Professional Documents
Culture Documents
E-mail: brtc666@163.com
Apr.10th,2018
Main Contents
1.1 History:
China is one of the countries that use biogas
early in the world.
Mr.Luo Guorui built a biogas digester called
“Chinese Guorui Natural Gas Store” in 1920,
which was the first Hydraulic Digester in China.
Guorui Natural Gas Store
1.2 Government’s attention
On April 11.1958,
Chairman Mao
Zedong was
watching the
demonstration of
biogas stove in
Wuhan City,Hubei
Province.
On July 10.1980,
Vice Chairman
Deng Xiaoping was
supervising the rural
household biogas
in Chengdu City,
Sichuan Province.
On March 15.1991, Chairman Jiang Zemin Visited
local household and looked the application of biogas
in Xiangtan County of Hunan Province.
President Hu Jintao
Visited the
application of local
household biogas
in Henan Province
in 2003.
Prime Minister
Wen Jiabao
gave lecture
concerning
development of
biogas
technology in
rural areas.
2. The development of biogas
digester in China rural areas
6—Biogas guide:
The gas guide
is made of
copper, the
diameter is
usually 8-10
mm.
Structure of hydraulic biogas digester
7—Outlet pipe:
Outlet pipe is
round shaped. It
is installed aslant
at middle or
lower part of the
digester.
(It’s similar with
inlet pipe.)
Structure of hydraulic biogas digester
8—Hydraulic chamber :
It’s laid of brick,
the function of
hydraulic
chamber is to
store the liquid
(digested
effluent) from
digester .
Structure of hydraulic biogas digester
9—Overflow pipe:
The overflow pipe is
located at the center
between hydraulic
chamber and storage
tank, the diameter is
10-15cm. The
overflow pipe must
be 20cm underground
at least.
Structure of hydraulic biogas digester
10—Storage tank:
The storage tank is
a tank which can
store the
digested effluent
from hydraulic
chamber , the
volume is about
1-2 cubic meters.
3.3 Principle of hydraulic biogas digester
When a biogas
digester produce
biogas, the gas
press the liquid
into hydraulic
chamber, making
liquid level higher.
3.3 Principle of hydraulic biogas digester
On the contrary,
when biogas is used,
liquid get back into the
digester from the
hydraulic chamber, so
the liquid level drops.
In this way, internal
and external pressure is
balanced.
That’s why we call it
hydraulic biogas
digester.
4. Advantages of hydraulic biogas digester
R02 f1
1 ,
2 f1 2
R02 f2
2 ,
2 f2 2
6. Calculation (1)
V3 R02 H 0
6. Calculation (1)
V=V1+ V2+ V3
= (0.0827+0.0501+0.3142) D03
= 0.4470 0
3
D
6. Calculation (2)
If we have determined the volume of
a biogas digester that will be built, its
diameter and other geometric
parameters is gotten as:
V
D0= 3
0.447
=1.3078 3 V
Example 1:
Assuming a biogas digester with volume of 10 m3
is to be built, its diameter is:
D0=1.3078×2.155
=2.818(m)
Volume of each part is:
V1= 0.0827×2.8183 =1.85 m3
V2= 0.0501×2.8183 =1.12 m3
V3= 0.3142×2.8183 =7.03 m3
Other geometric parameters:
From the above, we get:
1 1
f1= D0 2.818 0.564(m)
5 5
1 1
f2= D0 2.818 0.352(m)
8 8
1 1
H0= 2.5 D0 2.5 2.818 1.127(m)
1 1
R0= D0 2.818 1.409(m)
2 2
D0 2 1
( ) D0
R02 f1 2 5 58
ρ1= 2 f 2 1 2 80 D0
1 2 D0
5
= 0.725 D0
= 0.725×2.818
= 2.043 (m)
2
R f 2 17
ρ2= 0
D0
2 f2 2 16
=1.0625D0=1.0625×2.818
=2.994 (m)
6. Calculation (3)
F=F1+ F2+ F3
=2πρ1f1+2πρ2f2+2πR0H0
=2π(ρ1f1+ρ2f2+ R0H0)
Exercise1:
Assuming a biogas digester with volume of 8
m3 is to be built, its geometric parameters are:
D0=? H0 =? f1 =? f2 =?
R0 =?
ρ1=? ρ2=?
Volume of each part is:
V1= ? m3
V2= ? m3
V3= ? m3
Table for dimension of digester
6. Calculation (4)
Calculation for volume of hydraulic chamber
(outlet chamber) :
Volume of hydraulic chamber is equal to gas
production for a half day, i.e.:
1
Vh=V×rv×
2
Where,
Vh= Volume of hydraulic chamber (m3)
V = Volume of biogas digester (m3)
rv = Gas production rate (m3/m3/d)
Example 2:
Calculation for volume of hydraulic chamber
If :
V = 8 m3, rv = 0.35 m3/m3/d,
then
1
Vh= 8×0.35× = 1.40 m3
2
Namely, volume of hydraulic chamber
is 1.40 m3.
6. Calculation (5)
Determination of digester volume :
If we have known gas production rate, raw
material quantity, biogas consumption per
person per day and number of family members,
we can calculate the volume of biogas digester
by the following formula:
Average biogas consumption per person×number of persons
V= Gas production rate
Example 3:
Calculation for volume of digester
Assuming biogas consumption is 0.3m3/per
person per day, number of family members is
5 and gas production rate is 0.25m3/ m3/d.
Then :
0.30 5
V=
0.25
= 6 (m3)
7. Summary of design parameters
1. Maximum working
pressure in digester
is 7840 Pa (≤800
mm water gauge) ;
2. Maximum working
volume is 90% of
gross digester
volume;
7. Summary of design parameters
3. Volume of
hydraulic chamber
is half biogas
production per day;
4. Thickness of soil
filled on digester
top should not be
less than 250 mm;
7. Summary of design parameters
Slope
No. Description (Height: Remarks
width)
1 Sandy soil 1:1 This is suitable for the
Sub-sandy soil digester construction
2 1: 0.67 with good soil
3 Sub-stick clay 1: 0.50 conditions of
Clay humidity, hydrology
4 1: 0.33
and geology, and
5 Soil with gravels or cobbles 1: 0.67 without groundwater,
Dry loess no supporters for
6 1: 0.25
digester base pit.
12.2 The central rod and radius gauges
It is important to set a
rod at the center for the
cylinder digester
construction to keep
digester wall circular and
vertical regularly. Link the
two couples of diagonal
stakes at four corners.
Hanging a tag at the point
of intersection to determine
the center of the digester.
12.2 The central rod and radius gauges
Stand a rod at the
center, and then fasten
the upper part of the rod
with threads as shown
in Figure a. The central
rod should not be
moved after it
positioned during
construction.
12.3 The central rod and radius gauges
The circular shape of the
digester is controlled by the
radius gauges. Use them to
check every block of the
digester wall.
After complete one layer
of laying work, move the
radius gauges up with a
height as the thickness of a
layer. The gauges must be
always kept horizontally.
12.4 Construction of the digester dome
In order to ensure
geometric size of the dome,
usually we use inflexible wire
as radius gauge for laying
dome bricks.
If the center of the dome
curvature is lower than the
digester bottom, a small pit is
dug in advance as shown in
Figure d. The pit can be filled
after the dome is completed.
12.5 Safety during construction
Collapse prevention: During digging the pit
of digester, the wall should be of proper slope
depending on the soil quality.
Some measurements must be taken to fix
the poor quality soil. Heavy article is not
allowed to put near digester side.
Water must be drained during rainy season.
12.5 Safety during construction
During dome construction without
mould, use flat stones to insert into gaps
between bricks tightly. No people are
allowed to stand on the dome until the
soil become hardened.
Heavy articles are not allowed to put
on newly built dome to avoid collapse
due to over load.
Table 2.1- Procedure of painting the sealing
layers on digester internal surface
Layers to paint Procedure of painting Remarks
1. 1-2 times of pure cement Be suitable for
mortar movable plug and
2. 1:3 cement mortar (5 mm) internal surface of
3. Once pure cement mortar biogas digester built
Seven layers
4. Once 1:2.5 cement mortar (5 with concrete
painting
mm) prefabricated
5. Once pure cement mortar blocks, common
6. 1:2.5 cement mortar (5 mm) bricks or stone
7. Surface treatment blocks.
Table 2.2
Be suitable for
1. 1-2 times of pure cement internal surface of
mortar gas space of concrete
2. 1:3 cement mortar (5 mm) digesters cast at site,
Five layers painting 3. Once pure cement mortar and digestion
4. Once 1:2.5 cement mortar chamber of digesters
(5 mm) built with concrete
5. Surface treatment blocks, bricks or
stone blocks.
Table 2.3
Layers
Procedure of painting Remarks
to paint
1. 1-2 times of pure cement Be suitable for internal surface of
Four mortar hydraulic chamber and inlet of
layers 2. 1:3 cement mortar (5 mm) digesters built with concrete
painting 3. 1:2.5 cement mortar (5 mm) prefabricated blocks, common
4. 3 times of pure cement mortar bricks or stone blocks.
Be suitable for internal surface of
Three 1. 1:3 cement mortar (5 mm) hydraulic chamber, inlet and
layers 2. 1:2.5 cement mortar (5 mm) water sealing chamber above
painting 3. 3 times of pure cement mortar movable cover of concrete
digester cast at site.
Table 2.4
Layers to
Procedure of painting Remarks
paint
Be suitable for internal and
Single
external surface treatment of
layer Pure cement mortar 1-3 times
concrete feeding and outlet
painting
pipes
Any one of the following three methods of inner digester
surface treatment for gas space can be selected:
Treating
1. Painting pure cement mortar for three to five times
inner
2. Painting sodium silicate and then pure cement mortar for
surface
totally three to five times
3. Painting melted paraffin three times