B Septic Tank
1 Excavation Cum 1 5.500 3.500 1.500 28.875 400 11550.00
2 PCC Cum 1 4.600 0.250 0.100 0.115 4500 517.50
3 RCC Slab (150 mm thk) Cum 1 4.500 1.960 0.150 1.323 6500 8599.50
4 Brickwork Cum 1 5.400 2.750 0.490 7.277 5800 42203.70
5 Plastering with neat finish Sqm 1 10.000 1.500 15.000 300 4500.00
Total (B) 67370.70