Professional Documents
Culture Documents
In this research, the cost of energy (C.O.E.) per kW was the distinguishing
feature considered among the turbines studied.
Here the numerator stands for annual total cost and denominator for energy
load.
2
Towers: These are an important part of the wind turbine cost (up to one
quarter), but are a relatively mature component. Most are rolled steel, with
costs being driven by steel prices. However, increased competition, the
integration of lightweight materials and the more distributed location of
manufacturers that will be possible as markets expand means tower costs may
come down, perhaps by 15% to 20% by 2030.
Blades: Wind turbine rotor blades can account for one-fifth of turbine costs.
The key driver behind blade design evolution is weight minimisation as this
reduces loads and helps improve efficiency. Using more carbon fibre in blades,
as well as improving the design of blades (with production efficiency and
aerodynamic efficiency in mind) can help reduce weight and costs, although
the high cost of carbon fibre is a problem. Cost reductions of 10% to 20%
could be possible by 2021.
Gearboxes: Typically represent 13% to 15% of wind turbine costs The R&D
focus for gearboxes is to improve reliability and reduce costs. Vertical
integration of gearbox manufacturing by wind turbine suppliers should help
reduce costs. Cost reductions may also stem from the increasing share of
gearless drive generators using permanent magnet synchronous motors.
Overall, cost reductions could reach 15% by 2021.
2) Development Cost:
Blade development costs were calculated for each of the three blade sizes. It
was assumed that the costs for engineering design and documentation were
essentially constant with the blade size if current fabrication materials and
methods were used. This simplifying assumption is based upon the need for
similar types of analyses and design documents regardless of the blade scale.
The cost associated with the fabrication of tooling and prototypes was
estimated by assuming the cost to be dependent upon the blade scale, as is the
cost of static, fatigue, and operational field testing.
3) Facilities Cost:
The annual blade production capacity and the plant conceptual design were
used to develop tooling, equipment, and facilities cost estimates.
4) Transportation Cost:
Transportation of large wind turbine blades can be difficult and expensive.
Careful analysis of cost required is necessary.
6
● Insurance
● Land rent
● Service, repair and spare parts
● Administrative tasks
● Power (it does take some electricity to run)
● Miscellaneous
8
Wind turbines cost more the bigger they get, but they produce
more electricity with larger nacelles and turbine blades.
In 2019, it was reported that the average rotor diameter had risen to
129 meters.
REFERENCES:
https://jrenewables.springeropen.com/articles/10.1186/s40807-020-00062-
7
https://publications.lib.chalmers.se/records/fulltext/179861/179861.pdf
https://weatherguardwind.com/how-much-does-wind-turbine-cost-worth-it/
https://www.irena.org/-/media/Files/IRENA/Agency/Publication/2012/RE_
Technologies_Cost_Analysis-WIND_POWER.pdf
https://www.nrel.gov/docs/fy07osti/40566.pdf
https://windpower.sandia.gov/other/031428.pdf