SECTION 1 : EXCVATION,LAYING, LOWERING, JOINTING, TESTING & COMMISSIONING OF D.I & GI PIPES
Laying and jointing of DI pipes of various diameters below ground at minimum cover of 1 m
including excavation, sand bedding, backfilling with proper compaction, disposal of surplus
materials, shoring shuttering wherever necessary, installation of bend, tees, reducers, tail pieces,
specials fixing, hydro testing with required water & commissioning complete as per technical
specification & instruction of the SSEPL representative and Engineer-In-Charge.
1.1
1. Pipe will be available within 1 km range.
2. All kind of utilities have to be identified and necessary shifting to be done with prior permission
from Construction manager for which payment will be made extra but restoration cost of utility
damaged by sub contractor to be borne by sub contarctor.
GI Pipe (Medium)
1.1.1 50 mm dia GI Pipe (Medium) Rmt 337596 55.00
1.1.2 65 mm dia GI Pipe (Medium) Rmt 60010 60.00
1.1.3 80 mm dia GI Pipe (Medium) Rmt 52575 65.00
DI Pipe Class K-7 \ K-9
1.1.4 100 mm dia DI Pipe Class K-7 Rmt 81845 70.00
1.1.5 125 mm dia DI Pipe Class K-7 \ K-9 Rmt 38598 75.00
1.1.6 150 mm dia DI pipe Class K-7 \ K-9 Rmt 90057 85.00
1.1.7 200 mm dia DI pipe Class K-7 \ K-9 Rmt 92096 100.00
1.1.8 250 mm dia DI pipe Class K-7 \ K-9 Rmt 47339 115.00
1.1.9 300 mm dia DI pipe Class K-7 \ K-9 Rmt 24606 130.00
1.1..10 350 mm dia DI pipe Class K-7 \ K-9 Rmt 14200 140.00
1.1.11 400 mm dia DI pipe Class K-9 Rmt 3286 160.00
1.1.12 500 mm dia DI pipe Class K-9 Rmt 12853 200.00