Equipment lifetime.
Engineering documentation.
Vendor is responsible for any other parts to be done by other manufacturers.
Detailed scope of supply.
Layout of package(s) within package allowable space.
Package turndown
Sub-supplier list.
All equipment special tools required for maintenance and overhaul.
Complete client data sheets
Design, engineer, fabricate, test and supply this package.
Pre-commissioning, commissioning and start-up spare parts for pumps/engine controllers.
Separate quotation for 2 years spare parts.
P&ID's and documentation: Includes installation, operation and maintenance manual.
Inspection & Testing.
Instrumentation & Accessories:-
- The supplied instruments should be available for 10 years.
- Fiber / Nylon explosion proof cable glands to be used.
- All insulation materials shall be flame retardant, low halogen content.
- 316 St.St cable tray.
- St.St. fitting (Compression type).
- 316 St.St. instrument air tubing.
- Instrument air tubing header & branches.
- SDV's shall have 2 solenoid valves and automatic reset, SDV's valves 12" and over shall
have double acting actuator and fail false.
- All field instrument cables shall have steel wires with flame retardant.
- Solenoid valves shall be explosion proof.
- All electronic field instrumentation shall be covered with polyester for protections from
direct sun radiation.
- Control valves shall be low emission valve stem.
-
Steel Structure & Accessories: -
- Baseplates : Rigid self-supporting type.
- Ladders : Painted steel or galvanized steel.
- Platforms : Covered by galvanized grating.
- Handrails : Painted steel or galvanized steel.
- Pipe supports : Painted steel or galvanized steel.
- Walkways : Galvanized steel.
- Grating : Galvanized steel.
Hydraulic test : 1.5 times the max. working pressure for 1hr.