The Richard J Midulla Generating Station

Case study: Combined-cycle control systems Credit: Siemens

Empowering
operators for
efficient operations
Many of the functions that have traditionally been performed at an engineering or
administrative level are now being handled directly by operators at a power plant
where a new control system is expected to improve plant performance, reduce
forced outages and extend equipment life, write Bill Conley and Galen George

M
aximizing power plant businesses in 42 Florida counties rely on the ability to recognize and mitigate potential
performance and Seminole Member cooperatives for electricity. reliability issues. MGS is now beginning to see
reliability is every plant One of Seminole’s primary resources includes the benefits of using a modern control system
owner’s aspiration. the Richard J Midulla Generating Station with the appropriate tools, in terms of overall
Experienced plant (MGS). plant performance.
personnel know that Located on the Hardee/Polk County line in As we all know, the life of a control room
a power plant’s performance is determined central Florida, MGS is an 810 MW facility that operator can be stressful. In the daily
largely by the performance of the operators. uses natural gas as its primary fuel. The facility business of power plant operations, they are
An intuitive control system with the appropriate consists of a combined-cycle power plant responsible for monitoring thousands of data
diagnostic capabilities provides the operator and five simple-cycle, twin pack, peaking points and controlling the plant based on
with the tools necessary to be successful. combustion turbines. their interpretation of this data.
At Seminole Electric Cooperatives Midulla In 2006, MGS was the first installation to In addition, operators must also record,
Generating Station, employees are continually upgrade its digital plant control system from report and coordinate all of the data
looking for ways to optimize plant performance TXP to the Siemens SPPA-T3000 system as part necessary to manage the plant as efficiently
and reliability. of an overall programme to improve plant as possible. Armed with this massive amount
Seminole Electric Cooperative is one performance and reliability. of information, operators have to decipher
of the largest not-for-profit generation and More recently, MGS and Siemens added and determine what actions, if any, to take.
transmission cooperatives in the US. Its mission an updated, highly customizable new It continues to be critical to support them
is to provide reliable, competitively priced, human machine interface (HMI) to their plant with the right tools, targeted information and
wholesale electric power to its nine-member distributed control system (DCS). The new guidance for sound operation.
distribution electric cooperatives. HMI empowers operators to interact more As part of the control system upgrade,
Approximately 1.6 million people and effectively within the plant’s DCS, giving them MGS took a new approach, delving into

Reprinted with revisions to format, from the NOVEMBER 2016 edition of POWER ENGINEERING INTERNATIONAL
Copyright 2016 by PennWell Corporation
Case study: Combined-cycle control systems

the use of applications focused on not only the background, which makes it much more are now inherent parts of the new HMI.
making the information readily available, user-friendly and accessible when compared These two new alarm classes provide
but by also providing tools that enable them to an add-on system. proactive warnings before a limit is reached.
to focus more on effective proactive plant The integrated alarm management They do this by analyzing the data at the
operation rather than putting out fires. The
SPPA-T3000 Cue plant control system enables
this approach by helping plant operators
ensure the highest reliability and availability in
the most intuitive manner possible.
With the upgraded DCS, the visual displays
provide the most relevant key performance
indicators (KPIs) and sophisticated alarm
management tools at the top of each screen.
With significantly improved visual reference
and organized plant alarm statistical data,
operators are now able to quickly and
effectively review overall plant and equipment
status.
MGS operators have also made great
use of the new system’s many configurable
alarm models. They can easily customize this The advanced HMI
Credit: Siemens
application, including how system pages
are set up, as well as adding and removing
elements.
To provide the operators with tools that analysis (AMA) software provides operators system and equipment level rather than
make their daily activities more effective, MGS with both specific and statistical data for each relying on a single instrument.
chose to implement shift logs and turnovers alarm condition, providing the information This provides an early indication of
within the upgraded DCS. By integrating needed to continuously improve alarm conditions that are likely to lead to a trip. In
the shift-logs into the SPPA-T3000, the logs functionality. Over time, heavy volumes of addition, with a click of the mouse, a display
automatically populate with events, alarms nuisance alarms can distract operators. opens with the relevant control windows,
and other process data, without the need for All distractions – alarms, phone calls, radio trends, detailed descriptions of the detected
manual entry. communication and more – add up over time, issue and instructions the operator can use to
In addition, MGS decided it would integrate and tend to reduce focus on efficient and avoid reaching the point where a plant trip is
the non-DCS type activities into the electronic reliable operation of the plant. required.
logbook. It is collaborating with Siemens to The AMA system application provides In addition to the new alarms, the system
provide a customized format to easily enter statistical analysis for alarm frequency, type includes integrated component diagnostic
these non-DCS events into the electronic log. and distribution. MGS operators are able to modelling software that continuously runs in
This will improve the effectiveness of shift-to-shift easily identify opportunities for improvement the background. Once a model is built, the
communications while improving consistency and provide the needed information to system continuously monitors performance
and accuracy. initiate the management of change process. of critical plant equipment and compares
Due to the ease and intuitiveness of the Ultimately, this provides opportunities to reduce it to the expected performance based on
upgraded controls, the operators at MGS are the number of ‘nuisance’or unnecessary empirical limits and learned behaviour.
quickly learning how to use the new features alarms, without risking equipment damage. As the model tracks changes within the
after only a few days of informal on-site training. equipment limits, the potential equipment
Integrating diagnostic cues failure or performance problem is alarmed
Reducing distractions Working with Siemens as the pilot for the and again, with a click of the mouse, a display
One of the best ways to improve the new SPPA-T3000 Cue system, MGS was opens with the relevant control windows,
effectiveness of operators during transient able to take alarm customization to the trends, detailed descriptions of the detected
conditions is by minimizing unnecessary next level. In addition to the standard alarm issue and instructions the operator can use to
alarms that tend to distract and desensitize. enhancements, the new HMI provides the avoid reaching the point where plant reliability
Alarm management systems in plants have ability for operators to create new alarm is impacted.
historically been standalone systems. However, classes specifically designed to enhance their As part of the pilot project, Siemens
with the new operating system, this function ability to proactively manage plant upsets. built custom models for much of the major
is fully integrated into the plant DCS, with no With Siemens’ help, MGS created two new equipment in the plant, such as the boiler
add-ons required.The tool continuously runs in alarm classes, Trip Warning and Trip Stop, that feed pumps. The new system also allows
Case study: Combined-cycle control systems

plant personnel to build their own customized engineering or administrative level are now maintenance.
models that work specifically for unique issues being handled directly by operators. The new MGS has been able to increase operator
that may arise within the plant. SPPA-T3000 Cue system upgrade now makes effectiveness and efficiency through
Using these diagnostics engineering tools, it easy for even the most traditional operators technology. Its operators are now empowered
MGS was able to add a custom model for a to feel comfortable using the intuitive tools to do more than they have ever been able to
unique plant situation. Recently they had an digging through symptoms and diagnosing do before, with much less effort and stress. And
issue with algae plugging their closed cycle problems. with the predictability of the new upgraded
cooling heat exchanger, requiring immediate An added value to this upgrade is that control system, MGS operators are able to
corrective actions. After the heat exchanger the system allows plants to tap into their perform tasks that were – up until now – out
was returned to service, an operator own internal talent for a more customized of their hands.
concerned that all the algae had not been approach that empowers operators to The ongoing goal at MGS is continuous
removed built his own custom model for the proactively run the plant as opposed to improvement and, from a performance
heat exchanger. Using this model, he was keeping the plant running. standpoint, to run as economically as possible.
able to easily confirm that the heat exchanger The more economically the plant runs, the
was operating at optimal performance levels. Measuring success more value it can provide to its customers. If
As a result, they now have a model that will When measuring success, MGS looks the newly-upgraded operating system can
also alert operations of future algae problems at specific KPIs aimed towards safety, prevent one failure, it will more than pay for
long before they become an issue. environmental compliance, reliability and itself. The plant is predicting that its newly-
While alarm management, electronic efficiency. upgraded control system will enable operators
logs and equipment modelling technologies By offering tools that provide operators to improve plant performance, reduce forced
already exist, by integrating them into one with an easy means for truly understanding outages and extend the life of the equipment.
control system, they have never been more problems with the plant and process, rather
user-friendly or readily available to the operator than just addressing symptoms, operators Bill Conley is Manager of Operations at
‘on demand’. The tools to effectively operate can focus on maintaining safe, reliable and Richard J Midulla Generating Station. Galen
and monitor the plant are now in one place, efficient plant operations. George is Manager of Business Development
and there when the operator needs them. Also, by predicting issues before they cause & Marketing at Siemens Power & Gas Division,
Many of the functions that have damage, MGS can minimize repair time Instrumentation & Electric.
traditionally been performed at an and cost of equipment through scheduled