∗ (1 + 0.6) + 3.68 ∗ (1 + 0.3 ∗ 0.6) = 4.9 (EN 1995-1-1, 2014)
24 > 4.9 OK
3.3. Glulam Column
A quick analysis of the 3D model has showed that the highest axial forces are in the columns supporting the
midframe:
As the highest column there is 8.5m a preliminary sizing of h=L/20 was used, rounded up to the nearest
50mm. as a square section is preferred in the case of columns a section of 450 x 450mm GL24h was
considered.
Characteristic loads:
Partial safety factors for material: (ISE Manual, 2007) Table 3.19
Glulam 𝛾𝑚 = 1.25
Material properties:
𝐸𝑜.05 = 9400 𝑁⁄
𝑚𝑚2
ULS
Design Equation:
(ISE Manual, 2007) Cl. 5.3.1
𝜎𝑐,0,𝑑 ≤ 𝑘𝑐,𝑦 ∗ 𝑓𝑐,0,𝑑
Where:
From (ISE Manual, 2007) Table 3.22 take effective length as 1*L (ISE Manual, 2007) Table 3.22
𝐿𝑒𝑓,𝑦 = 8500𝑚𝑚
𝐿𝑒𝑓,𝑧 = 8500𝑚𝑚
𝐿𝑒𝑓,𝑦 8500
= = 28.3
ℎ 300
𝐿𝑒𝑓,𝑧 8500
= = 28.3
𝑏 300
26.3 ∗ 103
𝜎𝑐,0,𝑑 = = 0.13 𝑁⁄𝑚𝑚 2
450 ∗ 450
0.13 < 0.45 ∗ 12.7 = 5.7 OK
Case 2:
74.3 ∗ 103
𝜎𝑐,0,𝑑 = = 0.37 𝑁⁄
450 ∗ 450 𝑚𝑚 2
0.37 < 5.7 OK
Basic wind speed calculation in accordance with (BS EN 6399-2, 1997)Section 2.2.1
𝛥𝑠 = 100 site altitude above sea level in meters (BS EN 6399-2, 1997) Cl 2.2.2.2
𝑆𝑠 = 1 seasonal factor
𝑆𝑏 = 1.85 terrain and building factor - Section 2.2.3.3 - Table 4 (BS EN 6399-2, 1997) Cl
2.2.2.3 Table 4
𝑉𝑒 = 𝑉𝑠 𝑆𝑏 = 40.07 Effective wind speed
𝐻𝑒 = 𝐻𝑟
𝐿
= 2.35 external pressure coefficient - longitudinal (BS EN 6399-2, 1997) Table 5
𝐻𝑒
Longitudinal Coefficients
𝐶𝑝𝑒.𝑤𝑖𝑛𝑤𝑎𝑟𝑑.𝐿 = 0.75 BS 6399-2 - Table 5 (interpolation)
BS EN 6399-2. (1997). Loading for buildings. Code of practice for wind loads.
EN 1995-1-1. (2014). Eurocode 5: Design of timber structures. General. Common rules and rules for buildings.
Holger Gross, Gross Produktion AB. (2013, 10 17). Glulam Handbook Volume 1. Stockholm, Sweden:
Skogsindustrierna – The Swedish Forest Industries Federation.
ISE Manual. (2007). Manual for the design of timber building structures to Eurocode 5.
Swedish Wood. (2016). Design of Timber Structures - Volume 1. Stockholm: Swedish Forest Industries
Federation.
APPENDIX A
LETTER TO ARCHITECT
Further to our discussions, with the client where he expresses his desire of building a storage room under upper
floor on the indicated location, I write to you to confirm that the desired wall opening is possible and our
recommendation on how the currently proposed inner masonry wall currently separating the two floor levels can
be modified to suit client needs. The wall opening and storage room in question is indicated on Figure 16 on the
following page.
During our preliminary appraisal that wall was designed as a continuous cavity wall for the whole 20m length
3.5m height, with another 3.5m masonry piers above 1m wide (0.5m at the ends) at a distance of 4m edge to edge.
Therefore, above the desired opening there will be no masonry wall however there is a cantilevering balcony and
the timber floor joists that will need to be supported. Hence, we propose that an additional post and beam frame
to be installed at the desired location with the dimensions and connection details to be communicated at a further
date.
Additionally, the wall under consideration undertake the role of a retaining wall as the site is located on a sloped
terrain. Consequently, 3 new retaining walls need to be designed and erected during the site preparation, serving
as a boundary for the newly discussed storage room.
As those new retaining walls will have no doubt bearing role for the structure above, foundations need to be
designed also.
However, all the above changes will result in a cost increase as this will add up to the structural design cost but
also the labour cost. The construction programme will also suffer delays due to these changes.
Please let us know if the changes in the design previously mentioned are acceptable and advise your client
accordingly.
Please let us know if the solutions are then acceptable so we can proceed with the structural design.
Best Regards
Figure 16 Proposed storeroom under Upper Hall
APPENDIX B
DRAWINGS